DEWITT FM 237 (0941-01-024)

Items: 60

County: DEWITT
Length: N/A
Highway: FM 237
District: YOAKUM
Control Number: 0941-01-024
DBE Goal: N/A
Project: STP 2018(256)HES
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $967,039.25
Date: 11/03/2017 (8 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$967,039.25
$856,905.05
Over/Under Est: -11.39% -$110,134.20
$919,638.47
Over/Under Est: -4.9% -$47,400.78
Amt Left: 7.32% $62,733.42
$943,510.32
Over/Under Est: -2.43% -$23,528.93
Amt Left: 10.11% $86,605.27
Delta: -2.60% -$23,871.85
Over/Under Est: 10.29% $99,527.75
Amt Left: 24.47% $209,661.95
Delta: -13.04% -$123,056.68
$1,078,373.52
Over/Under Est: 11.51% $111,334.27
Amt Left: 25.85% $221,468.47
Delta: -1.11% -$11,806.52
Over/Under Est: 23.59% $228,143.49
Amt Left: 39.48% $338,277.69
Delta: -10.83% -$116,809.22
Over/Under Est: 24.63% $238,212.76
Amt Left: 40.65% $348,346.96
Delta: -0.84% -$10,069.27
$1,228,895.30
Over/Under Est: 27.08% $261,856.05
Amt Left: 43.41% $371,990.25
Delta: -1.96% -$23,643.29
Over/Under Est: 28.81% $278,627.28
Amt Left: 45.37% $388,761.48
Delta: -1.36% -$16,771.23
$1,248,740.90
Over/Under Est: 29.13% $281,701.65
Amt Left: 45.73% $391,835.85
Delta: -0.25% -$3,074.37

