FREESTONE FM 80 (0612-01-046)

Items: 59

County: FREESTONE
Length: N/A
Highway: FM 80
District: BRYAN
Control Number: 0612-01-046
DBE Goal: 500.0%
Project: BR 2B24(084)
Guaranty: N/A
Time: 192 WORKING DAYS
Engineer's Estimate: $3,479,853.55
Date: 07/09/2024 (1 year ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
DELMY REYES
MATT HENSARLING
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$3,479,853.55
$2,767,000.00
Over/Under Est: -20.49% -$712,853.55
$2,853,360.35
Over/Under Est: -18% -$626,493.20
Amt Left: 3.12% $86,360.35
Over/Under Est: -13.02% -$453,187.65
Amt Left: 9.38% $259,665.90
Delta: -6.07% -$173,305.55
$3,174,397.05
Over/Under Est: -8.78% -$305,456.50
Amt Left: 14.72% $407,397.05
Delta: -4.88% -$147,731.15
$3,409,472.55
Over/Under Est: -2.02% -$70,381.00
Amt Left: 23.22% $642,472.55
Delta: -7.41% -$235,075.50
$3,430,085.17
Over/Under Est: -1.43% -$49,768.38
Amt Left: 23.96% $663,085.17
Delta: -0.60% -$20,612.62
Over/Under Est: 30.64% $1,066,251.49
Amt Left: 64.3% $1,779,105.04
Delta: -32.54% -$1,116,019.87
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 8.57% $239,846.88
TEXAS SHAFTS, INC. 7.69% $215,218.49
MORRIS COUNTY CONTRACTORS, L.L.C. 2.88% $80,601.98
TEXOP CONSTRUCTION 1.02% $28,546.54
WOLFE CONSTRUCTION GROUP, INCORPORATED 1.01% $28,266.67
STRIPING TECHNOLOGY, L.P. 0.82% $22,949.18
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.65% $18,191.42
PENHALL COMPANY 0.28% $7,836.30
HERMANOS STEEL, LLC 0.24% $6,716.83
Total: 23.16% $648,174.29

Bid Items & Bid Tabulations

59 Total 0 of 59
FREESTONE  |  FM 80  |  BRYAN  |  0612-01-046  |  07/09/2024  |  $3,479,853.55  |  BR 2B24(084)  |  BRIDGE REPL  |  192 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PMCO CONSTRUCTION LLC
SKYLINE BRIDGE LLC
KNIFE RIVER CORPORATION - SOUTH
C. E. BARKER, LTD.
A. L. HELMCAMP, INC.
TALBERT COMPANIES LLC
FUQUA CONSTRUCTION CO., INC.
PREPARING ROW
STA 17.200 $6,000.000 $2,900.000 $2,800.000 $5,800.000 $12,500.000 $3,000.000 $2,875.000 $26,166.487
REMOVING CONC (DRIVEWAYS)
SY 128.000 $24.000 $33.000 $30.000 $20.000 $54.780 $75.000 $22.860 $33.177
REMOVE TRT BASE & ASPH PAV (12"-20")
SY 4,574.000 $20.000 $14.500 $12.000 $9.000 $20.090 $13.000 $7.190 $15.275
EXCAVATION (ROADWAY)
CY 605.000 $50.000 $22.000 $18.000 $30.000 $16.640 $30.000 $37.230 $40.173
EXCAVATION (CHANNEL)
CY 540.000 $50.000 $24.000 $15.000 $30.000 $44.640 $30.000 $55.960 $45.278
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 6,532.000 $40.000 $30.000 $30.000 $32.000 $45.450 $55.000 $58.730 $32.322
FURNISHING AND PLACING TOPSOIL (4")
SY 6,644.000 $2.750 $4.500 $4.000 $1.750 $6.590 $3.500 $4.700 $11.494
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 6,644.000 $1.100 $0.650 $1.000 $0.800 $0.790 $0.700 $1.970 $0.741
CELL FBR MLCH SEED(TEMP)(WARM)
SY 3,322.000 $1.100 $0.750 $1.000 $0.800 $0.790 $0.700 $2.070 $0.845
