Bid Cobra

FAYETTE SH 159 (0267-02-043)

Items: 102

County: FAYETTE
Length: 0.3190 MILES
Highway: SH 159
District: YOAKUM
Control Number: 0267-02-043
DBE Goal: 5.0%
Project: BR 2025(849)
Guaranty: $81,000.00
Time: 224 WORKING DAYS
Engineer's Estimate: $4,057,944.10
Date: 07/01/2025 (11 months ago)
Contract Number: 7253009
Type: BRIDGE REPLACEMENT
Project ID: A00206338
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (10)
E
Engineer's Estimate
$4,057,944.10
$4,282,480.36
Over/Under Est: 5.53% $224,536.26
Over/Under Est: 6.75% $273,936.18
Amt Left: 1.15% $49,399.92
$4,565,294.71
Over/Under Est: 12.5% $507,350.61
Amt Left: 6.6% $282,814.35
Delta: -5.39% -$233,414.43
Over/Under Est: 12.88% $522,696.32
Amt Left: 6.96% $298,160.06
Delta: -0.34% -$15,345.71
Over/Under Est: 13.48% $546,963.67
Amt Left: 7.53% $322,427.41
Delta: -0.53% -$24,267.35
$4,895,500.99
Over/Under Est: 20.64% $837,556.89
Amt Left: 14.31% $613,020.63
Delta: -6.31% -$290,593.22
$5,063,886.08
Over/Under Est: 24.79% $1,005,941.98
Amt Left: 18.25% $781,405.72
Delta: -3.44% -$168,385.09
Over/Under Est: 30.23% $1,226,649.90
Amt Left: 23.4% $1,002,113.64
Delta: -4.36% -$220,707.92
Over/Under Est: 37.4% $1,517,615.90
Amt Left: 30.19% $1,293,079.64
Delta: -5.51% -$290,966.00
Over/Under Est: 47.78% $1,938,955.90
Amt Left: 40.03% $1,714,419.64
Delta: -7.56% -$421,340.00
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 10.71% $458,653.65
M & D FOUNDATION DRILLING INDUSTRIES, INC. 7.60% $325,468.51
FARR FOUNDATION, INC. 2.04% $87,362.60
DIIBS SPECIALISTS, LLC 1.16% $49,676.77
JB PINNACLE GROUP, LLC 1.14% $48,820.28
LONE STAR EROSION CONTROL 1.14% $48,820.28
STRIPE IT UP, LLC 1.03% $44,109.55
CND CONTRACTING, LLC 0.58% $24,838.39
DALLAS LITE AND BARRICADE, INC. 0.45% $19,271.16
INTERSTATE BARRICADES & MARKINGS, INC. 0.29% $12,419.19
SK CONCRETE SERVICES LLC 0.11% $4,710.73
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 26.25% $1,124,151.11

Bid Items & Bid Tabulations

102 Total 0 of 102
FAYETTE  |  SH 159  |  YOAKUM  |  0267-02-043  |  07/01/2025  |  $4,057,944.10  |  BR 2025(849)  |  BRIDGE REPL  |  224 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACME BRIDGE COMPANY, INC.
KNIFE RIVER CORPORATION - SOUTH
RELMCO, INC.
HUNTER INDUSTRIES, LTD.
