FAYETTE IH 10 (0535-07-053)

Items: 39

County: FAYETTE
Length: 15.3330 MILES
Highway: IH 10
District: YOAKUM
Control Number: 0535-07-053
DBE Goal: 0.0%
Project: C 535-7-53
Guaranty: $100,000.00
Time: 105 WORKING DAYS
Engineer's Estimate: $10,408,946.50
Date: 11/06/2024 (1 year ago)
Contract Number: 11243016
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00140570
Project Description: PFC
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$10,408,946.50
$10,827,269.87
Over/Under Est: 4.02% $418,323.37
Over/Under Est: 7.03% $731,484.19
Amt Left: 2.89% $313,160.82
Over/Under Est: 10.62% $1,105,635.00
Amt Left: 6.35% $687,311.63
Delta: -3.36% -$374,150.81
Over/Under Est: 24.08% $2,506,511.84
Amt Left: 19.29% $2,088,188.47
Delta: -12.17% -$1,400,876.84
Subcontractor Percentage Amount
STRIPE LINES, INC. 6.41% $694,028.00
CPAVE, INC. 1.58% $171,070.86
WEST TEXAS ROCK RESOURCES, LLC 0.34% $36,812.72
Total: 8.33% $901,911.58

Bid Items & Bid Tabulations

39 Total 0 of 39
FAYETTE  |  IH 10  |  YOAKUM  |  0535-07-053  |  11/06/2024  |  $10,408,946.50  |  C 535-7-53  |  SURF/ROADWAY RESTOR  |  105 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
TEXAS MATERIALS GROUP, INC.
LONE STAR PAVING COMPANY
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
BACKFILL (TY B)
STA 809.660 $145.000 $108.200 $259.000 $150.000 $150.000
BLADING
HR 40.000 $120.000 $108.000 $130.000 $100.000 $114.000
AGGR (TY-PB, GR-4)(SAC-B)
CY 2,731.000 $110.000 $111.780 $193.500 $150.000 $203.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 120,707.000 $4.500 $3.970 $3.650 $5.000 $3.400
D-GR HMA TY-D SAC-B PG76-22
TON 40,053.000 $95.000 $105.200 $115.250 $120.000 $128.000
PFC-C PG76-22 SAC-A
TON 19,691.000 $145.000 $161.300 $148.350 $180.000 $177.000
TACK COAT
GAL 29,654.000 $3.500 $3.110 $3.650 $3.500 $3.660
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 360.000 $90.000 $69.620 $80.000 $85.000 $52.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 466.000 $125.000 $166.300 $135.200 $145.000 $136.000
PLANE ASPH CONC PAV(2")
SY 355,019.000 $1.650 $1.220 $2.050 $1.500 $2.350
PLANE ASPH CONC PAV (0" TO 1.5")
SY 38,190.000 $1.600 $1.390 $1.350 $1.500 $1.850
FULL - DEPTH REPAIR CRCP (8")
CY 64.000 $310.000 $2,047.010 $1,984.000 $1,350.000 $3,000.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 60.000 $300.000 $290.000 $303.500 $400.000 $290.000
CLEANING AND SEALING EXISTING JOINTS
LF 1,774.200 $35.000 $18.080 $18.950 $27.000 $18.080
MOBILIZATION
LS 1.000 $990,000.000 $748,371.400 $655,500.000 $200,000.000 $984,376.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $4,500.000 $4,434.210 $1,430.000 $9,000.000 $12,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $8,500.000 $8,000.000 $13,100.000 $13,500.000 $12,320.000
TMA (STATIONARY)
DAY 150.000 $275.000 $300.000 $264.000 $250.000 $207.000
TMA (MOBILE OPERATION)
DAY 30.000 $275.000 $500.000 $643.500 $250.000 $207.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 161,932.000 $0.150 $0.230 $0.180 $0.150 $0.170
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 70,214.000 $0.350 $0.390 $0.350 $0.400 $0.340
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 1,953.000 $0.750 $1.280 $0.450 $2.000 $0.400
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 300,603.000 $0.400 $0.390 $0.350 $0.400 $0.340
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 9,480.000 $0.600 $0.790 $0.500 $0.600 $0.480
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 1,215.000 $2.000 $2.000 $2.050 $2.500 $1.980
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 293,628.000 $0.500 $0.390 $0.350 $0.400 $0.340
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
LF 651.000 $1.250 $1.280 $1.150 $2.000 $1.100
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 3,160.000 $1.100 $0.950 $0.900 $0.900 $0.850
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 80,966.000 $1.000 $1.000 $0.050 $0.900 $0.850
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 80,966.000 $1.000 $1.000 $0.050 $0.900 $0.850
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 20,242.000 $0.750 $0.900 $0.850 $0.700 $0.800
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 87,551.000 $0.750 $0.900 $0.850 $0.700 $0.800
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 85,226.000 $0.750 $0.900 $0.850 $0.700 $0.800
PREFAB PM TY C (W)(12")(SLD)
LF 405.000 $8.500 $13.000 $9.450 $8.000 $9.000
PREFAB PM TY C (W)(24")(SLD)
LF 421.000 $15.000 $17.000 $15.750 $15.000 $15.000
PREFAB PM TY C (W)(NUMBER)
EA 9.000 $250.000 $250.000 $94.250 $300.000 $90.000
REFL PAV MRKR TY II-C-R
EA 2,504.000 $4.750 $6.250 $6.850 $5.000 $6.500
ELIM EXT PM & MRKS (6")
LF 161,932.000 $0.400 $0.850 $0.050 $0.600 $0.740
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $10,000.000 $10,000.000 $7,600.000 $8,500.000 $14,000.000
Totals: $10,408,946.500 $10,827,269.878 $11,140,430.690 $11,514,581.500 $12,915,458.346