CELL FBR MLCH SEED(TEMP)(COOL)
SY 3,322.000 $1.100 $0.750 $1.000 $0.800 $0.790 $0.700 $2.270 $1.300
VEGETATIVE WATERING
MG 66.500 $50.000 $50.000 $1.000 $80.000 $62.900 $10.000 $342.480 $340.393
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 6,159.000 $60.000 $26.000 $40.000 $22.000 $19.880 $28.000 $50.730 $39.000
LIME (COMMERCIAL LIME SLURRY)
TON 110.000 $460.000 $390.000 $400.000 $350.000 $393.860 $450.000 $372.070 $598.000
LIME TRT (EXST MATL)(10")
SY 6,598.000 $30.000 $9.000 $10.000 $6.500 $28.400 $10.000 $11.500 $39.000
CEMENT
TON 69.000 $300.000 $410.000 $400.000 $275.000 $401.730 $350.000 $326.660 $367.594
CEMENT TREAT (EXIST MATL) (10")
SY 6,598.000 $6.000 $9.000 $11.300 $3.000 $7.100 $7.000 $5.870 $6.500
ASPH (RC-250)
GAL 1,430.000 $20.000 $30.000 $15.000 $10.000 $10.960 $8.000 $11.480 $20.178
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 43.000 $650.000 $795.000 $800.000 $475.000 $913.010 $800.000 $1,468.710 $845.000
CEM STABIL BKFL
CY 206.000 $230.000 $325.000 $350.000 $340.000 $182.600 $525.000 $317.750 $279.105
DRILL SHAFT (36 IN)
LF 760.000 $350.000 $350.000 $340.000 $425.000 $387.180 $325.000 $325.450 $409.533
CL C CONC (ABUT)
CY 79.200 $1,535.000 $1,350.000 $1,100.000 $2,150.000 $1,294.290 $2,900.000 $1,915.240 $2,037.615
REINF CONC SLAB
SF 4,680.000 $40.000 $32.000 $33.500 $40.000 $30.370 $80.000 $35.740 $39.762
APPROACH SLAB
CY 100.800 $975.000 $900.000 $900.000 $1,000.000 $847.010 $1,200.000 $1,074.100 $1,083.193
PRESTR CONC GIRDER (TX28)
LF 645.000 $250.000 $245.000 $260.000 $375.000 $320.210 $275.000 $188.380 $330.850
RIPRAP (CONC)(4 IN)
CY 81.000 $900.000 $715.000 $750.000 $785.000 $595.820 $1,100.000 $918.180 $1,252.730
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,163.000 $240.000 $175.000 $200.000 $148.000 $118.890 $115.000 $271.030 $279.457
RIPRAP (MOW STRIP)(4 IN)
CY 109.000 $875.000 $685.000 $750.050 $750.000 $606.780 $1,000.000 $817.190 $951.757
RAIL (TY T223)
LF 324.000 $208.000 $150.000 $150.000 $175.000 $182.020 $275.000 $177.090 $305.175
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 140.000 $166.000 $120.000 $150.000 $175.000 $255.640 $280.000 $115.000 $221.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,300.000 $30,000.000 $15,000.000 $60,000.000 $27,999.080 $40,000.000 $28,976.650 $48,411.160
REMOV STR (SMALL FENCE)
LF 190.000 $17.000 $13.500 $5.000 $15.000 $22.420 $30.000 $11.500 $8.775
MOBILIZATION
LS 1.000 $259,832.000 $276,000.000 $270,000.000 $300,000.000 $300,000.000 $290,000.000 $381,191.170 $573,090.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $14,000.000 $3,500.000 $2,100.000 $5,000.000 $3,226.290 $4,000.000 $5,750.000 $16,741.060
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 109.000 $45.000 $58.000 $45.000 $48.000 $46.260 $42.000 $46.910 $59.162
ROCK FILTER DAMS (REMOVE)
LF 109.000 $14.000 $16.000 $10.000 $18.000 $18.260 $16.000 $11.940 $19.079