E-Z BEL CONSTRUCTION, LLC
C. E. BARKER, LTD.
STX CIVIL
TEXAS MATERIALS GROUP, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
URBAN INFRACONSTRUCTION LLC
PREPARING ROW
STA 8.000 $3,500.000 $4,720.000 $2,689.000 $5,500.000 $4,026.500 $3,900.000 $60,000.000 $2,900.000 $5,900.000 $4,500.000 $20,000.000
REMOV CONC (RIPRAP)
SY 491.000 $17.000 $14.600 $14.500 $20.000 $23.800 $1.000 $9.220 $18.000 $56.000 $15.000 $25.000
RMV (12") TRT/UNTRT BASE & ASPH PAV
CY 909.000 $9.500 $15.500 $16.800 $20.000 $13.600 $30.000 $9.220 $23.000 $32.000 $60.000 $35.000
RMV (22") TRT/UNTRT BASE & ASPH PAV
CY 286.300 $17.000 $26.400 $17.800 $20.000 $27.200 $16.000 $9.220 $36.000 $45.000 $60.000 $25.000
EXCAV (ROADWAY)
CY 1,329.000 $17.500 $11.700 $18.650 $19.000 $23.800 $18.000 $18.290 $22.000 $24.000 $15.000 $30.000
EXCAV (CHANNEL)
CY 1,519.000 $13.000 $16.700 $8.600 $19.000 $23.800 $22.000 $18.290 $18.000 $30.000 $12.000 $40.000
EMBANK (FNL)(OC)(TY C)
CY 10,430.000 $22.000 $17.400 $13.000 $21.000 $29.400 $21.000 $30.480 $38.000 $29.000 $25.000 $40.000
BLADING
HR 40.000 $100.000 $48.400 $142.000 $150.000 $103.500 $150.000 $106.690 $60.000 $180.500 $20.000 $200.000
FURN & PLACE TOPSOIL (VEH)
CY 211.000 $11.000 $18.100 $43.000 $30.000 $27.000 $64.000 $6.350 $40.000 $59.000 $50.000 $52.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 5,921.000 $0.500 $0.390 $0.180 $0.400 $0.450 $0.170 $1.020 $0.500 $0.500 $1.500 $0.200
BROADCAST SEED (TEMP_WARM)
SY 1,480.000 $0.500 $0.590 $0.180 $0.610 $1.200 $0.170 $1.020 $0.500 $0.600 $1.000 $0.200
BROADCAST SEED (TEMP_COOL)
SY 1,480.000 $0.500 $0.590 $0.180 $0.610 $1.200 $0.170 $1.020 $0.500 $0.600 $1.000 $0.200
VEGETATIVE WATERING
TGL 51.000 $70.000 $38.200 $56.000 $50.000 $20.400 $81.000 $106.690 $60.000 $26.250 $1.000 $215.000
SOIL RET BLKT(SL_MOD_SAND_SHORT)
SY 3,706.000 $2.500 $1.400 $2.000 $1.430 $2.500 $2.000 $10.160 $4.000 $1.500 $3.000 $2.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 1,385.300 $95.000 $121.000 $97.700 $150.000 $99.180 $165.000 $82.880 $96.000 $101.000 $70.000 $135.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 51.500 $300.000 $223.000 $360.700 $250.000 $550.000 $400.000 $355.620 $608.000 $372.000 $350.000 $430.000
LIME TRT (EXIST MATL)(8")
SY 3,210.000 $4.500 $5.100 $14.600 $8.000 $4.600 $10.000 $7.110 $10.000 $15.000 $15.000 $20.000
CEMENT
TON 31.600 $215.000 $326.000 $238.000 $250.000 $330.000 $433.000 $304.820 $285.000 $291.000 $350.000 $465.000
CEMENT TRT (EXIST MATL)(8")
SY 3,210.000 $4.250 $3.750 $7.500 $8.000 $4.600 $8.000 $7.110 $10.000 $8.000 $15.000 $15.000
PRIME COAT (MC-30)
GAL 1,184.000 $8.000 $6.800 $9.000 $5.500 $10.100 $6.000 $6.100 $8.000 $6.500 $10.000 $7.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 83.800 $350.000 $317.000 $386.000 $200.000 $366.350 $223.000 $226.580 $514.000 $466.000 $650.000 $260.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 3,657.000 $6.000 $5.800 $6.750 $6.000 $7.800 $5.000 $4.570 $7.500 $6.000 $10.000 $5.000
D-GR HMA TY-B PG70-22
TON 944.600 $95.000 $141.000 $128.000 $110.000 $141.900 $133.000 $135.140 $173.000 $150.000 $200.000 $145.000
D-GR HMA TY-D SAC-B PG70-22
TON 1,507.300 $110.000 $157.000 $139.000 $130.000 $130.200 $148.000 $150.380 $174.000 $175.000 $175.000 $150.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 685.100 $115.000 $157.000 $149.000 $120.000 $146.300 $148.000 $150.380 $235.000 $210.000 $200.000 $170.000
TACK COAT
GAL 1,702.000 $5.000 $5.300 $4.000 $6.000 $5.090 $5.000 $5.080 $4.500 $4.000 $8.000 $6.000
CEM STABIL BKFL
CY 578.000 $100.000 $185.000 $175.300 $180.000 $170.000 $340.000 $133.100 $180.000 $230.000 $200.000 $230.000
TRENCH EXCAVATION PROTECTION
