GOLIAD US 183 (0155-03-037)

Items: 87

County: GOLIAD
Length: N/A
Highway: US 183
District: CORPUS CHRISTI
Control Number: 0155-03-037
DBE Goal: N/A
Project: BR 1502(573)
Guaranty: N/A
Time: 254 WORKING DAYS
Engineer's Estimate: $2,949,650.25
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$2,949,650.25
1
$3,587,103.15
Over/Under Est: 21.61% $637,452.90
Over/Under Est: 31.7% $934,918.78
Amt Left: 8.29% $297,465.88
Over/Under Est: 56.84% $1,676,618.09
Amt Left: 28.97% $1,039,165.19
Delta: -19.09% -$741,699.31

Bid Items & Bid Tabulations

87 Total 0 of 87
GOLIAD  |  US 183  |  CORPUS CHRISTI  |  0155-03-037  |  01/09/2019  |  $2,949,650.25  |  BR 1502(573)  |  BRIDGE REPL  |  254 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
ANGEL BROTHERS HOLDINGS CORP.
HUNTER INDUSTRIES, LTD.
PREPARING ROW
STA 17.200 $1,500.000 $5,000.000 $11,500.000 $5,565.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 6,154.000 $5.000 $2.500 $3.000 $13.320
EXCAVATION (ROADWAY)
CY 3,801.000 $5.000 $12.000 $18.000 $39.420
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,265.000 $7.000 $18.000 $22.000 $39.420
FURNISHING AND PLACING TOPSOIL (4")
SY 10,179.000 $0.500 $4.000 $1.500 $2.760
BLOCK SODDING
SY 1,332.000 $4.000 $4.300 $4.750 $5.940
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 8,847.000 $0.250 $0.510 $0.250 $0.330
BROADCAST SEED (TEMP) (WARM)
SY 4,424.000 $0.150 $0.510 $0.300 $0.400
BROADCAST SEED (TEMP) (COOL)
SY 4,423.000 $0.150 $0.510 $0.300 $0.400
VEGETATIVE WATERING
MG 320.000 $15.000 $20.000 $20.000 $36.630
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 2,171.000 $60.000 $84.000 $75.000 $97.010
CEMENT
TON 143.000 $150.000 $165.000 $155.000 $183.750
CEMENT TREAT (SUBGRADE) (8")
SY 6,510.000 $2.500 $2.500 $2.500 $4.560
CEMENT TREAT (NEW BASE)(12")
SY 6,510.000 $4.000 $2.500 $2.500 $4.560
PRIME COAT (MC-30)
GAL 1,237.000 $3.500 $5.370 $5.500 $8.760
ASPH (MULTI OPTION)
GAL 5,249.000 $3.000 $4.030 $4.000 $9.900
AGGR (MULTI OPTION)
CY 122.000 $65.000 $145.120 $275.000 $216.810
CEM STABIL BKFL
CY 40.000 $80.000 $150.000 $250.000 $180.000
TEMPORARY SPL SHORING
SF 4,815.000 $10.000 $17.500 $32.000 $50.000
DRILL SHAFT (36 IN)
LF 1,218.000 $175.000 $160.000 $225.000 $248.040
CL C CONC (ABUT)
CY 44.000 $750.000 $1,100.000 $1,400.000 $1,000.000
CL C CONC (CAP)
CY 99.500 $1,000.000 $1,200.000 $1,200.000 $900.000
CL C CONC (COLUMN)
CY 71.000 $750.000 $1,100.000 $830.000 $900.000
REINF CONC SLAB
SF 23,920.000 $20.000 $16.000 $17.000 $20.000
RETAINING WALL (MSE)
SF 7,709.000 $40.000 $75.000 $61.000 $40.000
PRESTR CONC GIRDER (TX40)
LF 3,102.000 $140.000 $135.000 $135.500 $150.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 156.000 $100.000 $150.000 $175.000 $175.000
RIPRAP (MOW STRIP)(4 IN)
CY 40.800 $450.000 $425.000 $520.000 $500.000
RAIL (TY T223)
LF 1,956.600 $100.000 $65.000 $85.000 $135.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 135.000 $75.000 $65.000 $95.000 $80.000
GABIONS (3' X 3')(GALV)
CY 232.000 $200.000 $185.000 $225.000 $195.000
RC PIPE (CL III)(18 IN)
LF 40.000 $60.000 $60.000 $140.000 $100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,300.000 $1,250.000 $2,400.000 $1,800.000
REMOV STR (HEADWALL)
EA 2.000 $1,000.000 $1,500.000 $1,200.000 $250.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $50,000.000 $120,000.000 $102,000.000 $400,000.000
REMOVE STR (GABION)
LF 696.000 $60.000 $20.000 $60.000 $10.000
MOBILIZATION
LS 1.000 $200,000.000 $300,000.000 $380,000.000 $456,999.650
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $3,000.000 $4,850.000 $1,600.000 $1,835.260
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 200.000 $30.000 $66.000 $35.000 $29.300
ROCK FILTER DAMS (REMOVE)
LF 200.000 $10.000 $11.000 $18.000 $8.300
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 54.000 $20.000 $20.350 $45.000 $18.500