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 222.000 $40.000 $48.000 $10.000 $25.000 $34.090 $30.000 $49.060 $78.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $11.000 $16.000 $1.000 $6.000 $6.090 $10.000 $7.210 $14.261
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,229.000 $5.000 $4.250 $3.500 $7.750 $4.570 $4.000 $5.210 $5.734
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,229.000 $1.750 $1.100 $1.500 $1.250 $1.220 $1.050 $1.640 $1.900
DRIVEWAYS AND TURNOUTS (ACP)
SY 183.000 $50.000 $80.000 $125.000 $80.000 $68.170 $200.000 $35.190 $126.100
MTL W-BEAM GD FEN (TIM POST)
LF 1,575.000 $27.000 $24.000 $26.000 $33.000 $27.390 $25.000 $27.030 $41.592
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,500.000 $1,750.000 $2,000.000 $3,000.000 $2,641.650 $2,500.000 $2,070.000 $3,031.648
REMOVE METAL BEAM GUARD FENCE
LF 1,700.000 $5.000 $2.150 $5.000 $5.000 $4.260 $4.000 $2.880 $7.919
RM MTL BM GD FEN TRANS (T101)
EA 8.000 $230.000 $170.000 $250.000 $300.000 $182.600 $170.000 $287.500 $291.200
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,200.000 $3,150.000 $3,400.000 $3,300.000 $3,499.880 $3,200.000 $3,335.000 $4,180.971
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $210.000 $225.000 $250.000 $350.000 $304.340 $300.000 $287.500 $378.181
WIRE FENCE (TY A)
LF 55.000 $40.000 $54.000 $50.000 $100.000 $121.740 $45.000 $24.380 $24.575
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $650.000 $750.000 $1,250.000 $1,400.000 $821.710 $750.000 $847.440 $1,053.791
REMOVE SM RD SN SUP&AM
EA 9.000 $129.000 $128.750 $200.000 $100.000 $140.000 $130.000 $134.930 $194.149
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $28.000 $44.250 $50.000 $25.000 $24.350 $25.000 $25.300 $33.502
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $37.000 $30.000 $50.000 $40.000 $31.040 $30.000 $27.600 $43.883
PAVEMENT SEALER 6"
LF 5,540.000 $0.500 $1.100 $1.500 $1.250 $0.290 $1.300 $0.280 $0.702
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 3,430.000 $2.000 $2.650 $2.850 $3.000 $3.350 $3.000 $3.160 $2.646
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 190.000 $2.000 $5.700 $6.000 $6.000 $3.350 $6.000 $3.160 $1.497
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 1,920.000 $2.000 $2.700 $3.000 $3.000 $3.350 $3.000 $3.160 $1.747
REFL PAV MRKR TY II-A-A
EA 35.000 $8.000 $13.000 $12.500 $12.500 $12.170 $12.500 $11.500 $12.547
PAV SURF PREP FOR MRK (6")
LF 5,540.000 $0.350 $0.550 $0.750 $0.650 $0.070 $0.600 $0.070 $0.574
SP MIXES SP-C SAC-A PG64-22
TON 629.000 $210.000 $260.000 $300.000 $220.000 $301.900 $190.000 $253.900 $221.000
BONDING COURSE
GAL 572.000 $7.000 $9.000 $9.500 $5.000 $10.350 $5.000 $18.880 $7.455
Totals: $3,479,853.550 $2,767,000.000 $2,853,360.350 $3,026,665.900 $3,174,397.066 $3,409,472.550 $3,430,085.178 $4,546,105.158