FAYETTE FM 1115 (1262-01-016)

Items: 60

County: FAYETTE
Length: 0.1670 MILES
Highway: FM 1115
District: YOAKUM
Control Number: 1262-01-016
DBE Goal: 0.0%
Project: BR 2026(191)
Guaranty: $29,000.00
Time: WORKING DAYS
Engineer's Estimate: $1,442,457.80
Date: 12/03/2025 (6 months ago)
Contract Number: 12253219
Type: BRIDGE REPLACEMENT
Project ID: A00130033
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$1,442,457.80
$1,375,081.21
Over/Under Est: -4.67% -$67,376.59
Over/Under Est: 2.81% $40,598.08
Amt Left: 7.85% $107,974.67
Over/Under Est: 3.37% $48,666.15
Amt Left: 8.44% $116,042.74
Delta: -0.54% -$8,068.07
Over/Under Est: 4.97% $71,711.60
Amt Left: 10.11% $139,088.19
Delta: -1.55% -$23,045.45
$1,610,496.20
Over/Under Est: 11.65% $168,038.40
Amt Left: 17.12% $235,414.99
Delta: -6.36% -$96,326.80
$1,767,926.59
Over/Under Est: 22.56% $325,468.79
Amt Left: 28.57% $392,845.38
Delta: -9.78% -$157,430.39
Over/Under Est: 38.39% $553,788.00
Amt Left: 45.17% $621,164.59
Delta: -12.91% -$228,319.21
$2,167,418.83
Over/Under Est: 50.26% $724,961.03
Amt Left: 57.62% $792,337.62
Delta: -8.57% -$171,173.03

Bid Items & Bid Tabulations

60 Total 0 of 60
FAYETTE  |  FM 1115  |  YOAKUM  |  1262-01-016  |  12/03/2025  |  $1,442,457.80  |  BR 2026(191)  |  BRIDGE REPL  |  WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
E-Z BEL CONSTRUCTION, LLC
R CONSTRUCTION CIVIL, LLC
ACME BRIDGE COMPANY, INC.
STX CIVIL
TREVWAY, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
C. E. BARKER, LTD.
PREPARING ROW
STA 7.000 $3,500.000 $4,154.700 $6,500.000 $3,900.000 $4,910.000 $1,500.000 $2,500.000 $3,600.000 $30,000.000
REMOV CONC (RIPRAP)
SY 13.000 $16.500 $14.300 $100.000 $99.000 $67.900 $20.000 $256.200 $40.000 $91.280
OBLITERATING ABANDONED ROAD
SY 2,247.000 $6.000 $2.200 $7.000 $6.500 $2.450 $7.000 $9.000 $5.500 $10.820
EXCAV (ROADWAY)
CY 839.000 $22.000 $23.100 $24.000 $22.000 $20.600 $20.000 $19.850 $25.000 $39.450
EXCAV (CHANNEL)
CY 755.000 $20.000 $23.100 $19.000 $24.000 $25.000 $22.000 $17.650 $20.000 $39.450
EMBANK (FNL)(OC)(TY C)
CY 1,116.000 $22.000 $23.100 $16.000 $22.000 $15.010 $30.000 $32.200 $30.000 $39.450
BLADING
HR 20.000 $150.000 $77.000 $150.000 $100.000 $78.400 $100.000 $100.000 $20.000 $133.620
FURN & PLACE TOPSOIL (4")
SY 722.000 $5.000 $2.200 $25.000 $8.000 $0.500 $4.000 $5.000 $4.000 $6.680
BROADCAST SEED (PERM_RURAL_SAND)
SY 2,920.000 $1.000 $0.380 $1.000 $0.700 $0.370 $0.250 $1.260 $2.000 $0.190
BROADCAST SEED (TEMP_WARM)
SY 730.000 $1.000 $0.240 $2.000 $1.350 $0.230 $0.250 $0.630 $1.000 $0.190
BROADCAST SEED (TEMP_COOL)
SY 730.000 $1.000 $0.260 $2.000 $1.350 $0.260 $0.250 $0.630 $1.000 $0.190
VEGETATIVE WATERING
TGL 25.000 $65.000 $30.800 $110.000 $200.000 $40.000 $50.000 $100.000 $1.000 $133.620
SOIL RET BLKT(SL_MOD_SAND_LONG)
SY 502.000 $3.000 $1.490 $3.000 $4.250 $1.450 $5.000 $5.000 $4.000 $3.390
