PREPARING ROW
|
STA
|
1.000
|
$2,500.000
|
$2,700.000
|
$3,330.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
140.000
|
$25.000
|
$100.000
|
$109.890
|
|
|
REMOVING STAB BASE & ASPH PAV(16")
|
SY
|
7,334.000
|
$8.000
|
$7.750
|
$9.990
|
|
|
OBLITERATING ABANDONED ROAD
|
SY
|
473.000
|
$5.500
|
$10.000
|
$8.940
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
3,570.000
|
$10.000
|
$24.250
|
$9.990
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
4,312.000
|
$15.000
|
$8.500
|
$9.990
|
|
|
BLADING
|
HR
|
25.000
|
$100.000
|
$95.000
|
$96.900
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
400.000
|
$0.300
|
$0.170
|
$3.160
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
37,029.000
|
$0.150
|
$0.170
|
$0.160
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
9,265.000
|
$0.150
|
$0.180
|
$0.170
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
9,265.000
|
$0.150
|
$0.180
|
$0.170
|
|
|
VEGETATIVE WATERING
|
MG
|
314.200
|
$15.000
|
$11.000
|
$19.980
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
2,013.000
|
$64.000
|
$100.000
|
$62.900
|
|
|
REWORK BS MTL (TY C) (8") (DENS CONT)
|
SY
|
7,939.000
|
$3.500
|
$2.450
|
$2.280
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
364.000
|
$174.000
|
$150.000
|
$162.750
|
|
|
LIME TRT (SUBGRADE)(6")
|
SY
|
30,396.000
|
$3.000
|
$4.000
|
$2.280
|
|
|
CEMENT
|
TON
|
175.000
|
$145.000
|
$162.000
|
$168.000
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
14,313.000
|
$2.450
|
$3.000
|
$2.280
|
|
|
PRIME COAT (MC-30)
|
GAL
|
7,340.000
|
$4.000
|
$4.300
|
$4.470
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
265.000
|
$100.000
|
$118.000
|
$92.110
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
8,973.000
|
$4.000
|
$4.000
|
$3.800
|
|
|
CONC PVMT (CONT REINF - CRCP) (10")
|
SY
|
11,561.000
|
$62.000
|
$77.800
|
$95.000
|
|
|
CONC PVMT (CONT REINF-CRCP)(HES)(10")
|
SY
|
615.000
|
$90.000
|
$97.900
|
$105.000
|
|
|
CEM STABIL BKFL
|
CY
|
8.000
|
$160.000
|
$160.000
|
$265.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,234.000
|
$21.000
|
$37.650
|
$40.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
10.000
|
$220.000
|
$245.000
|
$231.000
|
|
|
CL A CONC (COLLAR)
|
EA
|
1.000
|
$1,000.000
|
$545.000
|
$750.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
26.000
|
$475.000
|
$530.000
|
$520.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
96.000
|
$150.000
|
$240.000
|
$250.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
|
LF
|
5.000
|
$850.000
|
$1,800.000
|
$850.000
|
|
|
CONC BOX CULV (8 FT X 8 FT)(EXTEND)
|
LF
|
22.000
|
$925.000
|
$1,820.000
|
$1,300.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
32.000
|
$80.000
|
$202.000
|
$100.000
|
|
|
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
|
EA
|
2.000
|
$5,000.000
|
$8,400.000
|
$6,500.000
|
|
|
SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C)
|
EA
|
4.000
|
$7,200.000
|
$8,100.000
|
$4,500.000
|
|
|
SET (TY I)(S= 8 FT)(HW= 9 FT)(3:1) (C)
|
EA
|
4.000
|
$12,000.000
|
$17,900.000
|
$15,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,600.000
|
$1,400.000
|
$2,200.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$280,000.000
|
$183,500.000
|
$385,239.300
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$5,000.000
|
$3,000.000
|
$5,653.410
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
120.000
|
$30.000
|
$37.100
|
$29.740
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
120.000
|
$10.000
|
$10.600
|
$9.480
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,234.000
|
$3.400
|
$4.250
|
$4.820
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,234.000
|
$1.100
|
$1.050
|
$1.140
|
|
|
DRIVEWAYS (ACP)
|
SY
|
261.000
|
$40.000
|
$96.000
|
$35.040
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
19,977.000
|
$0.230
|
$0.210
|
$0.160
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
4.000
|
$200.000
|
$200.000
|
$180.000
|
|
|
RELOCATE RD IL ASM (TRANS-BASE)
|
EA
|
1.000
|
$2,000.000
|
$1,810.000
|
$1,710.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
30.000
|
$8.000
|
$7.900
|
$7.460
