FRIO IH 35 (0017-07-136)

Items: 46

County: FRIO
Length: N/A
Highway: IH 35
District: SAN ANTONIO
Control Number: 0017-07-136
DBE Goal: N/A
Project: STP 1902(204)HES
Guaranty: N/A
Time: 185 WORKING DAYS
Engineer's Estimate: $921,017.48
Date: 07/09/2019 (6 years ago)
Contract Number: N/A
Type: INSTAL FLASH BEACON & SAFETY LIGHT AT INTERSECTIO
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$921,017.48
$952,818.04
Over/Under Est: 3.45% $31,800.56
$1,285,707.00
Over/Under Est: 39.6% $364,689.52
Amt Left: 34.94% $332,888.96

Bid Items & Bid Tabulations

46 Total 0 of 46
FRIO  |  IH 35  |  SAN ANTONIO  |  0017-07-136  |  07/09/2019  |  $921,017.48  |  STP 1902(204)HES  |  INSTAL FLASH BEACON & SAFETY LIGHT A...  |  185 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
E-Z BEL CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 628.000 $278.710 $300.000 $278.000
MOBILIZATION
LS 1.000 $63,412.300 $83,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $6,860.000 $3,000.000 $15,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,200.000 $2.340 $1.850 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,200.000 $0.640 $0.800 $2.000
RUMBLE STRIPS (SHOULDER)
LF 122,200.000 $0.270 $0.150 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 59,900.000 $0.230 $0.200 $0.200
CONDT (PVC) (SCH 80) (2")
LF 855.000 $8.410 $16.000 $15.000
CONDT (PVC) (SCH 80) (3")
LF 1,070.000 $12.420 $18.000 $15.000
ELEC CONDR (NO.6) BARE
LF 1,845.000 $1.320 $1.550 $2.000
ELEC CONDR (NO.6) INSULATED
LF 250.000 $1.590 $1.700 $2.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 5,100.000 $1.970 $2.300 $3.000
GROUND BOX TY A (122311)W/APRON
EA 4.000 $937.430 $850.000 $900.000
GROUND BOX TY D (162922)W/APRON
EA 16.000 $940.060 $1,000.000 $1,000.000
ZINC-COAT STL WIRE STRAND (3/16")
LF 4,530.000 $3.830 $3.000 $6.000
ZINC-COAT STL WIRE STRAND (5/16")
LF 4,530.000 $3.890 $3.000 $6.000
ELC SRV TY D 120/240 070(NS)AL(E)TP(O)
EA 12.000 $3,632.140 $5,000.000 $4,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $610.840 $750.000 $650.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 130.000 $0.770 $2.000 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 513.000 $5.630 $5.770 $11.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 9.000 $37.310 $50.000 $500.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 122,200.000 $0.210 $0.120 $0.150
REFL PAV MRK TY II (Y) 4" (BRK)
LF 11,600.000 $0.180 $0.150 $0.150
REFL PAV MRK TY II (Y) 4" (SLD)
LF 51,700.000 $0.230 $0.120 $0.150
PAVEMENT SEALER 4"
LF 250.000 $0.090 $0.500 $0.500
PAVEMENT SEALER 8"
LF 130.000 $0.270 $1.000 $0.500
PAVEMENT SEALER 24"
LF 513.000 $1.910 $3.000 $10.000
PAVEMENT SEALER (YLD TRI)
EA 9.000 $14.740 $33.000 $500.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 122,200.000 $0.360 $0.360 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 11,600.000 $0.430 $0.380 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 51,950.000 $0.280 $0.360 $0.400
REFL PAV MRKR TY I-C
EA 8.000 $3.070 $8.000 $10.000
REFL PAV MRKR TY II-A-A
EA 1,314.000 $2.790 $3.770 $8.000
PAV SURF PREP FOR MRK (4")
LF 250.000 $0.040 $0.500 $1.000
PAV SURF PREP FOR MRK (8")
LF 130.000 $0.140 $1.000 $1.000
PAV SURF PREP FOR MRK (24")
LF 513.000 $1.140 $2.000 $1.000
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 9.000 $9.600 $22.000 $300.000
INSTALL HWY TRF SIG (FLASH BEACON)
EA 12.000 $4,410.490 $1,300.000 $6,000.000
VEH SIG SEC (12")LED(YEL)
EA 96.000 $221.140 $270.000 $285.000
VEH SIG SEC (12")LED(RED)
EA 78.000 $219.580 $270.000 $285.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 8,545.000 $1.880 $1.900 $3.000
INS TRF SIG PL AM (S)STR(TY B)
EA 24.000 $3,142.750 $4,500.000 $5,000.000
INS TRF SIG PL AM (S)STR(TY B)LUM
EA 23.000 $4,550.970 $6,000.000 $6,000.000
INS TRF SIG PL AM (S)STR(TY D)LUM
EA 1.000 $5,584.370 $8,500.000 $8,000.000
TMA (STATIONARY)
DAY 48.000 $181.620 $280.000 $350.000
TMA (MOBILE OPERATION)
DAY 8.000 $150.000 $565.000 $850.000
Totals: $921,017.480 $952,818.040 $1,285,707.000