FRANKLIN SH 37 (0189-05-051)

Items: 55

County: FRANKLIN
Length: N/A
Highway: SH 37
District: PARIS
Control Number: 0189-05-051
DBE Goal: 0.0%
Project: C 189-5-51
Guaranty: N/A
Time: 175 WORKING DAYS
Engineer's Estimate: $13,722,551.87
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$13,722,551.87
1
$12,962,475.51
Over/Under Est: -5.54% -$760,076.36
Over/Under Est: -0.47% -$64,607.76
Amt Left: 5.37% $695,468.60
$14,263,623.91
Over/Under Est: 3.94% $541,072.04
Amt Left: 10.04% $1,301,148.40
Delta: -4.43% -$605,679.80
Over/Under Est: 19.36% $2,656,239.87
Amt Left: 26.36% $3,416,316.23
Delta: -14.83% -$2,115,167.83
Subcontractor Percentage Amount
TEXOP CONSTRUCTION 5.42% $657,886.90
WITHERS CONSTRUCTION, LLC 2.90% $352,005.90
BAHENA CONSTRUCTION CO., INC. 2.76% $335,012.52
SCR CIVIL CONSTRUCTION, LLC 2.75% $333,798.70
DUSTIN ALLEN, INC. 2.53% $307,094.81
STRIPING TECHNOLOGY, L.P. 1.45% $176,002.95
PANOLA SIGN & BARRICADE, INC. 0.35% $42,483.47
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.22% $26,703.90
SURFACE PREPARATION TECHNOLOGIES, LLC 0.19% $23,062.46
RB CONTRACTING, LLC 0.19% $23,062.46
Total: 18.76% $2,277,114.07

Bid Items & Bid Tabulations

55 Total 0 of 55
FRANKLIN  |  SH 37  |  PARIS  |  0189-05-051  |  01/05/2024  |  $13,722,551.87  |  C 189-5-51  |  PREVENT MAINT  |  175 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
PREPARING ROW
STA 579.000 $2,000.000 $668.800 $608.000 $900.000 $1,750.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 695.000 $40.000 $89.410 $65.000 $25.000 $40.000
BACKFILL (TY B)
STA 704.000 $180.000 $149.620 $325.000 $150.000 $300.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 77,971.000 $0.750 $0.110 $0.350 $0.180 $0.170
BROADCAST SEED (TEMP) (WARM)
SY 38,986.000 $0.600 $0.100 $0.290 $0.150 $0.150
BROADCAST SEED (TEMP) (COOL)
SY 38,986.000 $0.600 $0.110 $0.290 $0.150 $0.170
VEGETATIVE WATERING
MG 470.000 $30.000 $23.360 $50.000 $15.000 $25.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 11,814.000 $3.000 $4.650 $3.800 $6.000 $4.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 17,215.000 $55.000 $65.270 $74.400 $75.000 $115.000
PLAN & TEXT ASPH CONC PAV(0" TO 4")
SY 344,260.000 $4.000 $3.130 $3.100 $4.000 $4.000
RIPRAP (MOW STRIP)(4 IN)
CY 464.000 $575.000 $770.000 $550.000 $600.000 $830.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 1,759.000 $50.000 $46.200 $46.000 $35.000 $25.000
CLEANING AND SEALING JOINTS (CL 7)
LF 9,370.000 $10.000 $29.700 $32.000 $27.000 $35.000
MOBILIZATION
LS 1.000 $1,247,504.720 $388,874.260 $545,105.000 $660,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $7,500.000 $30,224.650 $28,540.000 $15,000.000 $20,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,800.000 $2.500 $3.300 $5.000 $4.500 $6.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,800.000 $0.750 $0.990 $1.000 $0.500 $3.000
INTERSECTIONS (ACP)
SY 6,047.000 $55.000 $26.600 $23.500 $45.000 $80.000
DRIVEWAYS (ACP)
SY 2,781.000 $65.000 $50.800 $46.100 $65.000 $65.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 132,141.000 $0.300 $0.100 $0.095 $0.200 $0.220
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 55,866.000 $0.400 $0.100 $0.095 $0.400 $0.280
MTL W-BEAM GD FEN (STEEL POST)
LF 3,310.000 $30.000 $28.600 $26.000 $28.000 $34.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 2,000.000 $20.000 $11.000 $10.000 $10.000 $10.000
MTL THRIE-BEAM GD FEN ADJUSTMENT
LF 10.000 $20.000 $82.500 $75.000 $800.000 $1,000.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 265.000 $80.000 $101.200 $92.000 $100.000 $125.000
MTL THRIE-BEAM GD FEN (STEEL POST)
EA 20.000 $2,500.000 $4,418.780 $2,025.000 $2,400.000 $2,600.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 16.000 $895.000 $869.000 $790.000 $950.000 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 3,220.000 $4.000 $2.200 $2.000 $2.500 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 34.000 $3,000.000 $3,190.000 $2,900.000 $3,100.000 $3,600.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 10.000 $1,200.000 $1,320.000 $1,200.000 $1,200.000 $1,320.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $330.000 $300.000 $250.000 $260.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 131.000 $35.000 $35.200 $32.000 $35.000 $33.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 7,228.000 $0.300 $0.550 $0.500 $0.550 $0.700
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 13,255.000 $0.300 $0.550 $0.500 $0.550 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 609.000 $1.250 $2.030 $1.750 $1.500 $1.300
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 6,992.000 $1.250 $2.030 $1.750 $1.500 $1.300
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,535.000 $1.150 $1.320 $1.200 $1.300 $1.400
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 76.000 $12.000 $7.700 $7.000 $8.000 $10.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 8.000 $170.000 $165.000 $150.000 $200.000 $200.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 6.000 $225.000 $187.000 $170.000 $200.000 $225.000
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
EA 27.000 $80.000 $60.500 $55.000 $60.000 $75.000
REFL PAV MRK TY I (Y)12"(SLD)(090MIL)
LF 751.000 $5.000 $4.400 $4.000 $5.000 $5.250
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 2,160.000 $0.700 $1.100 $1.000 $1.100 $1.300
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 141,826.000 $0.700 $0.750 $0.680 $0.720 $1.000
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 14,284.000 $0.700 $0.880 $0.800 $0.900 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 52,608.000 $0.700 $0.750 $0.680 $0.720 $1.000
REFL PAV MRKR TY I-C
EA 231.000 $5.000 $4.400 $4.000 $5.000 $5.300
REFL PAV MRKR TY II-A-A
EA 2,064.000 $5.500 $4.400 $4.000 $5.000 $5.300
D-GR HMA TY-C PG64-22 (LEVEL-UP)
TON 2,285.000 $110.000 $132.470 $131.800 $150.000 $132.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 3,570.000 $110.000 $130.110 $144.700 $150.000 $132.000
SP MIXES SP-C SAC-A PG64-22
TON 53,567.000 $110.000 $118.630 $127.800 $132.000 $130.000
UNDERSEAL COURSE
GAL 86,069.000 $5.000 $5.880 $5.750 $4.000 $5.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,500.000 $18,771.880 $13,500.000 $20,000.000 $20,000.000
TMA (STATIONARY)
DAY 179.000 $200.000 $461.590 $400.000 $200.000 $250.000
TMA (MOBILE OPERATION)
HR 104.000 $50.000 $140.200 $125.000 $20.000 $150.000
Totals: $13,722,551.870 $12,962,475.510 $13,657,944.115 $14,263,623.910 $16,378,791.740