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
30.000
|
$1.240
|
$1.650
|
$1.580
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
115.000
|
$1.300
|
$2.000
|
$1.870
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
1.000
|
$797.000
|
$1,100.000
|
$1,067.000
|
|
|
REMOVE GROUND BOX
|
EA
|
1.000
|
$319.560
|
$212.000
|
$200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
11.000
|
$650.000
|
$735.000
|
$695.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
7.000
|
$640.000
|
$600.000
|
$565.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
2.000
|
$670.000
|
$700.000
|
$670.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
56.000
|
$380.000
|
$265.000
|
$250.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
8.000
|
$450.000
|
$290.000
|
$275.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
42.000
|
$75.000
|
$63.600
|
$60.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
11.000
|
$80.000
|
$34.000
|
$32.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
2,762.000
|
$0.800
|
$0.550
|
$0.650
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
31,628.000
|
$0.750
|
$0.550
|
$0.650
|
|
|
WK ZN PAV MRK REMOV (W)8"(DOT)
|
LF
|
532.000
|
$3.000
|
$1.050
|
$1.200
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
6,718.000
|
$1.300
|
$1.000
|
$1.200
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
20,442.000
|
$0.750
|
$0.550
|
$0.650
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
4,728.000
|
$1.300
|
$1.000
|
$1.410
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
1,295.000
|
$1.100
|
$0.500
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
216.000
|
$1.400
|
$0.900
|
$2.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
7,580.000
|
$0.850
|
$0.750
|
$0.800
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
5,644.000
|
$0.400
|
$0.350
|
$0.330
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
10,326.000
|
$0.300
|
$0.350
|
$0.330
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
9,651.000
|
$0.300
|
$0.350
|
$0.330
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
9,263.000
|
$0.520
|
$1.050
|
$0.520
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
8,494.000
|
$0.600
|
$1.050
|
$0.520
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
39.000
|
$14.000
|
$12.750
|
$13.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
9.000
|
$260.000
|
$226.850
|
$230.000
|
|
PREFAB PAV MRK TY C (W) (UTURN ARROW)
|
EA
|
10.000
|
$380.000
|
$360.400
|
$380.000
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
8.000
|
$450.000
|
$711.250
|
$400.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
18.000
|
$350.000
|
$291.500
|
$275.000
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
56.000
|
$45.000
|
$36.000
|
$36.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
681.000
|
$4.000
|
$5.300
|
$4.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
40,250.000
|
$0.400
|
$0.500
|
$0.350
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
20,666.000
|
$0.100
|
$0.100
|
$0.060
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
4,399.000
|
$0.130
|
$0.170
|
$0.130
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
7.000
|
$20.000
|
$15.900
|
$20.000
|
|
|
PAV SURF PREP FOR MRK (UTURN ARR)
|
EA
|
5.000
|
$30.000
|
$31.800
|
$20.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
10.000
|
$25.000
|
$31.800
|
$20.000
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
44.000
|
$6.000
|
$10.600
|
$10.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
10,317.000
|
$82.850
|
$78.900
|
$75.120
|
|
|
D-GR HMA TY-D SAC-B PG76-22
|
TON
|
2,257.000
|
$87.000
|
$92.500
|
$83.340
|
|
|
TACK COAT
|
GAL
|
5,727.000
|
$3.250
|
$3.200
|
$3.170
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$8,500.000
|
$8,000.000
|
$8,118.750
|
|
|
LONG CHANNEL MOUNT CURB SYS (INSTALL)
|
LF
|
670.000
|
$55.000
|
$46.000
|
$45.000
|
|
|
TMA (STATIONARY)
|
DAY
|
15.000
|
$270.000
|
$150.000
|
$324.750
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
30.000
|
$450.000
|
$150.000
|
$324.750
|
|
Totals: |
$3,254,483.000
|
$3,518,108.380
|
$3,659,247.576
|