LF 365.000 $10.000 $4.400 $14.600 $15.000 $9.000 $1.000 $20.320 $15.000 $16.000 $5.000 $14.000
TEMPORARY SPL SHORING
SF 6,981.000 $20.000 $23.300 $27.850 $26.000 $29.000 $17.000 $3.560 $60.000 $39.900 $35.000 $35.000
DRILL SHAFT (18 IN)
LF 230.000 $160.000 $66.600 $83.300 $300.000 $162.890 $98.000 $183.100 $153.000 $92.000 $130.000 $195.000
DRILL SHAFT (36 IN)
LF 1,610.000 $295.000 $246.000 $260.500 $325.000 $286.340 $384.000 $274.000 $270.000 $293.000 $230.000 $285.000
CL C CONC (ABUT)
CY 100.400 $1,150.000 $1,000.000 $1,393.400 $1,043.000 $1,650.000 $1,700.000 $1,527.380 $1,400.000 $1,635.000 $1,900.000 $1,950.000
CL C CONC (CAP)
CY 68.900 $1,150.000 $1,350.000 $1,336.000 $1,337.000 $1,950.000 $1,600.000 $1,290.410 $1,900.000 $1,985.000 $2,000.000 $2,000.000
CL C CONC (COLUMN)
CY 37.600 $1,300.000 $1,560.000 $1,222.000 $1,337.000 $1,050.000 $1,200.000 $1,379.970 $1,900.000 $1,709.000 $2,200.000 $2,000.000
REINF CONC SLAB
SF 10,175.000 $21.000 $27.000 $37.000 $27.550 $30.000 $27.000 $25.490 $24.000 $41.000 $40.000 $25.000
PRESTR CONC GIRDER (TX34)
LF 1,473.500 $190.000 $247.000 $234.000 $200.000 $215.000 $275.000 $192.420 $275.000 $251.000 $300.000 $230.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 16.000 $185.000 $230.000 $326.000 $300.000 $200.000 $230.000 $144.790 $160.000 $203.000 $500.000 $240.000
RIPRAP (STONE PROTECTION)(36 IN)
CY 3,072.000 $230.000 $246.000 $200.000 $205.000 $185.000 $143.000 $173.830 $170.000 $180.000 $200.000 $288.000
RAIL (TY SSTR)
LF 450.000 $80.000 $127.000 $144.000 $95.000 $104.400 $96.000 $169.680 $120.000 $167.000 $120.000 $100.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 151.000 $190.000 $257.000 $248.000 $215.000 $263.870 $280.000 $213.880 $287.000 $281.000 $250.000 $270.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $6,000.000 $7,910.000 $7,085.000 $11,750.000 $9,500.000 $16,491.000 $5,613.730 $6,633.000 $3,400.000 $6,000.000 $3,500.000
INLET (COMPL)(PSL)(RH)(3FTX3FT)
EA 1.000 $5,500.000 $6,390.000 $6,551.000 $10,600.000 $9,000.000 $13,045.000 $5,613.730 $7,600.000 $5,700.000 $6,000.000 $5,800.000
HEADWALL (CH - FW - 45) (DIA= 18 IN)
EA 1.000 $7,000.000 $4,190.000 $12,300.000 $5,350.000 $5,500.000 $13,504.000 $11,633.890 $8,000.000 $6,200.000 $15,000.000 $6,350.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 1.000 $1,300.000 $2,020.000 $2,078.000 $2,200.000 $1,300.000 $5,160.000 $1,447.890 $1,750.000 $1,500.000 $3,000.000 $1,045.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $1,500.000 $2,370.000 $2,008.000 $2,200.000 $2,400.000 $5,160.000 $1,549.490 $2,500.000 $2,900.000 $3,000.000 $2,900.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $1,950.000 $2,500.000 $2,388.000 $2,200.000 $3,000.000 $5,161.000 $1,701.900 $2,800.000 $4,000.000 $4,000.000 $4,100.000
ADJUSTING MANHOLES
EA 2.000 $1,000.000 $903.000 $1,951.000 $1,200.000 $3,250.000 $2,188.000 $533.430 $1,800.000 $2,808.000 $3,000.000 $2,900.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $40,000.000 $26,400.000 $31,521.000 $150,000.000 $37,799.890 $27,896.000 $50,803.000 $30,000.000 $63,000.000 $250,000.000 $75,000.000
REMOV STR (SMALL)
EA 6.000 $950.000 $335.000 $860.000 $3,500.000 $4,500.000 $2,000.000 $2,667.160 $500.000 $1,700.000 $2,000.000 $5,500.000
MOBILIZATION
LS 1.000 $275,000.000 $325,000.000 $368,791.000 $395,000.000 $415,109.770 $400,000.000 $450,000.000 $400,200.000 $527,000.000 $500,000.000 $555,069.150
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $3,500.000 $4,890.000 $3,685.000 $4,500.000 $3,207.310 $2,500.000 $4,191.250 $3,200.000 $2,100.000 $6,700.000 $13,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $6,740.000 $8,184.000 $15,000.000 $7,720.030 $3,500.000 $15,240.900 $8,000.000 $13,500.000 $30,000.000 $20,000.000
