PREPARING ROW
|
STA
|
161.000
|
$5,000.000
|
$550.000
|
$420.000
|
$850.000
|
|
|
REMOVING STAB BASE AND ASPH PAV(0"-16")
|
SY
|
2,261.000
|
$10.000
|
$4.700
|
$12.890
|
$6.000
|
|
|
OBLITERATING ABANDONED ROAD
|
STA
|
3.000
|
$1,235.000
|
$1,550.000
|
$5,045.000
|
$1,400.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
21,239.000
|
$4.000
|
$12.000
|
$12.700
|
$15.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
3,764.000
|
$15.000
|
$4.000
|
$9.350
|
$15.000
|
|
|
BLADING
|
STA
|
161.000
|
$73.000
|
$140.000
|
$139.000
|
$100.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
22,609.000
|
$0.200
|
$0.160
|
$1.150
|
$0.180
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
22,609.000
|
$0.200
|
$0.160
|
$1.150
|
$0.180
|
|
|
VEGETATIVE WATERING
|
MG
|
934.000
|
$15.000
|
$16.000
|
$37.000
|
$15.000
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
9,908.000
|
$35.000
|
$36.850
|
$44.000
|
$58.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
114.000
|
$165.000
|
$209.000
|
$254.000
|
$190.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
6,851.000
|
$2.750
|
$3.050
|
$7.150
|
$3.750
|
|
|
CEMENT
|
TON
|
1,115.000
|
$150.000
|
$140.000
|
$145.000
|
$150.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
20,552.000
|
$2.500
|
$2.500
|
$4.800
|
$1.550
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
60,226.000
|
$2.150
|
$2.500
|
$3.120
|
$1.850
|
|
|
PRIME COAT (RC-250)
|
GAL
|
8,966.000
|
$5.000
|
$4.000
|
$5.450
|
$3.500
|
|
|
ASPH (AC-20XP)
|
GAL
|
13,879.000
|
$3.250
|
$3.250
|
$4.740
|
$3.500
|
|
|
ASPH (RC-250)
|
GAL
|
20,477.000
|
$5.000
|
$4.000
|
$5.300
|
$3.500
|
|
|
AGGR(TY-B GR-3 SAC-B)
|
CY
|
313.000
|
$85.000
|
$73.500
|
$132.000
|
$124.000
|
|
|
AGGR(TY-B GR-5 SAC-B)
|
CY
|
722.000
|
$75.000
|
$77.500
|
$139.000
|
$146.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
13,852.000
|
$61.300
|
$88.000
|
$85.250
|
$87.000
|
|
|
D-GR HMA TY-C SAC-B PG64-22
|
TON
|
3,152.000
|
$65.000
|
$96.000
|
$89.630
|
$100.000
|
|
|
D-GR HMA TY-C SAC-A, PG70-28
|
TON
|
11,173.000
|
$80.000
|
$105.000
|
$101.880
|
$110.000
|
|
|
PLANE ASPH CONC PAV(0" TO 6")
|
SY
|
3,193.000
|
$1.580
|
$4.700
|
$16.680
|
$4.250
|
|
|
PLANE ASPH CONC PAV (4")
|
SY
|
57,033.000
|
$2.030
|
$1.900
|
$3.770
|
$2.450
|
|
|
CEM STABIL BKFL
|
CY
|
222.000
|
$64.000
|
$100.000
|
$294.000
|
$228.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,046.000
|
$15.000
|
$44.000
|
$63.000
|
$19.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
36.000
|
$420.000
|
$475.000
|
$630.000
|
$485.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
44.000
|
$519.450
|
$385.000
|
$370.000
|
$527.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
|
LF
|
48.000
|
$323.450
|
$495.000
|
$545.000
|
$655.000
|
|
|
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
|
LF
|
28.000
|
$484.300
|
$1,025.000
|
$622.000
|
$831.000
|
|
|
CONC BOX CULV (5 FT X 6 FT) (EXTEND)
|
LF
|
10.000
|
$750.360
|
$770.000
|
$815.000
|
$824.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
94.000
|
$80.000
|
$98.000
|
$129.000
|
$71.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
6.000
|
$5,750.000
|
$4,620.000
|
$3,625.000
|
$6,600.000
|
|
|
WINGWALL (PW - 1) (HW=3 FT)
|
EA
|
1.000
|
$4,000.000
|
$5,500.000
|
$5,570.000
|
$7,500.000
|
|
|
WINGWALL (PW - 1) (HW=4 FT)
|
EA
|
3.000
|
$5,500.000
|
$6,820.000
|
$7,160.000
|
$8,500.000
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
2.000
|
$12,000.000
|
$8,910.000
|
$21,150.000
|
$6,900.000
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
1.000
|
$20,000.000
|
$9,900.000
|
$22,060.000
|
$7,500.000
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
1.000
|
$45,000.000
|
$23,100.000
|
$33,200.000
|
$16,500.000
|
|
|
WINGWALL (PW - 1) (HW=9 FT)
|
EA
|
1.000
|
$45,000.000
|
$30,800.000
|
$43,500.000
|
$14,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$1,115.840
|
$1,320.000
|
$3,200.000
|
$1,675.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$347,900.000
|
$350,000.000
|
$595,000.000
|
