FAYETTE IH 10 (0535-07-053)
Items: 39
County: FAYETTE
Length: 15.3330 MILES
Highway: IH 10
District: YOAKUM
Control Number: 0535-07-053
DBE Goal: 0.0%
Project: C 535-7-53
Guaranty: $100,000.00
Time: 105 WORKING DAYS
Engineer's Estimate: $10,408,946.50
Date: 11/06/2024 (1 year ago)
Contract Number: 11243016
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00140570
Project Description: PFC
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
FAYETTE IH 10 (0535-07-053)
Project Name: N/A
Project: C 535-7-53
Length: 15.3330 MILES
Project Type: OVERLAY
Limits From: US 77
Limits To: COLORADO C/L (EASTBOUND ONLY)
Project Description: PFC
COLORADO IH 10 (0535-08-093)
Project Name: IH 10 PFC 2511-1
Project: C 535-8-93
Length: 10.2560 MILES
Project Type: OVERLAY
Limits From: FAYETTE C/L
Limits To: HATTERMANN LN (EASTBOUND ONLY)
Project Description: PFC
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$10,408,946.50 | |||
| $10,827,269.87 |
4.02%
$418,323.37
|
|||
| $11,140,430.69 |
7.03%
$731,484.19
|
2.89%
$313,160.82
|
||
| $11,514,581.50 |
10.62%
$1,105,635.00
|
6.35%
$687,311.63
|
-3.36%
-$374,150.81
|
|
| $12,915,458.34 |
24.08%
$2,506,511.84
|
19.29%
$2,088,188.47
|
-12.17%
-$1,400,876.84
|
E
Engineer's Estimate
$10,408,946.50
1
Awarded
$10,827,269.87
Over/Under Est:
4.02%
$418,323.37
$11,140,430.69
Over/Under Est:
7.03%
$731,484.19
Amt Left:
2.89%
$313,160.82
$11,514,581.50
Over/Under Est:
10.62%
$1,105,635.00
Amt Left:
6.35%
$687,311.63
Delta:
-3.36%
-$374,150.81
$12,915,458.34
Over/Under Est:
24.08%
$2,506,511.84
Amt Left:
19.29%
$2,088,188.47
Delta:
-12.17%
-$1,400,876.84
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPE LINES, INC. | 6.41% | $694,028.00 |
| CPAVE, INC. | 1.58% | $171,070.86 |
| WEST TEXAS ROCK RESOURCES, LLC | 0.34% | $36,812.72 |
| Total: | 8.33% | $901,911.58 |
Bid Items & Bid Tabulations
39
Total
0 of 39