GOLIAD POST OAK RD (0916-26-023)
Items: 45
County: GOLIAD
Length: 0.0000 MILES
Highway: POST OAK RD
District: CORPUS CHRISTI
Control Number: 0916-26-023
DBE Goal: 0.0%
Project: BR 2024(964)
Guaranty: $24,000.00
Time: 147 WORKING DAYS
Engineer's Estimate: $1,200,909.50
Date: 05/06/2026 (5 weeks ago) Changed
Contract Number: 5263226
Type: BRIDGE REPLACEMENT
Project ID: A00136586
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES ON POST OAK RD AT MANAHUILLA CREEK BRIDGE.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NICK NOVOSAD
GOLIAD POST OAK RD (0916-26-023)
Project Name: N/A
Project: BR 2024(964)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: STR. (AA0145001) POST OAK RD
Limits To: APPROX. .30 MI E OF FM 1726
Project Description: REPLACE BRIDGE AND APPROACHES ON POST OAK RD AT MANAHUILLA CREEK BRIDGE.
Bidders (13)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,200,909.50 | |||
| $1,135,007.50 |
-5.49%
-$65,902.00
|
|||
| $1,138,135.00 |
-5.23%
-$62,774.50
|
0.28%
$3,127.50
|
||
| $1,149,885.00 |
-4.25%
-$51,024.50
|
1.31%
$14,877.50
|
-1.03%
-$11,750.00
|
|
| $1,171,268.05 |
-2.47%
-$29,641.45
|
3.19%
$36,260.55
|
-1.86%
-$21,383.05
|
|
| $1,194,888.00 |
-0.5%
-$6,021.50
|
5.28%
$59,880.50
|
-2.02%
-$23,619.95
|
|
| $1,280,548.00 |
6.63%
$79,638.50
|
12.82%
$145,540.50
|
-7.17%
-$85,660.00
|
|
| $1,290,348.57 |
7.45%
$89,439.07
|
13.69%
$155,341.07
|
-0.77%
-$9,800.57
|
|
| $1,334,440.40 |
11.12%
$133,530.90
|
17.57%
$199,432.90
|
-3.42%
-$44,091.83
|
|
| $1,450,414.82 |
20.78%
$249,505.32
|
27.79%
$315,407.32
|
-8.69%
-$115,974.42
|
|
| $1,474,491.00 |
22.78%
$273,581.50
|
29.91%
$339,483.50
|
-1.66%
-$24,076.18
|
|
| $1,499,416.50 |
24.86%
$298,507.00
|
32.11%
$364,409.00
|
-1.69%
-$24,925.50
|
|
| $1,696,578.00 |
41.27%
$495,668.50
|
49.48%
$561,570.50
|
-13.15%
-$197,161.50
|
|
| $1,974,928.19 |
64.45%
$774,018.69
|
74%
$839,920.69
|
-16.41%
-$278,350.19
|
E
Engineer's Estimate
$1,200,909.50
1
Awarded
$1,135,007.50
Over/Under Est:
-5.49%
-$65,902.00
$1,138,135.00
Over/Under Est:
-5.23%
-$62,774.50
Amt Left:
0.28%
$3,127.50
$1,149,885.00
Over/Under Est:
-4.25%
-$51,024.50
Amt Left:
1.31%
$14,877.50
Delta:
-1.03%
-$11,750.00
$1,171,268.05
Over/Under Est:
-2.47%
-$29,641.45
Amt Left:
3.19%
$36,260.55
Delta:
-1.86%
-$21,383.05
$1,194,888.00
Over/Under Est:
-0.5%
-$6,021.50
Amt Left:
5.28%
$59,880.50
Delta:
-2.02%
-$23,619.95
$1,280,548.00
Over/Under Est:
6.63%
$79,638.50
Amt Left:
12.82%
$145,540.50
Delta:
-7.17%
-$85,660.00
$1,290,348.57
Over/Under Est:
7.45%
$89,439.07
Amt Left:
13.69%
$155,341.07
Delta:
-0.77%
-$9,800.57
$1,334,440.40
Over/Under Est:
11.12%
$133,530.90
Amt Left:
17.57%
$199,432.90
Delta:
-3.42%
-$44,091.83
$1,450,414.82
Over/Under Est:
20.78%
$249,505.32
Amt Left:
27.79%
$315,407.32
Delta:
-8.69%
-$115,974.42
$1,474,491.00
Over/Under Est:
22.78%
$273,581.50
Amt Left:
29.91%
$339,483.50
Delta:
-1.66%
-$24,076.18
$1,499,416.50
Over/Under Est:
24.86%
$298,507.00
Amt Left:
32.11%
$364,409.00
Delta:
-1.69%
-$24,925.50
$1,696,578.00
Over/Under Est:
41.27%
$495,668.50
Amt Left:
49.48%
$561,570.50
Delta:
-13.15%
-$197,161.50
$1,974,928.19
Over/Under Est:
64.45%
$774,018.69
Amt Left:
74%
$839,920.69
Delta:
-16.41%
-$278,350.19
Bid Items & Bid Tabulations
45
Total
0 of 45
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,049.05 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,384.50 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,000.00 |
| Total: | $10,433.55 |