Bid Cobra

FAYETTE US 77 (0268-01-056)

Items: 97

County: FAYETTE
Length: N/A
Highway: US 77
District: YOAKUM
Control Number: 0268-01-056
DBE Goal: N/A
Project: F 2022(658)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $3,824,673.10
Date: 12/01/2022 (3 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
COVEY MORROW
CHASE HERMES
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$3,824,673.10
$3,760,967.65
Over/Under Est: -1.67% -$63,705.45
Over/Under Est: 5.93% $226,646.99
Amt Left: 7.72% $290,352.44
$4,426,087.51
Over/Under Est: 15.72% $601,414.41
Amt Left: 17.68% $665,119.86
Delta: -9.25% -$374,767.42
Over/Under Est: 15.88% $607,240.94
Amt Left: 17.84% $670,946.39
Delta: -0.13% -$5,826.53
Over/Under Est: 26.62% $1,018,112.66
Amt Left: 28.76% $1,081,818.11
Delta: -9.27% -$410,871.72
Over/Under Est: 37.16% $1,421,157.97
Amt Left: 39.48% $1,484,863.42
Delta: -8.32% -$403,045.31
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 2.40% $90,263.22
WILLOW CITY SIGN & RAIL, INC. 1.26% $47,388.19
BROCK CONSTRUCTION, LLC 0.70% $26,326.77
LONESTAR TRAFFIC SAFETY, LLC 0.42% $15,796.06
CEN TEX HYDROSEED, INC. 0.25% $9,402.42
WEST TEXAS ROCK RESOURCES, LLC 0.15% $5,641.45
Total: 5.18% $194,818.11

