DEWITT US0183 (6343-65-001)

Items: 34

County: DEWITT
Length: N/A
Highway: US0183
District: YOAKUM
Control Number: 6343-65-001
DBE Goal: N/A
Project: RMC - 634365001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $2,834,231.50
Date: 04/03/2019 (7 years ago)
Contract Number: N/A
Type: CALL OUT ASPHALTIC CONCRETE PAVEMENT OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$2,834,231.50
$3,029,377.45
Over/Under Est: 6.89% $195,145.95
Over/Under Est: 8.36% $236,892.80
Amt Left: 1.38% $41,746.85
Over/Under Est: 20.34% $576,503.10
Amt Left: 12.59% $381,357.15
Delta: -11.06% -$339,610.30
Over/Under Est: 29.53% $836,921.45
Amt Left: 21.19% $641,775.50
Delta: -7.64% -$260,418.35
Over/Under Est: 37.47% $1,062,048.11
Amt Left: 28.62% $866,902.16
Delta: -6.13% -$225,126.66

Bid Items & Bid Tabulations

34 Total 0 of 34
DEWITT  |  US0183  |  YOAKUM  |  6343-65-001  |  04/03/2019  |  $2,834,231.50  |  RMC - 634365001  |  CALL OUT ASPHIC CONC PAVMT OVERLAY  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
LONE STAR PAVING COMPANY
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
DEAN WORD COMPANY, LTD.
BACKFILL (TY A OR B)
STA 264.000 $125.000 $94.650 $260.000 $50.000 $200.000 $193.919
BLADING
HR 50.000 $80.000 $91.200 $125.000 $95.000 $100.000 $115.500
PRIME COAT (MULTI OPTION)
GAL 3,520.000 $3.350 $4.060 $4.000 $3.000 $5.000 $9.570
AGGR(TY-PE GR-3 SAC-B)
CY 2,209.000 $80.000 $88.340 $122.000 $85.000 $130.000 $160.050
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 75,093.000 $3.500 $3.690 $3.650 $3.000 $4.500 $4.147
D-GR HMA TY-B PG64-22
TON 195.000 $100.000 $105.810 $92.300 $150.000 $105.000 $118.800
D-GR HMA TY-D SAC-B PG70-22
TON 21,150.000 $85.000 $86.850 $84.500 $100.000 $113.000 $107.548
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 600.000 $60.000 $82.900 $83.000 $100.000 $111.000 $109.939
PLANE CONC PAV(0" TO 2")
SY 93,867.000 $2.000 $1.730 $2.700 $2.000 $1.500 $2.855
PLANE ASPH CONC PAV (8")
SY 444.000 $10.000 $13.650 $7.500 $20.000 $8.000 $16.570
CLEANING AND SEALING EXISTING JOINTS
LF 200.000 $25.000 $94.090 $80.000 $50.000 $125.000 $52.000
MOBILIZATION (CALLOUT)
EA 3.000 $55,000.000 $89,803.790 $50,000.000 $110,000.000 $35,000.000 $52,190.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $2,500.000 $3,622.810 $2,000.000 $3,500.000 $13,000.000 $35,920.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 600.000 $1.500 $1.660 $1.000 $1.000 $1.500 $1.870
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,100.000 $1.500 $1.660 $1.000 $1.000 $1.500 $1.870
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 360.000 $0.800 $0.900 $1.100 $2.750 $2.500 $3.120
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 5,280.000 $0.350 $0.400 $0.500 $0.440 $0.500 $0.551
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 84,480.000 $0.350 $0.380 $0.500 $0.440 $0.430 $0.437
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 7,040.000 $0.350 $0.400 $0.500 $0.440 $0.650 $0.530
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 42,240.000 $0.350 $0.400 $0.500 $0.440 $0.600 $0.426
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 415.000 $8.000 $5.000 $7.750 $4.000 $8.250 $8.320
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 288.000 $12.000 $10.000 $15.000 $17.000 $15.600 $14.560
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $200.000 $205.000 $250.000 $325.000 $300.000 $234.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 4.000 $300.000 $290.000 $415.000 $500.000 $450.000 $353.600
PREFAB PAV MRK TY C (W) (WORD)
EA 4.000 $250.000 $250.000 $250.000 $475.000 $415.000 $299.520
PREFAB PAV MRK TY C (W) (RR XING)
EA 4.000 $600.000 $450.000 $600.000 $800.000 $700.000 $676.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 192.000 $12.000 $10.500 $15.500 $13.000 $12.000 $14.560
REFL PAV MRKR TY I-C
EA 21.000 $4.000 $5.000 $6.600 $11.000 $10.000 $4.680
REFL PAV MRKR TY II-A-A
EA 880.000 $3.000 $5.000 $5.500 $5.500 $5.000 $4.420
REFL PAV MRKR TY II-C-R
EA 66.000 $4.000 $5.000 $6.600 $11.000 $10.000 $4.680
TMA (STATIONARY)
EA 3.000 $1,500.000 $5,141.870 $3,500.000 $6,500.000 $5,000.000 $3,850.000
TMA (MOBILE OPERATION)
DAY 8.000 $250.000 $270.620 $340.000 $275.000 $250.000 $1,980.000
1 LANE CLOSURE-2 LANE ROAD, PAVED SHLDR
EA 35.000 $1,000.000 $1,082.500 $1,000.000 $2,500.000 $1,800.000 $3,300.000
1 LANE CLOSURE-4 LANE ROAD
EA 10.000 $1,500.000 $1,299.000 $1,500.000 $2,500.000 $1,800.000 $3,300.000
Totals: $2,834,231.500 $3,029,377.450 $3,071,124.300 $3,410,734.600 $3,671,152.950 $3,896,279.622