$635,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$12,000.000
|
$7,000.000
|
$7,350.000
|
$15,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,296.000
|
$25.000
|
$26.000
|
$31.500
|
$35.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,296.000
|
$7.000
|
$7.500
|
$10.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$21.000
|
$25.100
|
$26.000
|
$30.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$13.000
|
$10.000
|
$10.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
15,893.000
|
$2.000
|
$2.150
|
$2.600
|
$3.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
15,893.000
|
$0.500
|
$0.600
|
$1.000
|
$0.380
|
|
|
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
|
LF
|
600.000
|
$20.000
|
$7.300
|
$23.100
|
$35.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
1,800.000
|
$10.000
|
$5.050
|
$10.500
|
$25.000
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
600.000
|
$15.000
|
$7.300
|
$18.900
|
$23.000
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
154.000
|
$15.000
|
$16.000
|
$26.250
|
$75.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
37,869.000
|
$0.160
|
$0.130
|
$0.210
|
$0.350
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
18,935.000
|
$0.150
|
$0.220
|
$0.520
|
$0.350
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
213.000
|
$20.000
|
$24.200
|
$21.000
|
$25.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
6.000
|
$2,600.000
|
$2,475.000
|
$2,600.000
|
$2,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
4.000
|
$10,000.000
|
$9,500.000
|
$8,175.000
|
$10,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
28.000
|
$15.000
|
$1,400.000
|
$1,340.000
|
$1,700.000
|
|
|
CRASH CUSH ATTEN (STKPL)
|
EA
|
4.000
|
$1,000.000
|
$950.000
|
$640.000
|
$800.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 2
|
EA
|
2.000
|
$350.000
|
$385.000
|
$420.000
|
$390.000
|
|
|
MAILBOX INSTALL-S (RR-POST) TY 4
|
EA
|
12.000
|
$245.000
|
$275.000
|
$305.000
|
$280.000
|
|
|
MAILBOX INSTALL-D (RR-POST) TY 4
|
EA
|
2.000
|
$270.000
|
$247.500
|
$305.000
|
$250.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$500.000
|
$550.000
|
$525.000
|
$555.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
11.000
|
$600.000
|
$605.000
|
$630.000
|
$610.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
7.000
|
$800.000
|
$715.000
|
$819.000
|
$725.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
15.000
|
$200.000
|
$82.500
|
$26.000
|
$85.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
16.000
|
$60.000
|
$60.500
|
$58.000
|
$62.000
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
705.000
|
$1.000
|
$1.370
|
$1.000
|
$1.390
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
700.000
|
$0.720
|
$0.880
|
$1.000
|
$0.890
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
15.000
|
$12.000
|
$27.500
|
$21.000
|
$28.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
7.000
|
$130.000
|
$110.000
|
$420.000
|
$110.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
3.000
|
$250.000
|
$132.000
|
$158.000
|
$135.000
|
|
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
|
LF
|
1,485.000
|
$5.000
|
$6.050
|
$8.400
|
$6.110
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
3,080.000
|
$0.600
|
$0.440
|
$0.400
|
$0.440
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
38,360.000
|
$0.400
|
$0.440
|
$0.400
|
$0.440
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
43,450.000
|
$0.300
|
$0.440
|
$0.400
|
$0.440
|
|
REFL PAV MRKR TY I-C
|
EA
|
155.000
|
$5.000
|
$5.500
|
$9.500
|
$5.560
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,003.000
|
$5.000
|
$4.400
|
$5.150
|
$4.440
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$8,500.000
|
$10,450.000
|
$16,275.000
|
$20,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
20.000
|
$50.000
|
$275.000
|
$892.500
|
$250.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
160.000
|
$200.000
|
$55.000
|
$126.000
|
$50.000
|
|
Totals: |
$5,268,158.060
|
$5,364,691.000
|
$6,302,941.910
|
$6,388,776.550
|