FAYETTE IH 10 (0535-06-049)

Items: 86

County: FAYETTE
Length: N/A
Highway: IH 10
District: YOAKUM
Control Number: 0535-06-049
DBE Goal: N/A
Project: F 2B23(083)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $10,245,886.00
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT REST AREA
Mail/Deliver Bids To: N/A
COVEY MORROW
CHASE HERMES
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$10,245,886.00
$9,282,086.86
Over/Under Est: -9.41% -$963,799.14
Over/Under Est: -2.77% -$283,337.38
Amt Left: 7.33% $680,461.76
$10,366,917.78
Over/Under Est: 1.18% $121,031.78
Amt Left: 11.69% $1,084,830.92
Delta: -4.06% -$404,369.16
Over/Under Est: 1.42% $145,980.87
Amt Left: 11.96% $1,109,780.01
Delta: -0.24% -$24,949.09
Subcontractor Percentage Amount
TRAF-TEX, INC. 6.97% $646,961.45
DEPENDABLE FENCE 1.40% $129,949.22
THE LEVY COMPANY, LLC 1.07% $99,318.33
JUAN DEANDA TRUCKING LLC 0.98% $90,964.45
A K FUQUAY CONSTRUCTION 0.79% $73,328.49
TORO BRAVO CONSTRUCTION, LLC 0.72% $66,831.03
RUCOBA & MAYA CONSTRUCTION, LLC 0.67% $62,189.98
TRP CONSTRUCTION GROUP, LLC 0.44% $40,841.18
EGGEMEYER LAND CLEARING, LLC 0.30% $27,846.26
SK CONCRETE SERVICES LLC 0.25% $23,205.22
MUNOZ FOUNDATION DRILLING, INC. 0.20% $18,564.17
MURRAY CONSTRUCTION 0.16% $14,851.34
Total: 13.95% $1,294,851.12