CONSTRUCTION EXITS (REMOVE)
SY 54.000 $6.000 $11.000 $20.000 $6.700
BACKHOE WORK (EROSION & SEDMT CONT)
HR 20.000 $75.000 $27.500 $65.000 $102.600
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,659.000 $2.500 $3.570 $3.000 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,659.000 $1.000 $1.100 $0.750 $0.500
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 1,860.000 $25.000 $18.000 $22.000 $25.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 1,860.000 $4.500 $10.000 $4.000 $25.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 1,860.000 $10.000 $15.000 $11.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $2,100.000 $2,100.000 $2,193.000
REMOVE METAL BEAM GUARD FENCE
LF 450.000 $4.000 $3.000 $3.250 $3.100
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,700.000 $2,600.000 $2,800.000 $2,790.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $350.000 $400.000 $275.000 $275.000
CRASH CUSH ATTEN (INSTL)
EA 2.000 $15,000.000 $7,800.000 $5,500.000 $9,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,300.000 $900.000 $850.000 $2,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $900.000 $600.000 $500.000 $850.000
WIRE FENCE (TY A)
LF 200.000 $10.000 $15.000 $19.000 $20.000
TEMP RD IL (RD IL ASM)
MO 16.000 $1,500.000 $4,500.000 $6,800.000 $6,700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $530.000 $250.000 $567.000 $567.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $600.000 $250.000 $771.000 $771.000
REMOVE SM RD SN SUP&AM
EA 5.000 $60.000 $50.000 $125.000 $125.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 4.000 $60.000 $25.000 $45.000 $45.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 24.000 $25.000 $22.000 $13.000 $13.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 4.000 $60.000 $150.000 $45.000 $45.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 20.000 $10.000 $30.000 $20.000 $20.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 16,607.000 $0.600 $0.600 $0.550 $0.550
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 141.000 $1.000 $1.650 $1.500 $1.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 18.000 $10.000 $6.600 $6.000 $6.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 10,570.000 $0.600 $0.660 $0.600 $0.600
WK ZN PAV MRK REMOV (Y)24"(SLD)
LF 11.000 $5.000 $6.600 $6.000 $6.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,610.000 $0.600 $0.770 $0.700 $0.700
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 16.000 $5.000 $5.500 $5.000 $5.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 175.000 $5.000 $4.400 $4.000 $4.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 12,899.000 $0.150 $0.240 $0.220 $0.220
REFL PAV MRK TY II (W) 8" (SLD)
LF 3,610.000 $0.250 $0.440 $0.400 $0.400
REFL PAV MRK TY II (W) 24" (SLD)
LF 16.000 $2.500 $2.750 $2.500 $2.500
REFL PAV MRK TY II (Y) 4" (SLD)
LF 12,796.000 $0.150 $0.270 $0.250 $0.250
REFL PAV MRK TY II (Y) 24" (SLD)
LF 175.000 $2.500 $2.200 $2.000 $2.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 12,899.000 $0.250 $0.410 $0.380 $0.380
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 12,796.000 $0.250 $0.410 $0.380 $0.380
REFL PAV MRKR TY II-A-A
EA 302.000 $2.500 $3.850 $3.500 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 21,997.000 $0.750 $1.000 $0.600 $0.750
ELIM EXT PAV MRK & MRKS (8")
LF 464.000 $0.750 $1.000 $2.000 $1.000
TEMP TRAF SIGNALS
EA 2.000 $30,000.000 $16,000.000 $35,000.000 $38,140.500
GEOGRID BASE REINFORCEMENT (TY I)
SY 6,510.000 $1.000 $2.000 $2.400 $4.380
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 245.000 $55.000 $100.000 $115.000 $125.000
TMA (STATIONARY)
EA 2.000 $5,000.000 $25,000.000 $14,000.000 $7,000.000
TMA (MOBILE OPERATION)
HR 50.000 $40.000 $200.000 $40.000 $275.000
Totals: $2,949,650.250 $3,587,103.150 $3,884,569.030 $4,626,268.340