Bid Cobra

GILLESPIE US 290 (0113-02-063)

Items: 115

County: GILLESPIE
Length: N/A
Highway: US 290
District: AUSTIN
Control Number: 0113-02-063
DBE Goal: N/A
Project: C 113-2-63
Guaranty: N/A
Time: 219 WORKING DAYS
Engineer's Estimate: $11,488,921.20
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$11,488,921.20
$12,041,546.04
Over/Under Est: 4.81% $552,624.84
Over/Under Est: 8.16% $937,644.90
Amt Left: 3.2% $385,020.06
$12,612,540.30
Over/Under Est: 9.78% $1,123,619.10
Amt Left: 4.74% $570,994.26
Delta: -1.50% -$185,974.20
Over/Under Est: 15.69% $1,802,517.52
Amt Left: 10.38% $1,249,892.68
Delta: -5.38% -$678,898.42
Subcontractor Percentage Amount
CAPITAL EXCAVATION COMPANY 0.00% $0.00
CONTRACTORS ASPHALT, LP 0.00% $0.00
D. I. J. CONSTRUCTION, INC. 0.00% $0.00
EGGEMEYER LAND CLEARING, LLC 0.00% $0.00
FLASHER EQUIPMENT COMPANY 0.00% $0.00
HARDROCK UTILITY CONTRACTORS, L.L.C. 0.00% $0.00
HARDY HOLE DRILLING 0.00% $0.00
LINDAMOOD, INC. 0.00% $0.00
LONE STAR EROSION CONTROL 0.00% $0.00
MPB, INC. 0.00% $0.00
MURRAY CONSTRUCTION 0.00% $0.00
PRIMATE CONSTRUCTION, LP 0.00% $0.00
ROADWAY SPECIALTIES, INC. 0.00% $0.00
TEXAS SHAFTS, INC. 0.00% $0.00
THE LEVY COMPANY, INC. 0.00% $0.00
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
UNDERGROUND SERVICES, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

115 Total 0 of 115
GILLESPIE  |  US 290  |  AUSTIN  |  0113-02-063  |  06/02/2023  |  $11,488,921.20  |  C 113-2-63  |  HWY IMPRV  |  219 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ACME BRIDGE COMPANY, INC.
ALLEN KELLER COMPANY
E-Z BEL CONSTRUCTION, LLC
PREPARING ROW
STA 153.000 $2,000.000 $643.800 $1,900.000 $210.000 $2,500.000
REMOVING CONC (RIPRAP)
SY 227.000 $20.000 $17.500 $20.400 $20.000 $26.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 11,168.000 $10.000 $5.900 $4.300 $4.050 $5.000
EXCAVATION (ROADWAY)
CY 26,961.000 $15.000 $17.500 $17.000 $15.000 $14.500
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 11,974.000 $12.000 $10.500 $12.000 $8.750 $12.000
FURNISHING AND PLACING TOPSOIL (4")
SY 59,500.000 $1.750 $1.830 $2.000 $2.050 $4.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 59,500.000 $0.180 $0.300 $0.200 $0.350 $0.200
DRILL SEEDING (TEMP) (WARM)
SY 29,750.000 $0.180 $0.240 $0.190 $0.250 $0.200
DRILL SEEDING (TEMP) (COOL)
SY 29,750.000 $0.180 $0.240 $0.190 $0.250 $0.200
VEGETATIVE WATERING
MG 3,000.000 $15.000 $23.400 $32.700 $10.000 $60.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 59,500.000 $1.150 $1.130 $0.940 $2.300 $1.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 12,983.000 $57.000 $80.750 $70.000 $66.000 $65.000
PRIME COAT (MULTI OPTION)
GAL 8,896.000 $4.500 $5.180 $4.550 $5.500 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,776.900 $48.000 $54.380 $59.200 $56.000 $55.000
PLAN & TEXT ASPH CONC PAV(0" TO 4")
SY 2,100.000 $3.290 $9.280 $8.300 $7.000 $7.750
CEM STABIL BKFL
CY 406.000 $125.000 $180.000 $127.000 $150.000 $280.000
FLOWABLE BACKFILL
CY 13.500 $215.000 $226.810 $222.000 $750.000 $250.000
TEMPORARY SPL SHORING
SF 415.000 $25.000 $100.000 $61.900 $70.000 $80.000
DRILL SHAFT (18 IN)
LF 108.000 $175.000 $191.890 $195.000 $290.000 $125.000
DRILL SHAFT (36 IN)
LF 822.000 $275.000 $412.850 $379.000 $530.000 $340.000
CL C CONC (ABUT)
CY 108.400 $1,600.000 $1,800.000 $1,400.000 $1,390.000 $1,500.000
CL C CONC (CAP)
CY 99.800 $1,600.000 $1,800.000 $1,320.000 $1,260.000 $1,100.000
CL C CONC (COLUMN)
CY 38.500 $1,600.000 $1,400.000 $1,260.000 $1,360.000 $1,800.000
REINF CONC SLAB
SF 12,950.000 $22.000 $28.000 $23.800 $26.000 $36.000
APPROACH SLAB
CY 319.000 $650.000 $750.000 $899.000 $970.000 $900.000
PRESTR CONC GIRDER (TX28)
LF 1,708.700 $200.000 $160.000 $206.000 $210.000 $275.000
RIPRAP (CONC)(5 IN)
CY 506.000 $485.000 $540.020 $529.000 $640.000 $750.000
RIPRAP (CONC)(CL B)
CY 123.500 $600.000 $572.420 $561.000 $660.000 $600.000
RIPRAP (STONE TY R)(DRY)(12 IN)
CY 12.000 $250.000 $218.560 $174.000 $310.000 $200.000
RIRRAP (STONE COMMON)(DRY)(15 IN)