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 1,037.500 $95.000 $67.720 $95.000 $87.000 $94.000 $85.000 $144.000 $110.000 $94.720
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 31.500 $300.000 $330.000 $455.000 $350.000 $279.000 $350.000 $505.260 $300.000 $402.000
LIME TRT (EXIST MATL)(8")
SY 1,957.000 $7.000 $5.500 $7.000 $5.500 $3.000 $5.000 $22.000 $20.000 $6.680
CEMENT
TON 18.900 $250.000 $214.530 $235.000 $255.000 $279.000 $235.000 $505.000 $300.000 $381.780
CEMENT TRT (EXIST MATL)(8")
SY 1,957.000 $3.000 $3.300 $2.000 $5.250 $3.050 $5.000 $22.000 $20.000 $6.680
ASPH (RC-250)
GAL 719.000 $7.000 $6.050 $9.000 $4.000 $8.700 $8.000 $10.110 $15.000 $10.180
AGGR (TY-E, GR-5)(SAC-B)
CY 26.000 $625.000 $174.730 $675.000 $1,025.000 $467.000 $650.000 $631.580 $600.000 $636.300
AGGR (TY-PE, GR-4)(SAC-B)
CY 56.000 $625.000 $218.040 $435.000 $1,025.000 $441.000 $650.000 $631.580 $700.000 $636.300
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 2,430.000 $5.000 $4.950 $7.000 $4.000 $7.500 $8.000 $7.580 $12.000 $7.640
CEM STABIL BKFL
CY 77.000 $215.000 $125.000 $99.000 $105.000 $210.000 $175.000 $215.910 $300.000 $184.530
DRILL SHAFT (24 IN)
LF 696.000 $195.000 $197.230 $181.000 $245.000 $172.000 $275.000 $320.000 $200.000 $334.980
CL C CONC (ABUT)
CY 28.400 $1,600.000 $1,700.000 $1,800.000 $600.000 $1,420.000 $1,000.000 $950.000 $1,800.000 $2,762.440
CL C CONC (CAP)
CY 21.600 $1,700.000 $1,300.000 $1,500.000 $715.000 $1,860.000 $1,600.000 $1,200.000 $1,900.000 $2,782.680
CL C CONC (COLUMN)
CY 10.400 $1,800.000 $1,200.000 $1,300.000 $785.000 $1,750.000 $1,800.000 $1,771.000 $2,000.000 $2,746.030
REINF CONC SLAB (SLAB BEAM)
SF 5,046.000 $17.000 $20.000 $27.000 $23.000 $19.300 $23.500 $22.000 $25.000 $31.920
PRESTR CONC SLAB BEAM (4SB15)
LF 1,184.820 $190.000 $190.000 $208.000 $225.000 $242.000 $260.000 $208.000 $265.000 $216.910
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,237.000 $170.000 $211.830 $175.000 $233.000 $170.000 $180.000 $145.000 $210.000 $193.750
RAIL (TY SSTR)
LF 264.000 $100.000 $102.600 $95.000 $155.000 $119.000 $160.000 $110.000 $160.000 $182.730
ARMOR JOINT (SEALED)
LF 86.000 $125.000 $230.780 $106.370 $72.000 $127.000 $235.000 $103.000 $250.000 $141.890
RC PIPE (CL III)(30 IN)
LF 112.000 $165.000 $198.630 $148.000 $97.000 $116.000 $150.000 $218.000 $130.000 $173.150
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 4.000 $2,500.000 $2,921.080 $4,200.000 $4,600.000 $3,070.000 $2,500.000 $4,768.000 $6,000.000 $3,436.020
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $22,000.000 $29,750.310 $15,000.000 $22,000.000 $26,500.000 $20,000.000 $75,000.000 $60,000.000 $33,723.900
REMOV STR (SMALL)
EA 1.000 $1,500.000 $1,752.650 $1,000.000 $1,000.000 $1,200.000 $250.000 $1,600.000 $5,000.000 $1,972.530
MOBILIZATION
LS 1.000 $155,000.000 $109,262.560 $110,000.000 $21,000.000 $154,000.000 $146,000.000 $170,000.000 $170,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $4,000.000 $1,992.620 $2,500.000 $1,500.000 $3,050.000 $1,500.000 $1,263.000 $20,000.000 $3,075.870
