ERATH FM 8 (0550-02-050)
Items: 40
County: ERATH
Length: N/A
Highway: FM 8
District: FORT WORTH
Control Number: 0550-02-050
DBE Goal: N/A
Project: C 550-2-50
Guaranty: N/A
Time: 214 WORKING DAYS
Engineer's Estimate: $8,255,308.63
Date: 06/03/2021 (5 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$8,255,308.63 | |||
| $6,087,434.10 |
-26.26%
-$2,167,874.53
|
|||
| $6,516,281.65 |
-21.07%
-$1,739,026.98
|
7.04%
$428,847.55
|
||
| $7,099,334.10 |
-14%
-$1,155,974.53
|
16.62%
$1,011,900.00
|
-8.95%
-$583,052.45
|
|
| $7,598,184.34 |
-7.96%
-$657,124.29
|
24.82%
$1,510,750.24
|
-7.03%
-$498,850.24
|
|
| $8,541,123.21 |
3.46%
$285,814.58
|
40.31%
$2,453,689.11
|
-12.41%
-$942,938.87
|
|
| $8,618,410.27 |
4.4%
$363,101.64
|
41.58%
$2,530,976.17
|
-0.90%
-$77,287.06
|
|
| $8,749,903.15 |
5.99%
$494,594.52
|
43.74%
$2,662,469.05
|
-1.53%
-$131,492.88
|
E
Engineer's Estimate
$8,255,308.63
1
Awarded
$6,087,434.10
Over/Under Est:
-26.26%
-$2,167,874.53
$6,516,281.65
Over/Under Est:
-21.07%
-$1,739,026.98
Amt Left:
7.04%
$428,847.55
$7,099,334.10
Over/Under Est:
-14%
-$1,155,974.53
Amt Left:
16.62%
$1,011,900.00
Delta:
-8.95%
-$583,052.45
$7,598,184.34
Over/Under Est:
-7.96%
-$657,124.29
Amt Left:
24.82%
$1,510,750.24
Delta:
-7.03%
-$498,850.24
$8,541,123.21
Over/Under Est:
3.46%
$285,814.58
Amt Left:
40.31%
$2,453,689.11
Delta:
-12.41%
-$942,938.87
$8,618,410.27
Over/Under Est:
4.4%
$363,101.64
Amt Left:
41.58%
$2,530,976.17
Delta:
-0.90%
-$77,287.06
$8,749,903.15
Over/Under Est:
5.99%
$494,594.52
Amt Left:
43.74%
$2,662,469.05
Delta:
-1.53%
-$131,492.88
Bid Items & Bid Tabulations
40
Total
0 of 40