Bid Items & Bid Tabulations

97 Total 0 of 97
FAYETTE  |  US 77  |  YOAKUM  |  0268-01-056  |  12/01/2022  |  $3,824,673.10  |  F 2022(658)  |  REHAB EXIST ROADWAY  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
HUNTER INDUSTRIES, LTD.
DUNN SERVICES, INC.
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
ACME BRIDGE COMPANY, INC.
PREPARING ROW
STA 56.250 $2,000.000 $1,000.000 $767.360 $126.700 $950.000 $1,000.000 $3,500.000
REMOVING CONC (RIPRAP)
SY 16.000 $25.000 $50.000 $75.240 $15.640 $35.000 $70.000 $64.100
REMOVING CONC (DRIVEWAYS)
SY 50.000 $20.000 $25.000 $37.620 $46.000 $17.500 $75.000 $34.900
EXCAVATION (ROADWAY)
CY 6,524.000 $15.000 $12.500 $23.040 $13.500 $19.000 $16.300 $12.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 5,812.000 $12.000 $12.500 $23.040 $24.100 $29.000 $24.000 $15.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 124.000 $30.000 $35.000 $40.500 $26.100 $86.000 $76.000 $48.400
BLADING
HR 50.000 $100.000 $100.000 $105.300 $125.000 $80.000 $130.000 $138.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 43,225.000 $0.250 $0.150 $0.210 $0.220 $0.200 $0.170 $0.310
DRILL SEEDING (TEMP) (WARM)
SY 10,806.000 $0.250 $0.150 $0.180 $0.220 $0.170 $0.160 $0.260
DRILL SEEDING (TEMP) (COOL)
SY 10,806.000 $0.250 $0.150 $0.180 $0.250 $0.170 $0.160 $0.260
VEGETATIVE WATERING
MG 363.840 $25.000 $12.500 $17.100 $55.000 $20.000 $48.000 $37.800
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 4,702.000 $75.000 $78.000 $83.570 $110.520 $94.000 $80.850 $125.000
LIME TRT (EXST MATL) (6")
SY 17,783.000 $4.000 $3.500 $2.630 $6.390 $3.000 $1.950 $1.600
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 127.000 $180.000 $250.000 $270.000 $284.500 $210.000 $221.500 $379.000
PRIME COAT (MC-30)
GAL 3,214.000 $4.500 $5.000 $4.790 $5.460 $6.000 $6.800 $5.400
AGGR(TY-PE GR-3 SAC-B)
CY 189.000 $200.000 $150.000 $144.670 $210.860 $150.000 $177.000 $172.000
AGGR(TY-PE GR-4 SAC-B)
CY 328.000 $120.000 $150.000 $144.940 $132.840 $194.000 $187.000 $146.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 20,963.000 $4.250 $4.000 $4.600 $5.190 $4.300 $4.400 $4.850
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 500.000 $65.000 $70.000 $98.100 $64.780 $78.000 $121.000 $203.000
PLANE ASPH CONC PAV (6")
SY 7,939.000 $5.000 $5.000 $4.790 $5.470 $8.250 $4.000 $7.500
PLAN & TEXT ASPH CONC PAV (0" TO 10")
SY 22,046.000 $6.000 $3.000 $5.870 $2.100 $8.150 $3.720 $8.600
CEM STABIL BKFL
CY 95.400 $140.000 $185.000 $208.950 $170.740 $230.000 $227.000 $222.000
CUT & RESTORING PAV
SY 554.000 $100.000 $90.000 $125.220 $575.000 $92.000 $72.000 $121.000
TRENCH EXCAVATION PROTECTION
LF 85.000 $10.000 $20.000 $12.350 $21.120 $32.000 $24.000 $50.000
TEMPORARY SPL SHORING
SF 700.000 $20.000 $50.000 $5.240 $41.060 $35.000 $110.000 $50.000
RIPRAP (CONC)(5 IN)
CY 32.400 $500.000 $650.000 $517.640 $799.690 $750.000 $738.000 $683.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 36.000 $220.000 $200.000 $207.900 $128.560 $250.000 $227.000 $240.000
RIPRAP (CONC)(DISSIPATER)
CY 1.000 $1,500.000 $1,500.000 $3,139.440 $3,000.000 $2,200.000 $5,600.000 $3,780.000
CMP (GAL STL 24 IN)
LF 20.000 $90.000 $100.000 $131.250 $292.110 $125.000 $170.000 $98.600
CONC BOX CULV (3 FT X 3 FT)
LF 65.000 $425.000 $400.000 $840.530 $415.610 $470.000 $568.000 $508.000
CONC BOX CULV (4 FT X 2 FT)
LF 67.000 $550.000 $400.000 $774.850 $330.500 $460.000 $682.000 $509.000
CONC BOX CULV (10 FT X 5 FT)
LF 122.000 $950.000 $1,500.000 $1,675.880 $1,418.000 $1,500.000 $1,912.000 $1,820.000
RC PIPE (CL III)(18 IN)
LF 278.000 $75.000 $85.000 $86.030 $150.550 $80.000 $73.700 $92.600
RC PIPE (CL III)(24 IN)
LF 204.000 $90.000 $120.000 $108.160 $208.250 $100.000 $165.000 $127.000
SET (TY I)(S=10 FT)(HW=6FT)(4:1)(C)
EA 4.000 $14,000.000 $20,000.000 $17,723.330 $5,800.000 $18,000.000 $26,740.000 $20,100.000
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 1.000 $6,000.000 $15,000.000 $16,557.540 $3,780.000 $19,000.000 $9,660.000 $13,100.000
SET (TY I)(S= 3 FT)(HW= 7 FT)(4:1) (C)
EA 1.000 $7,000.000 $35,000.000 $31,782.240 $11,287.020 $37,000.000 $34,000.000 $24,700.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (C)
EA 2.000 $8,000.000 $10,000.000 $18,657.500 $5,588.480 $13,000.000 $12,000.000 $11,300.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 14.000 $1,200.000 $1,500.000 $1,329.270 $2,058.750 $2,100.000 $1,364.000 $2,510.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 1.000 $1,400.000 $1,750.000 $2,623.900 $2,120.000 $2,000.000 $2,273.000 $2,640.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 7.000 $1,500.000 $1,750.000 $2,098.910 $2,628.000 $2,300.000 $2,273.000 $2,880.000
REMOV STR (SMALL)
EA 17.000 $800.000 $1,000.000 $2,593.450 $851.840 $1,700.000 $1,420.000 $3,000.000
MOBILIZATION
LS 1.000 $345,000.000 $370,000.000 $322,315.350 $395,500.000 $240,000.000 $620,000.000 $498,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $4,000.000 $5,000.000 $4,044.580 $3,600.000 $9,000.000 $11,650.000 $10,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 40.000 $40.000 $50.000 $42.000 $33.250 $65.000 $51.000 $62.700
ROCK FILTER DAMS (REMOVE)
LF 40.000 $10.000 $10.000 $15.750 $11.330 $13.000 $17.000 $12.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 820.000 $4.000 $5.000 $4.720 $3.970 $5.500 $5.680 $5.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 820.000 $1.000 $1.000 $1.050 $1.650 $1.000 $2.200 $1.300