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $7,000.000 $1,575.190 $5,000.000 $16,500.000 $17,000.000 $7,850.000 $15,000.000 $12,000.000 $25,452.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 148.000 $50.000 $51.840 $44.000 $80.000 $50.600 $40.000 $1.000 $1.000 $76.360
ROCK FILTER DAMS (REMOVE)
LF 148.000 $15.000 $29.220 $12.000 $10.000 $28.500 $10.000 $1.000 $1.000 $25.450
SANDBAGS FOR EROSION CONTROL
EA 30.000 $15.000 $10.130 $9.000 $18.000 $9.900 $2.000 $1.000 $5.000 $63.630
TEMP SEDMT CONT FENCE (INSTALL)
LF 769.000 $4.000 $4.170 $5.000 $4.000 $4.050 $3.000 $3.000 $1.000 $2.290
TEMP SEDMT CONT FENCE (REMOVE)
LF 769.000 $1.000 $1.190 $1.000 $1.300 $1.150 $1.000 $1.000 $1.000 $0.760
DRIVEWAYS (SURF TREAT)
SY 121.000 $40.000 $39.600 $25.000 $58.000 $47.900 $200.000 $41.680 $60.000 $42.000
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $30.000 $25.630 $25.000 $23.000 $25.500 $35.000 $28.920 $26.000 $44.540
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $2,135.990 $2,300.000 $1,700.000 $2,390.000 $2,300.000 $2,652.370 $1,600.000 $2,672.460
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $2.000 $2.670 $7.000 $2.750 $6.400 $1.000 $1.000 $3.000 $12.730
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $275.000 $267.000 $400.000 $160.000 $329.000 $250.000 $1.000 $500.000 $318.150
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,100.000 $3,203.990 $4,100.000 $3,300.000 $3,740.000 $3,550.000 $3,500.000 $3,200.000 $4,454.100
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $267.000 $400.000 $215.000 $440.000 $250.000 $1.000 $500.000 $318.150
WIRE FENCE (TY A)
LF 200.000 $25.000 $30.700 $25.000 $29.000 $15.000 $20.000 $23.410 $20.000 $63.630
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $600.000 $635.000 $100.000 $625.000 $672.050 $80.000 $631.000 $1,200.000 $2,227.050
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 12.000 $25.000 $12.000 $35.000 $25.000 $18.100 $20.000 $6.000 $20.000 $44.540
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 22.000 $35.000 $21.000 $47.000 $30.000 $29.000 $30.000 $13.000 $25.000 $57.270
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 1,760.000 $1.000 $3.500 $6.000 $3.500 $4.650 $1.500 $13.890 $6.000 $5.600
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 880.000 $1.000 $4.000 $6.000 $4.000 $4.650 $1.500 $4.420 $6.000 $5.600
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 220.000 $1.000 $4.000 $7.000 $4.000 $4.650 $1.150 $5.050 $8.000 $5.600
REFL PAV MRKR TY II-A-A
EA 22.000 $6.000 $10.000 $10.000 $10.000 $6.100 $10.000 $12.630 $15.000 $7.320
NO. OF WORKING DAYS
$/D 5,709.000 $5,709.000 $70.000 $90.000 $110.000 $90.000 $110.000 $75.000 $120.000 $120.000
Totals: $34,035,138.800 $1,774,711.207 $1,996,865.880 $2,119,113.950 $2,027,979.400 $2,238,486.200 $2,196,101.590 $2,681,325.800 $2,852,498.824