TMA (STATIONARY)
DAY 20.000 $250.000 $139.000 $578.000 $250.000 $154.400 $150.000 $1,016.060 $60.000 $309.000 $300.000 $875.000
TMA (MOBILE OPERATION)
DAY 20.000 $350.000 $351.000 $927.000 $250.000 $154.400 $100.000 $152.410 $60.000 $529.000 $300.000 $1,635.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 484.000 $35.000 $54.000 $48.000 $55.000 $46.300 $44.000 $50.800 $40.000 $56.000 $1.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 484.000 $10.000 $13.000 $16.000 $13.200 $14.700 $15.000 $20.320 $10.000 $13.500 $1.000 $18.000
SANDBAGS FOR EROSION CONTROL
EA 30.000 $10.000 $21.600 $24.000 $22.000 $10.000 $23.000 $20.320 $2.500 $22.500 $1.000 $26.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,720.000 $4.000 $4.150 $3.000 $4.240 $4.000 $3.000 $5.080 $5.000 $4.500 $1.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,720.000 $1.000 $1.200 $1.500 $1.210 $1.000 $1.000 $2.030 $1.000 $1.250 $1.000 $1.500
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,170.000 $40.000 $22.800 $24.750 $22.000 $60.000 $50.000 $81.790 $95.000 $41.800 $120.000 $98.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,170.000 $15.000 $6.300 $5.000 $11.000 $10.000 $10.000 $10.670 $20.000 $10.200 $15.000 $20.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,170.000 $15.000 $23.200 $24.750 $22.000 $25.000 $17.000 $10.670 $25.000 $29.010 $50.000 $17.000
DRIVEWAYS (SURF TREAT)
SY 397.000 $35.000 $48.500 $51.000 $100.000 $49.500 $39.000 $19.310 $50.000 $78.500 $15.000 $22.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 4,213.000 $1.000 $0.530 $0.400 $0.550 $0.940 $1.000 $5.080 $1.250 $1.250 $1.250 $0.550
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 2,107.000 $1.000 $0.530 $0.600 $0.550 $1.410 $1.000 $5.080 $1.880 $1.250 $1.250 $0.550
FILL MILLED ASPH RMBL STRIP(CENTERLINE)
LF 1,052.000 $3.000 $2.850 $10.000 $5.500 $3.400 $10.000 $5.080 $2.000 $21.750 $3.000 $7.000
MTL W-BEAM GD FEN (TIM POST)
LF 525.000 $25.000 $27.300 $27.000 $27.500 $24.630 $25.000 $35.560 $30.000 $27.000 $25.000 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,200.000 $2,390.000 $2,011.000 $2,035.000 $1,891.000 $1,891.000 $2,540.150 $2,290.000 $2,475.000 $1,600.000 $2,100.000
REMOVE METAL BEAM GUARD FENCE
LF 700.000 $2.400 $1.150 $2.700 $2.750 $3.500 $4.000 $5.080 $4.000 $1.200 $2.000 $1.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $150.000 $228.000 $271.000 $275.000 $275.000 $450.000 $508.030 $332.000 $225.000 $500.000 $230.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 2.000 $250.000 $228.000 $271.000 $275.000 $345.680 $275.000 $508.030 $332.000 $225.000 $300.000 $230.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,800.000 $3,410.000 $3,261.000 $3,300.000 $3,292.000 $3,292.000 $3,556.210 $3,980.000 $3,400.000 $3,000.000 $3,400.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 4.000 $900.000 $1,140.000 $1,630.500 $1,650.000 $1,325.000 $1,325.000 $1,524.090 $1,600.000 $1,123.000 $1,200.000 $1,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $225.000 $910.000 $271.750 $275.000 $275.000 $275.000 $1,016.060 $333.000 $898.500 $500.000 $925.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,200.000 $1,140.000 $995.000 $800.000 $800.000 $800.000 $2,540.150 $1,210.000 $1,123.000 $2,500.000 $1,100.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $900.000 $910.000 $995.000 $500.000 $700.000 $499.000 $1,016.060 $1,150.000 $898.500 $1,200.000 $925.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $9,000.000 $9,100.000 $3,001.000 $8,500.000 $8,125.000 $8,125.000 $35,562.100 $9,075.000 $9,000.000 $10,000.000 $9,500.