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 90.000 $50.000 $75.000 $100.000 $34.750 $50.000 $21.400 $16.300
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 540.000 $40.000 $75.000 $40.000 $48.610 $20.000 $21.400 $21.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 120.000 $40.000 $75.000 $90.000 $68.670 $25.000 $21.400 $21.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 90.000 $25.000 $15.000 $90.000 $15.130 $50.000 $21.400 $14.100
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 540.000 $20.000 $15.000 $20.000 $15.000 $18.000 $21.400 $17.300
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 120.000 $20.000 $15.000 $70.000 $20.000 $24.000 $21.400 $17.300
DRIVEWAYS (CONC)
SY 98.000 $80.000 $100.000 $104.890 $101.250 $145.000 $170.000 $147.000
DRIVEWAYS (ACP)
SY 590.000 $100.000 $35.000 $43.920 $143.600 $74.000 $63.000 $83.600
DRIVEWAYS (SURF TREAT)
SY 751.000 $35.000 $25.000 $31.500 $48.560 $49.000 $51.000 $88.200
RUMBLE STRIPS (SHOULDER)
LF 8,680.000 $0.500 $0.750 $0.650 $0.150 $0.600 $0.700 $0.470
RUMBLE STRIPS (CENTERLINE)
LF 4,340.000 $0.500 $0.750 $1.010 $0.180 $0.750 $0.700 $0.470
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $2.500 $5.000 $3.300 $2.240 $4.300 $6.000 $3.450
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $500.000 $330.000 $1,653.720 $300.000 $340.000 $345.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $500.000 $1,000.000 $935.000 $795.250 $500.000 $1,150.000 $977.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $10,000.000 $8,305.000 $8,900.000 $7,500.000 $10,850.000 $8,680.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 9.000 $250.000 $300.000 $175.000 $257.950 $300.000 $324.000 $402.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $600.000 $550.000 $640.000 $677.590 $550.000 $597.000 $877.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $750.000 $700.000 $675.000 $848.000 $700.000 $767.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $800.000 $800.000 $750.000 $863.000 $800.000 $852.000 $1,120.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,000.000 $950.000 $950.000 $1,030.000 $1,000.000 $1,050.000 $1,300.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 19.000 $400.000 $350.000 $400.000 $442.400 $350.000 $381.000 $650.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $450.000 $500.000 $425.000 $655.150 $400.000 $443.000 $715.000
REMOVE SM RD SN SUP&AM
EA 34.000 $75.000 $100.000 $50.000 $84.470 $110.000 $97.000 $115.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 3.000 $50.000 $35.000 $25.000 $28.280 $32.000 $34.000 $20.700
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 8.000 $70.000 $70.000 $70.000 $133.630 $70.000 $74.000 $63.200
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 80.000 $5.000 $2.000 $1.600 $0.250 $1.600 $1.420 $1.650
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 26,310.000 $0.400 $0.350 $0.340 $0.340 $0.340 $0.590 $0.360
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 38,660.000 $0.400 $0.350 $0.340 $0.400 $0.340 $0.590 $0.360
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 18,525.000 $0.650 $0.800 $0.770 $0.900 $0.770 $1.110 $0.800
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 24,700.000 $0.650 $0.800 $0.770 $0.850 $0.770 $1.110 $0.800
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 24.000 $2.000 $1.250 $1.660 $1.500 $1.310 $1.000 $2.350
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,176.000 $1.500 $1.250 $1.660 $1.530 $1.310 $1.000 $1.800
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 225.000 $2.000 $2.000 $1.600 $0.950 $1.600 $2.220 $1.650
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 28.000 $15.000 $25.000 $25.000 $16.160 $25.000 $12.500 $26.100
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 7.000 $30.000 $55.000 $52.000 $15.000 $52.000 $45.450 $54.400
REFL PAV MRKR TY I-C
EA 12.000 $20.000 $8.000 $7.770 $3.230 $7.800 $8.180 $8.100
REFL PAV MRKR TY II-A-A
EA 167.000 $4.000 $8.000 $7.770 $3.430 $7.800 $6.820 $8.100
ELIM EXT PAV MRK & MRKS (4")
LF 4,976.000 $1.000 $2.000 $1.060 $0.430 $5.000 $1.700 $3.200
D-GR HMA TY-B PG64-22
TON 7,360.000 $100.000 $94.000 $92.340 $96.360 $114.000 $123.650 $121.000
D-GR HMA TY-D SAC-B PG70-22
TON 6,743.000 $110.000 $97.000 $100.980 $120.000 $128.000 $127.550 $138.000
TACK COAT
GAL 4,075.000 $4.000 $4.000 $4.010 $3.100 $3.000 $4.550 $4.750
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $7,500.000 $7,500.000 $10,000.000 $500.000 $4,000.000 $3,000.000 $21,500.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $10,000.000 $11,000.000 $7,500.000 $8,000.000 $12,000.000 $8,200.000 $5,020.000
TMA (STATIONARY)
DAY 20.000 $300.000 $300.000 $500.000 $265.000 $500.000 $500.000 $71.800
TMA (MOBILE OPERATION)
DAY 20.000 $250.000 $350.000 $1,000.000 $295.000 $500.000 $940.000 $640.000
HPPM-RIB W/RET REQ TYI(W)4"(BRK)100MIL
LF 20.000 $0.850 $1.100 $1.060 $1.000 $1.100 $1.130 $1.100
HPPM-RIB W/RET REQ TYI(W)4"(SLD)100MIL
LF 15,840.000 $0.850 $1.100 $0.770 $0.720 $0.770 $0.850 $0.800
HPPM-RIB W/RET REQ TYI(Y)4"(BRK)100MIL
LF 1,387.000 $0.850 $1.100 $1.060 $0.930 $1.100 $0.900 $1.100
HPPM-RIB W/RET REQ TYI(Y)4"(SLD)100MIL
LF 7,834.000 $0.850 $1.100 $1.060 $0.900 $1.100 $0.850 $1.100
Totals: $3,824,673.100 $3,760,967.650 $4,051,320.100 $4,426,087.527 $4,431,914.040 $4,842,785.760 $5,245,831.072