CY 135.600 $250.000 $171.520 $156.000 $180.000 $215.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,096.000 $180.000 $192.840 $125.000 $140.000 $165.000
RIPRAP (MOW STRIP)(4 IN)
CY 81.600 $600.000 $702.020 $688.000 $740.000 $600.000
RAIL (TY SSTR)
LF 422.000 $65.000 $115.000 $127.000 $140.000 $195.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 205.000 $200.000 $200.000 $214.000 $320.000 $300.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 12.000 $875.000 $2,440.870 $2,390.000 $1,490.000 $2,750.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 88.000 $1,100.000 $1,004.430 $984.000 $1,670.000 $1,750.000
RC PIPE (CL IV)(18 IN)
LF 1,412.000 $85.000 $97.200 $95.200 $110.000 $200.000
RC PIPE (CL IV)(24 IN)
LF 176.000 $120.000 $146.880 $144.000 $140.000 $300.000
WINGWALL (PW - 1) (HW=8 FT)
EA 7.000 $25,000.000 $30,780.870 $30,100.000 $27,030.000 $40,000.000
SET (TY II) (18 IN) (CMP) (6: 1) (C)
EA 80.000 $1,500.000 $1,620.050 $1,590.000 $1,200.000 $2,400.000
SET (TY II) (24 IN) (CMP) (6: 1) (C)
EA 10.000 $2,050.000 $1,890.050 $1,850.000 $2,000.000 $2,550.000
REMOV STR (SET)
EA 24.000 $500.000 $199.810 $196.000 $370.000 $1,250.000
REMOV STR (WINGWALL)
EA 7.000 $1,500.000 $399.610 $391.000 $3,020.000 $1,600.000
REMOV STR (HEADWALL)
EA 7.000 $1,550.000 $405.010 $397.000 $3,000.000 $4,000.000
REMOV STR (PIPE)
LF 809.000 $20.000 $7.560 $7.400 $33.000 $10.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $90,000.000 $150,000.000 $164,000.000 $195,350.000 $100,000.000
MOBILIZATION
LS 1.000 $1,026,672.940 $1,064,114.540 $1,120,000.000 $875,000.000 $1,200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $8,500.000 $3,738.400 $10,000.000 $10,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 200.000 $35.000 $39.960 $39.100 $38.000 $33.500
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 200.000 $35.000 $45.360 $44.400 $52.000 $45.300
BACKHOE WORK (EROSION & SEDMT CONT)
HR 80.000 $75.000 $120.000 $134.000 $330.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,800.000 $3.500 $2.430 $2.400 $4.100 $3.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,800.000 $0.750 $1.300 $1.050 $0.400 $0.350
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 9,800.000 $7.330 $4.050 $3.950 $6.750 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 9,800.000 $3.010 $1.830 $1.050 $1.150 $1.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,520.000 $15.000 $30.000 $28.000 $120.000 $50.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 2,520.000 $12.000 $10.000 $4.950 $8.250 $10.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 2,520.000 $15.000 $10.000 $26.300 $26.000 $30.000
INTRSCT, DRVWAYS, & TURNOUT (CONC)
SY 104.000 $125.000 $145.800 $143.000 $200.000 $135.000
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 3,920.400 $35.000 $50.600 $54.900 $62.000 $52.000
MTL W-BEAM GD FEN (TIM POST)
LF 3,719.000 $27.000 $25.750 $25.200 $30.000 $27.100
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,250.000 $2,562.640 $2,390.000 $5,410.000 $2,375.000
SHORT RADIUS
LF 66.000 $85.000 $187.140 $183.000 $170.000 $36.600
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $1,200.000 $1,291.410 $1,260.000 $1,480.000 $915.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 40.000 $110.000 $119.570 $117.000 $97.000 $113.800
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 5.000 $1,500.000 $1,376.920 $1,350.000 $1,710.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 450.000 $2.500 $4.320 $4.250 $2.300 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 26.000 $3,600.000 $3,436.390 $3,370.000 $3,420.000 $3,355.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $260.000 $432.010 $423.000 $230.000 $225.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $700.000 $1,113.930 $1,090.000 $1,500.000 $1,250.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $900.000 $981.250 $961.000 $750.000 $1,150.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 4.000 $2,300.000 $10,427.460 $10,200.000 $6,370.000 $8,490.000
WIRE FENCE (TY C)