Bid Items & Bid Tabulations

86 Total 0 of 86
FAYETTE  |  IH 10  |  YOAKUM  |  0535-06-049  |  08/03/2023  |  $10,245,886.00  |  F 2B23(083)  |  CONSTRUCT REST AREA  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
CAPITAL EXCAVATION COMPANY
WEBBER, LLC
JOHN REED AND COMPANY, LLC
PREPARING ROW
STA 89.480 $7,100.000 $899.100 $350.000 $10,000.000 $6,000.000
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 18.000 $1,250.000 $550.000 $460.000 $400.000 $300.000
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 22.000 $1,500.000 $880.000 $810.000 $700.000 $600.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 1.000 $3,600.000 $3,960.000 $3,690.000 $2,200.000 $3,000.000
REMOVING CONC (RIPRAP)
CY 8.000 $75.000 $38.500 $127.000 $1,000.000 $30.000
REMOVING CONC (SIDEWALKS)
SY 88.000 $25.000 $24.500 $35.900 $80.000 $10.000
REMOVING CONC (CURB AND GUTTER)
LF 2,143.000 $15.000 $9.400 $11.150 $20.000 $5.000
REMOVING CONC (FLUME)
SY 207.000 $25.000 $24.500 $16.750 $80.000 $20.000
OBLITERATING ABANDONED ROAD
SY 5,009.000 $4.500 $8.200 $4.600 $30.000 $7.000
EXCAVATION (ROADWAY)
CY 19,428.000 $14.000 $12.600 $21.350 $25.000 $22.000
SUBGRADE WIDENING (ORD COMP)
STA 33.230 $1,070.000 $700.000 $2,390.000 $2,500.000 $700.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 2,339.000 $23.000 $11.800 $15.800 $45.000 $20.000
BLADING
STA 89.480 $220.000 $535.000 $740.000 $440.000 $40.000
BLADING
HR 50.000 $190.000 $156.000 $125.000 $250.000 $40.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 40,065.000 $0.500 $0.280 $0.300 $0.400 $0.280
BROADCAST SEED (TEMP) (WARM)
SY 10,017.000 $0.700 $0.250 $0.250 $0.400 $0.250
BROADCAST SEED (TEMP) (COOL)
SY 10,017.000 $0.700 $0.250 $0.250 $0.400 $0.250
VEGETATIVE WATERING
MG 337.200 $45.000 $24.500 $35.350 $50.000 $25.000
FL BS (RDWY DEL)(TY E GR 1-2)(FNL POS)
CY 7,140.000 $95.000 $80.640 $82.500 $175.000 $220.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 514.000 $290.000 $352.000 $350.000 $350.000 $300.000
LIME TRT (SUBGRADE)(6")
SY 43,114.000 $6.000 $3.000 $10.500 $6.000 $3.000
CEMENT
TON 388.000 $300.000 $275.000 $260.000 $250.000 $280.000
CEMENT TREAT (NEW BASE) (6")
SY 42,517.000 $4.500 $3.000 $6.150 $3.000 $3.000
PRIME COAT (MC-30)
GAL 8,512.000 $6.500 $5.850 $4.250 $4.000 $5.000
AGGR(TY-PE GR-3 SAC-B)
CY 501.000 $250.000 $149.320 $223.000 $180.000 $300.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 17,024.000 $6.000 $4.910 $4.250 $12.000 $4.800
CONC PVMT (CONT REINF - CRCP) (10")
SY 31,884.000 $120.000 $155.830 $130.900 $87.000 $110.000
CONC PVMT(CRCP)(TRANSITION SLAB)
SY 120.000 $250.000 $244.740 $260.000 $175.000 $100.000
CEM STABIL BKFL
CY 40.000 $180.000 $241.920 $250.000 $115.000 $150.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 92.000 $950.000 $920.000 $1,210.000 $820.000 $1,200.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 120.000 $350.000 $375.000 $350.000 $316.000 $500.000
RIPRAP (CONC) (CL B) (4")
CY 9.320 $860.000 $752.770 $1,040.000 $697.000 $1,900.000
RC PIPE (CL III)(24 IN)
LF 138.000 $130.000 $194.390 $160.000 $150.000 $150.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 2.000 $1,350.000 $1,618.940 $2,200.000 $2,600.000 $1,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 3.000 $2,340.000 $3,130.960 $2,580.000 $2,200.000 $2,600.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 1.000 $2,760.000 $3,238.960 $5,600.000 $3,180.000 $3,000.000
CLEAN EXIST CULVERTS
EA 4.000 $2,400.000 $1,066.850 $1,610.000 $1,180.000 $5,000.000
REMOV STR (PICNIC AREA)
EA 4.000 $10,000.000 $7,788.790 $6,200.000 $7,500.000 $1,000.000
REMOV STR (SMALL)
EA 4.000 $5,000.000 $13,884.020 $5,200.000 $4,200.000 $4,000.000
MOBILIZATION
LS 1.000 $900,000.000 $402,486.090 $900,000.000 $1,000,000.000 $980,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $3,500.000 $1,785.840 $710.000 $1,200.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 250.000 $55.000 $39.500 $42.650 $45.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 250.000 $12.000 $9.900 $10.700 $16.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 11,145.000 $5.000 $3.500 $3.800 $4.000 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 11,145.000 $1.500 $0.500 $0.550 $1.000 $0.600
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,490.000 $60.000 $32.170 $78.000 $40.000 $90.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 2,490.000 $14.000 $12.840 $9.750 $8.000 $5.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 2,490.000 $75.000 $13.140 $20.900 $10.000 $10.000
CONC CURB (TY II)
LF 3,369.000 $22.000 $16.350 $19.050 $28.000 $8.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,500.000 $950.000 $1,810.000 $2,300.000 $2,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,280.000 $900.000 $1,410.000 $1,500.000 $3,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $9,500.000 $8,250.000 $8,300.000 $12,000.000 $8,000.000
CHAIN LINK FENCE (INSTALL) (6')
LF 2,700.000 $50.000 $28.500 $29.200 $40.000 $15.000
CHAIN LINK FENCE (REMOVE)
LF 3,880.000 $6.400 $6.750 $4.250 $10.000 $2.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 12.000 $6,400.000 $5,251.000 $8,100.000 $5,251.000 $5,260.000
HI MST IL POLE (150 FT)(100 MPH)
EA 2.000 $66,500.000 $65,016.000 $71,000.000 $55,000.000 $65,020.000
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
EA 2.000 $30,000.000 $37,876.000 $43,200.000 $37,876.000 $37,900.000
CONDT (PVC) (SCH 40) (2")
LF 8,875.000 $22.000 $14.600 $15.750 $25.000 $15.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 120.000 $33.000 $34.400 $34.800 $32.000 $35.000
ELEC CONDR (NO.8) BARE
LF 8,995.000 $2.000 $2.100 $2.450 $2.000 $2.300
ELEC CONDR (NO.8) INSULATED
LF 23,780.000 $2.100 $2.190 $2.550 $2.000 $2.300
GROUND BOX TY A (122311)W/APRON
EA 17.000 $1,750.000 $1,450.000 $1,540.000 $1,400.000 $1,450.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 2.000 $8,000.000 $9,653.000 $8,800.000 $10,500.000 $9,653.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $900.000 $700.000 $740.000 $950.000 $900.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 10.000 $525.000 $425.000 $450.000 $600.000 $545.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 4.000 $550.000 $525.000 $550.000 $750.000 $690.000
REMOVE SM RD SN SUP&AM
EA 16.000 $150.000 $100.000 $105.000 $150.000 $130.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 39.000 $53.000 $65.000 $68.400 $50.000 $120.000
INSTL DEL ASSM (D-DW)SZ 2(WC)GND
EA 34.000 $59.000 $65.000 $68.400 $50.000 $150.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 6.000 $111.000 $75.000 $78.900 $65.000 $500.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 1,056.000 $1.600 $1.060 $1.250 $1.500 $2.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 1,177.000 $1.200 $1.420 $1.700 $2.000 $3.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,459.000 $1.000 $1.420 $1.700 $1.500 $2.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 917.000 $4.000 $7.000 $8.400 $4.000 $4.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 7,768.000 $0.500 $0.770 $0.950 $1.000 $1.250
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 5,162.000 $0.500 $0.770 $0.950 $1.000 $1.250
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $250.000 $725.000 $870.000 $275.000 $287.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 2.000 $310.000 $725.000 $870.000 $275.000 $420.000
REFL PAV MRKR TY II-C-R
EA 155.000 $8.000 $7.770 $9.350 $7.000 $10.000
ELIM EXT PAV MRK & MRKS (6")
LF 2,517.000 $5.900 $0.770 $0.950 $1.000 $0.560
D-GR HMA TY-B PG64-22
TON 1,630.000 $150.000 $109.700 $117.000 $140.000 $145.000
D-GR HMA TY-D SAC-B PG70-22
TON 4,616.000 $150.000 $115.900 $133.000 $170.000 $163.000
TACK COAT
GAL 731.000 $5.000 $4.090 $4.250 $16.000 $4.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,000.000 $9,000.000 $21,800.000 $13,316.720 $10,000.000
TMA (STATIONARY)
DAY 20.000 $220.000 $400.000 $171.000 $410.000 $1,000.000
TMA (MOBILE OPERATION)
DAY 20.000 $410.000 $500.000 $800.000 $750.000 $1,000.000
Totals: $10,245,886.000 $9,282,086.874 $9,962,548.620 $10,366,917.780 $10,391,866.870