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $450.000 $635.000 $603.000 $550.000 $747.610 $500.000 $563.910 $500.000 $674.000 $500.000 $695.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $300.000 $317.000 $349.000 $330.000 $747.610 $300.000 $326.160 $500.000 $337.050 $800.000 $350.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 5.000 $350.000 $455.000 $777.000 $508.750 $801.230 $463.000 $726.480 $570.000 $482.850 $1,200.000 $500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $410.000 $476.000 $777.000 $632.500 $1,037.370 $575.000 $726.480 $650.000 $505.000 $1,200.000 $520.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 1.000 $250.000 $317.000 $598.000 $275.000 $443.410 $250.000 $558.830 $350.000 $337.000 $1,200.000 $350.000
REMOVE SM RD SN SUP&AM
EA 5.000 $100.000 $106.000 $136.000 $110.000 $103.120 $170.000 $127.010 $100.000 $112.000 $200.000 $120.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 20.000 $15.000 $21.200 $24.000 $26.400 $53.620 $24.000 $12.190 $35.000 $22.500 $30.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 37.000 $26.000 $21.200 $27.000 $48.400 $62.900 $44.000 $28.450 $60.000 $22.500 $30.000 $25.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 7,644.000 $1.000 $1.050 $1.090 $1.100 $1.060 $1.000 $2.540 $1.210 $1.250 $2.000 $1.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 7,644.000 $21.000 $1.050 $1.090 $1.100 $1.060 $1.000 $2.540 $1.210 $1.250 $2.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 510.000 $2.000 $1.650 $1.090 $6.000 $1.630 $0.500 $2.030 $2.000 $1.000 $5.000 $1.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 4,213.000 $1.000 $2.100 $1.850 $2.200 $2.750 $2.000 $1.730 $2.420 $3.250 $2.000 $2.500
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 535.000 $1.000 $3.150 $1.850 $3.300 $3.400 $3.000 $1.730 $3.630 $3.250 $3.000 $3.500
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 1,391.000 $1.000 $2.100 $1.850 $2.200 $2.750 $2.000 $1.730 $2.420 $3.250 $3.000 $2.500
PAVEMENT SLER 6"
LF 420.000 $0.500 $2.100 $0.540 $2.200 $2.500 $2.000 $0.510 $2.420 $1.000 $1.000 $2.500
REFL PAV MRKR TY II-A-A
EA 51.000 $8.000 $6.100 $8.720 $6.330 $5.200 $6.000 $8.150 $6.960 $19.000 $20.000 $6.650
ELIM EXT PM & MRKS (4")
LF 4,630.000 $2.000 $1.050 $3.530 $1.100 $0.770 $1.000 $3.300 $1.210 $2.150 $2.000 $1.000
REMOVE AND REPLACE WOOD FENCE
LF 205.000 $45.000 $26.400 $30.800 $50.000 $40.000 $50.000 $60.960 $80.000 $60.500 $30.000 $85.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $5,500.000 $7,300.000 $14,131.000 $12,500.000 $5,146.690 $2,500.000 $10,160.600 $2,100.000 $14,050.000 $16,000.000 $40,100.000
1
RC PIPE (CL III)(18 IN)
LF 365.000 $95.000 $0.000 $0.000 $0.000 $115.000 $94.000 $0.000 $107.000 $0.000 $80.000 $70.000
1
RC PIPE (CL III)(24 IN)
LF 104.000 $110.000 $0.000 $0.000 $0.000 $105.000 $111.000 $0.000 $131.000 $0.000 $95.000 $175.000
1
RC PIPE (CL III)(30 IN)
LF 28.000 $130.000 $0.000 $0.000 $0.000 $135.000 $139.000 $0.000 $176.000 $0.000 $150.000 $230.000
1A
THERMOPLASTIC PIPE (PP) (18")
LF 365.000 $95.000 $50.000 $73.000 $30.800 $0.000 $0.000 $127.010 $0.000 $93.000 $0.000 $0.000
1A
THERMOPLASTIC PIPE (PP) (24")
LF 104.000 $110.000 $68.200 $74.000 $74.200 $0.000 $0.000 $132.090 $0.000 $149.500 $0.000 $0.000
1A
THERMOPLASTIC PIPE (PP) (30")
LF 28.000 $130.000 $93.600 $139.000 $95.200 $0.000 $0.000 $137.170 $0.000 $195.500 $0.000 $0.000
Totals: $4,107,699.100 $4,282,480.360 $4,331,880.280 $4,565,294.710 $4,580,640.424 $4,604,907.770 $4,895,501.005 $5,063,886.080 $5,284,594.000 $5,575,560.000 $5,996,900.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
Total: $1,500.00