GALVESTON IH 45 (0500-01-154)

Items: 69

County: GALVESTON
Length: 30.5510 MILES
Highway: IH 45
District: HOUSTON
Control Number: 0500-01-154
DBE Goal: 0.0%
Project: F 2026(484)
Guaranty: $78,000.00
Time: 398 WORKING DAYS
Engineer's Estimate: $3,887,385.31
Date: 04/08/2026 (2 months ago)
Contract Number: 4263219
Type: LANDSCAPE DEVELOPMENT
Project ID: A00199263
Contract Type: Federal
Project Description: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DAVID LAZARO
JOEL CLARKE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,887,385.31
Over/Under Est: -18.04% -$701,448.23
Over/Under Est: -15.6% -$606,385.31
Amt Left: 2.98% $95,062.92
Over/Under Est: -13.11% -$509,609.46
Amt Left: 6.02% $191,838.77
Delta: -2.95% -$96,775.85
Over/Under Est: -4.61% -$179,323.64
Amt Left: 16.39% $522,124.59
Delta: -9.78% -$330,285.82

Bid Items & Bid Tabulations

69 Total 0 of 69
GALVESTON  |  IH 45  |  HOUSTON  |  0500-01-154  |  04/08/2026  |  $3,887,385.31  |  F 2026(484)  |  LANDSCAPE DEVELOPMENT  |  398 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
CENTRAL NORTH CONSTRUCTION, LLC
APEX LANDSCAPE & IRRIGATION, LLC
GREEN SAGE SERVICES LLC
PREPARING ROW
AC 7.770 $11,170.000 $16,731.017 $1,300.000 $7,500.000 $7,000.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 93.000 $867.000 $430.108 $275.000 $800.000 $500.000
PREP ROW (TREE PRUNE AND TRIM)
AC 0.550 $5,200.000 $4,545.455 $3,000.000 $12,850.000 $5,500.000
PREP ROW (HAND CLEARING)
AC 0.200 $13,000.000 $12,500.000 $2,500.000 $10,000.000 $8,500.000
REMOV CONC (RIPRAP)
SY 261.650 $15.650 $17.836 $12.000 $20.000 $36.800
REMOV CONC (MISC)
SY 2,540.000 $12.550 $5.249 $12.000 $7.000 $35.000
SPEC EXCAV WORK (ORIGINAL)
CY 500.000 $75.000 $183.333 $12.000 $20.000 $40.000
SPEC EXCAV WORK (VEHICLE)
CY 101.300 $60.000 $193.320 $12.000 $50.000 $40.000
FURN & PLACE TOPSOIL (VEH)
CY 1,494.340 $57.000 $54.651 $35.000 $70.000 $44.000
EROSION CONTROL COMPOST (VEH)
CY 1,441.000 $46.000 $37.011 $17.000 $25.000 $27.000
GENERAL USE COMPOST (VEH)
CY 684.000 $46.000 $60.916 $21.000 $25.000 $29.000
BLOCK SODDING
SY 22,178.200 $5.250 $5.336 $3.750 $5.400 $4.700
FERTILIZER
AC 4.583 $446.250 $1,163.721 $550.000 $850.000 $950.000
VEGETATIVE WATERING
TGL 549.802 $45.000 $39.408 $18.000 $35.000 $50.000
IRRIGATION SYSTEM (TY I)
EA 1.000 $82,445.000 $10,000.000 $20,000.000 $70,000.000 $110,000.000
IRRIGATION SYSTEM (TY II)
EA 1.000 $19,900.000 $31,295.833 $20,000.000 $30,000.000 $22,000.000
IRRIGATION SYSTEM (TY III)
EA 1.000 $52,468.000 $7,500.000 $20,000.000 $30,000.000 $15,000.000
SOIL AMEND
SY 1,287.000 $2.150 $0.256 $1.000 $1.000 $1.500
SOIL AMEND (TY I)
SY 1,707.000 $1.000 $0.409 $1.000 $0.400 $1.000
PLANT BED PREP (TY I)
SY 4,956.200 $1.500 $0.269 $2.500 $1.250 $4.500
PLANT BED PREP (TY II)
SY 14.000 $4.800 $1.190 $5.000 $0.750 $8.000
PLANT BED PREP (TY III)
SY 7,308.000 $2.000 $0.456 $3.500 $1.250 $4.500
LANDSCAPE EDGE (TY I)
LF 4,264.000 $17.000 $10.944 $8.000 $7.000 $13.000
LOOSE AGGR GRND COVER (TY I)
CY 166.000 $271.000 $652.610 $275.000 $950.000 $300.000
PLANT MATERIAL (30 GAL) (TREE)
EA 6.000 $270.000 $168.056 $275.000 $230.000 $350.000
PLANT MATERIAL (45 GAL) (TREE)
EA 57.000 $560.000 $438.596 $600.000 $550.000 $380.000
PLANT MATERIAL (65 GAL) (TREE)
EA 42.000 $620.000 $672.619 $700.000 $720.000 $590.000
PLANT MATERIAL (3 GAL) (SHRUB)
EA 4,685.000 $40.000 $18.499 $21.000 $30.000 $27.000
PLANT MATERIAL (MIN 14' TRNK HT)(PALM)
EA 275.000 $1,270.000 $1,278.788 $2,000.000 $680.000 $650.000
SOIL AMEND (TY II)
