FOARD CR (0925-21-009)
Items: 33
County: FOARD
Length: N/A
Highway: CR
District: CHILDRESS
Control Number: 0925-21-009
DBE Goal: 350.0%
Project: BR 2020(321)
Guaranty: N/A
Time: 101 WORKING DAYS
Engineer's Estimate: $899,400.00
Date: 07/09/2024 (1 year ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT AND APPROACHES
Mail/Deliver Bids To: N/A
JARED GROVES
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$899,400.00 | |||
| $699,120.00 |
-22.27%
-$200,280.00
|
|||
| $744,947.10 |
-17.17%
-$154,452.90
|
6.55%
$45,827.10
|
||
| $936,878.00 |
4.17%
$37,478.00
|
34.01%
$237,758.00
|
-25.76%
-$191,930.90
|
|
| $946,874.00 |
5.28%
$47,474.00
|
35.44%
$247,754.00
|
-1.07%
-$9,996.00
|
|
| $1,076,566.40 |
19.7%
$177,166.40
|
53.99%
$377,446.40
|
-13.70%
-$129,692.40
|
|
| $1,549,580.00 |
72.29%
$650,180.00
|
121.65%
$850,460.00
|
-43.94%
-$473,013.60
|
E
Engineer's Estimate
$899,400.00
1
Awarded
$699,120.00
Over/Under Est:
-22.27%
-$200,280.00
$744,947.10
Over/Under Est:
-17.17%
-$154,452.90
Amt Left:
6.55%
$45,827.10
$936,878.00
Over/Under Est:
4.17%
$37,478.00
Amt Left:
34.01%
$237,758.00
Delta:
-25.76%
-$191,930.90
$946,874.00
Over/Under Est:
5.28%
$47,474.00
Amt Left:
35.44%
$247,754.00
Delta:
-1.07%
-$9,996.00
$1,076,566.40
Over/Under Est:
19.7%
$177,166.40
Amt Left:
53.99%
$377,446.40
Delta:
-13.70%
-$129,692.40
$1,549,580.00
Over/Under Est:
72.29%
$650,180.00
Amt Left:
121.65%
$850,460.00
Delta:
-43.94%
-$473,013.60
| Subcontractor | Percentage | Amount |
|---|---|---|
| CARTHAGE DRILLING, LLC | 7.58% | $52,993.30 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 3.76% | $26,286.91 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 1.24% | $8,669.09 |
| FC TRAFFIC CONTROL, INC. | 1.22% | $8,529.26 |
| PENHALL COMPANY | 0.64% | $4,474.37 |
| Total: | 14.44% | $100,952.93 |
Bid Items & Bid Tabulations
33
Total
0 of 33