LF 1,075.000 $20.000 $20.000 $18.700 $27.000 $20.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 1.000 $285.000 $270.010 $372.000 $290.000 $352.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 7.000 $585.000 $486.010 $714.000 $510.000 $675.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $685.000 $648.020 $828.000 $680.000 $783.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 31.000 $800.000 $783.020 $930.000 $830.000 $879.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 2.000 $900.000 $864.020 $1,230.000 $8,350.000 $1,164.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 3.000 $800.000 $972.030 $1,090.000 $1,030.000 $1,032.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $800.000 $1,026.030 $863.000 $11,330.000 $816.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $950.000 $1,053.030 $997.000 $1,110.000 $942.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 4.000 $1,200.000 $1,188.030 $1,190.000 $1,260.000 $1,122.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 1.000 $1,200.000 $1,296.040 $1,310.000 $1,370.000 $1,239.000
REMOVE SM RD SN SUP&AM
EA 93.000 $105.000 $81.000 $124.000 $86.000 $117.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 35.000 $40.000 $32.400 $28.600 $40.000 $27.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 30,600.000 $0.250 $0.430 $0.460 $0.450 $0.270
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 30,600.000 $0.250 $0.270 $0.290 $0.300 $0.270
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 30,600.000 $0.250 $0.430 $0.460 $0.450 $0.270
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 30,600.000 $0.600 $0.580 $0.620 $0.600 $0.650
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 30,600.000 $1.200 $0.540 $0.580 $0.550 $0.770
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 31,260.000 $0.650 $0.580 $0.620 $0.600 $0.650
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 225.000 $10.000 $9.990 $10.700 $11.000 $8.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 30,045.000 $1.100 $0.250 $0.270 $0.250 $0.340
REFL PAV MRK TY II (W) 24" (SLD)
LF 225.000 $10.000 $3.940 $4.200 $4.150 $4.000
REFL PAV MRK TY II (Y) 6" (BRK)
LF 7,500.000 $1.990 $0.260 $0.280 $0.250 $0.340
REFL PAV MRK TY II (Y) 6" (SLD)
LF 29,788.000 $1.120 $0.250 $0.270 $0.250 $0.340
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 7,650.000 $1.480 $0.770 $0.820 $0.800 $0.700
RE PM W/RET REQ TY II (W) 6" (BRK)
LF 7,650.000 $1.480 $0.260 $0.280 $0.250 $0.350
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 30,045.000 $2.200 $1.070 $1.150 $1.150 $1.100
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 7,500.000 $2.000 $1.140 $1.200 $1.200 $1.100
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 9,788.000 $2.500 $1.070 $1.150 $1.150 $1.100
REFL PAV MRKR TY I-C
EA 383.000 $4.500 $7.720 $8.300 $8.250 $5.000
REFL PAV MRKR TY II-A-A
EA 766.000 $4.000 $6.480 $6.900 $6.750 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 38,500.000 $0.350 $0.430 $0.460 $0.450 $0.520
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 3.000 $8,750.000 $14,602.010 $14,300.000 $15,430.000 $7,500.000
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 3.000 $500.000 $1,836.050 $1,800.000 $1,940.000 $750.000
D-GR HMA TY-B PG64-22
TON 14,351.000 $95.000 $99.000 $106.000 $100.000 $100.000
D-GR HMA TY-D PG76-22
TON 6,853.000 $120.000 $110.000 $125.000 $125.000 $120.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 6,206.000 $120.000 $115.700 $136.000 $130.000 $125.000
TOM-C PG76-22 SAC-B
TON 6,800.000 $140.000 $137.700 $152.000 $155.000 $145.000
BONDING COURSE
GAL 37,034.000 $3.500 $3.540 $4.100 $5.250 $3.850
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $9,000.000 $16,500.000 $32,870.000 $12,500.000
TMA (STATIONARY)
DAY 120.000 $300.000 $350.000 $185.000 $220.000 $240.000
TMA (MOBILE OPERATION)
DAY 120.000 $350.000 $850.000 $526.000 $1.000 $300.000
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 44.000 $2,055.000 $2,750.000 $361.000 $2,360.000 $750.000
Totals: $11,488,921.200 $12,041,546.051 $12,426,566.100 $12,612,540.300 $13,291,438.720