SY 1,707.000 $1.600 $0.142 $2.000 $0.300 $2.500
LANDSCAPE ESTABLISH
MO 12.000 $10,400.000 $6,652.778 $5,800.000 $4,000.000 $12,000.000
LANDSCAPE ESTABLISH
CYC 4.000 $14,300.000 $1,458.333 $5,700.000 $35,000.000 $28,050.000
IRRIG SYS OPER AND MAINT
MO 12.000 $5,200.000 $2,638.889 $5,000.000 $5,000.000 $2,500.000
LANDSCAPE TREAT
EA 275.000 $125.000 $242.424 $80.000 $80.000 $60.000
LANDSCAPE TREAT
CYC 1.000 $26,000.000 $3,833.333 $8,000.000 $30,000.000 $8,000.000
LANDSCAPE TREAT (TY I)
EA 105.000 $3.450 $1.084 $4.000 $4.000 $6.000
LANDSCAPE TREAT (TY II)
EA 315.000 $1.400 $0.335 $4.000 $4.000 $5.000
LANDSCAPE TREAT (TY I)
CYC 1.000 $52,000.000 $11,458.333 $25,000.000 $30,000.000 $45,000.000
LANDSCAPE TREAT (TY II)
CYC 2.000 $11,700.000 $5,145.833 $4,000.000 $22,500.000 $21,000.000
LANDSCAPE TREAT (TY III)
EA 4,790.000 $2.950 $0.348 $1.500 $1.000 $4.000
LANDSCAPE TREAT (TY IV)
EA 93.000 $125.000 $71.685 $50.000 $150.000 $50.000
LANDSCAPE TREAT (TY V)
EA 130.000 $65.000 $102.564 $50.000 $170.000 $200.000
LANDSCAPE TREAT (TY VI)
EA 60.000 $750.000 $472.222 $300.000 $450.000 $350.000
LANDSCAPE TREAT (TY VII)
EA 63.000 $45.000 $29.101 $50.000 $45.000 $40.000
LANDSCAPE TREAT (TY VIII)
EA 42.000 $5.000 $47.619 $60.000 $50.000 $55.000
LANDSCAPE TREAT (TY IX)
EA 105.000 $53.000 $14.286 $15.000 $75.000 $250.000
LANDSCAPE TREAT (TY X)
EA 105.000 $1.400 $15.873 $15.000 $10.000 $20.000
LANDSCAPE TREAT (TY III)
CYC 3.000 $26,000.000 $3,888.889 $18,000.000 $50,000.000 $11,000.000
LANDSCAPE TREAT (TY IV)
CYC 1.000 $13,000.000 $21,625.000 $42,000.000 $7,500.000 $18,000.000
LANDSCAPE TREAT (TY V)
CYC 1.000 $11,700.000 $16,625.000 $15,000.000 $7,500.000 $8,500.000
LANDSCAPE TREAT (TY VI)
CYC 1.000 $26,000.000 $3,295.000 $20,000.000 $3,500.000 $7,500.000
LANDSCAPE TREAT (TY VII)
CYC 96.000 $850.000 $625.000 $500.000 $700.000 $1,200.000
RDSIDE AMENITY
EA 25.000 $200.000 $133.333 $150.000 $750.000 $400.000
RDSIDE AMENITY (REMOV & RESET)
EA 1.000 $1,050.000 $5,833.333 $250.000 $2,000.000 $2,500.000
CONCRETE PAINT FINISH
SF 57,489.000 $0.900 $0.354 $3.000 $3.000 $3.250
EXPOSED AGGREGATE FINISH
SF 57,489.000 $2.200 $1.702 $4.000 $4.000 $4.150
RIPRAP (CONC)(5 IN)
CY 1,185.000 $505.000 $750.141 $600.000 $530.000 $560.000
RIPRAP (CONC)(6 IN)
CY 8.000 $705.000 $803.333 $600.000 $500.000 $1,550.000
MOBILIZATION
LS 1.000 $344,130.000 $190,876.110 $135,000.000 $143,350.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $8,500.000 $2,388.889 $4,500.000 $5,000.000 $5,500.000
TMA (STATIONARY)
DAY 260.000 $900.000 $384.615 $200.000 $10.000 $660.000
TMA (MOBILE OPERATION)
DAY 90.000 $800.000 $388.889 $240.000 $10.000 $730.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 3,520.000 $5.500 $4.261 $3.000 $1.350 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,520.000 $1.400 $0.308 $1.000 $0.250 $1.200
REMOVE AND RELAY PAVERS
SY 2,540.000 $61.750 $29.528 $105.000 $75.000 $92.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 10.000 $800.000 $700.000 $865.000 $900.000 $880.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 1.000 $900.000 $858.333 $859.000 $1,000.000 $1,050.000
REMOVE SM RD SN SUP&AM
EA 10.000 $120.000 $103.333 $130.000 $900.000 $125.000
INSTL OM SM RD SIGN (1-OM-TY1)Y
EA 1.000 $30.000 $98.333 $99.860 $150.000 $150.000
Totals: $3,887,385.306 $3,185,937.049 $3,280,999.996 $3,377,775.850 $3,708,061.670
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $2,500.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $11,700.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,525.00
Total: $19,725.00