Bid Items & Bid Tabulations

60 Total 0 of 60
DEWITT  |  FM 237  |  YOAKUM  |  0941-01-024  |  11/03/2017  |  $967,039.25  |  STP 2018(256)HES  |  SAFETY TREAT FIXED OBJECTS  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HILL COUNTRY BRIDGE, INC.
RELMCO, INC.
DUNN SERVICES, INC.
MAIN LANE INDUSTRIES LTD.
ISI CONTRACTING, INC.
DEAN WORD COMPANY, LTD.
REXCO CONSTRUCTION SERVICES, INC.
3LW CIVIL LLC
HUNTER INDUSTRIES, LTD.
SB CONTRACTORS LLC
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 2,049.000 $20.000 $14.550 $15.000 $13.500 $40.000 $27.000 $49.742 $43.390 $40.000 $26.640 $35.000
BLADING
HR 5.000 $150.000 $420.000 $85.000 $250.000 $150.000 $105.000 $93.225 $85.000 $500.000 $228.000 $65.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,210.000 $2.500 $1.100 $2.000 $1.200 $4.000 $1.500 $1.040 $3.070 $1.000 $1.000 $1.000
VEGETATIVE WATERING
MG 10.180 $100.000 $200.000 $100.000 $15.000 $100.000 $14.000 $69.730 $885.000 $85.000 $196.720 $55.000
CEM STABIL BKFL
CY 456.000 $125.000 $107.700 $120.000 $92.000 $65.000 $45.000 $127.730 $84.500 $200.000 $160.000 $150.000
CUT & RESTORING PAV
SY 682.000 $80.000 $79.900 $85.000 $102.500 $110.000 $150.000 $96.126 $135.000 $200.000 $105.000 $100.000
TRENCH EXCAVATION PROTECTION
LF 270.000 $10.000 $18.000 $10.000 $6.250 $5.000 $1.000 $12.440 $10.000 $8.000 $15.000 $6.000
TEMPORARY SPL SHORING
SF 345.000 $20.000 $31.100 $30.000 $21.000 $5.000 $5.000 $32.625 $15.000 $35.000 $18.000 $20.000
RIPRAP (CONC)(5 IN)
CY 11.800 $450.000 $810.000 $450.000 $450.000 $825.000 $520.000 $572.000 $448.600 $500.000 $400.000 $450.000
CMP (GAL STL 18 IN)
LF 232.000 $50.000 $106.700 $37.780 $46.500 $48.000 $68.000 $129.975 $42.750 $60.000 $225.000 $85.000
CMP (GAL STL 24 IN)
LF 130.000 $65.000 $116.800 $47.450 $85.300 $52.000 $90.000 $121.585 $48.120 $70.000 $235.000 $85.000
CMP (GAL STL 30 IN)
LF 16.000 $85.000 $100.700 $58.470 $76.500 $57.000 $84.000 $78.810 $115.570 $95.000 $295.000 $92.000
CMP AR (GAL STL DES 3)
LF 52.000 $80.000 $104.300 $55.430 $77.300 $54.000 $62.000 $93.370 $50.140 $110.000 $285.000 $92.000
CONC BOX CULV (5 FT X 3 FT)
LF 111.000 $500.000 $322.000 $260.640 $301.750 $255.000 $350.000 $392.222 $265.960 $325.000 $340.000 $500.000
CONC BOX CULV (5 FT X 5 FT)
LF 6.000 $600.000 $485.000 $1,586.000 $410.000 $510.000 $600.000 $1,325.750 $1,514.000 $375.000 $1,000.000 $1,800.000
CONC BOX CULV (6 FT X 3 FT)
LF 80.000 $700.000 $400.000 $299.650 $420.500 $330.000 $420.000 $372.570 $346.200 $450.000 $400.000 $550.000
RC PIPE (CL III)(18 IN)
LF 308.000 $50.000 $50.350 $52.650 $62.500 $59.000 $65.000 $71.085 $50.780 $60.000 $115.000 $110.000
RC PIPE (CL III)(24 IN)
LF 761.000 $60.000 $68.050 $62.790 $76.300 $68.000 $96.000 $76.950 $63.390 $65.000 $100.000 $120.000
RC PIPE (CL III)(30 IN)
LF 356.000 $100.000 $82.000 $82.610 $91.250 $81.000 $129.000 $93.520 $79.880 $75.000 $130.000 $135.000
RC PIPE (CL III)(36 IN)
LF 80.000 $150.000 $123.000 $109.070 $141.600 $102.000 $176.000 $121.680 $133.140 $120.000 $275.000 $155.000
RC PIPE (CL III)(42 IN)
LF 208.000 $150.000 $143.100 $157.690 $154.000 $129.000 $178.000 $177.482 $167.470 $160.000 $250.000 $195.000
RC PIPE (CL III)(48 IN)
LF 38.000 $200.000 $175.000 $177.970 $181.200 $155.000 $150.000 $234.720 $208.700 $220.000 $415.000 $210.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 6.000 $5,000.000 $2,810.000 $4,017.000 $5,200.000 $6,100.000 $7,000.000 $4,942.640 $8,421.200 $8,500.000 $2,800.000 $8,500.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(3:1) (C)
EA 2.000 $4,600.000 $6,520.000 $6,045.000 $7,800.000 $14,000.000 $7,000.000 $9,447.700 $9,790.000 $9,000.000 $9,600.000 $11,000.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C)
EA 4.000 $4,500.000 $2,770.000 $3,815.500 $4,700.000 $6,500.000 $7,000.000 $4,203.060 $8,400.000 $9,500.000 $4,700.000 $12,000.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 53.000 $950.000 $820.000 $988.000 $1,050.000 $1,150.000 $1,200.000 $1,061.250 $842.200 $775.000 $1,250.000 $1,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 17.000 $1,100.000 $985.000 $1,085.500 $800.000 $1,250.000 $1,300.000 $1,494.640 $1,024.200 $775.000 $1,350.000 $1,000.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 27.000 $1,200.000 $925.000 $1,176.500 $1,200.000 $1,225.000 $1,300.000 $1,199.520 $1,135.800 $975.000 $1,650.000 $1,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 36.000 $1,000.000 $770.000 $1,209.000 $850.000 $1,325.000 $1,600.000 $1,607.250 $1,440.520 $1,550.000 $1,450.000 $1,100.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $1,500.000 $1,475.000 $1,209.000 $1,250.000 $1,325.000 $1,500.000 $1,952.820 $1,553.200 $1,685.000 $2,050.000 $2,000.000
SET (TY II) (30 IN) (CMP) (6: 1) (P)
EA 2.000 $1,800.000 $1,225.000 $1,300.000 $1,700.000 $1,300.000 $1,900.000 $1,769.450 $1,439.600 $1,450.000 $2,250.000 $1,500.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 4.000 $800.000 $900.000 $1,332.500 $1,575.000 $1,425.000 $1,600.000 $1,958.600 $1,459.240 $1,885.000 $1,650.000 $1,500.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 14.000 $2,000.000 $1,110.000 $1,332.500 $1,270.000 $1,425.000 $2,200.000 $2,601.820 $1,704.800 $2,300.000 $2,150.000 $1,500.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 1.000 $2,400.000 $1,965.000 $1,651.000 $2,000.000 $2,650.000 $2,800.000 $2,696.250 $2,000.400 $2,800.000 $2,650.000 $2,500.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 3.000 $3,000.000 $2,035.000 $1,651.000 $2,100.000 $2,125.000 $3,500.000 $3,164.500 $2,320.000 $3,500.000 $2,850.000 $2,500.000
SET (TY II) (42 IN) (RCP) (3: 1) (C)
EA 6.000 $3,500.000 $1,795.000 $2,658.500 $3,500.000 $2,550.000 $3,500.000 $3,816.340 $2,687.200 $3,750.000 $2,950.000 $2,000.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 4.000 $3,600.000 $2,185.000 $2,714.400 $4,000.000 $2,550.000 $3,500.000 $4,089.800 $2,844.400 $3,950.000 $3,250.000 $2,500.000
SET (TY II) (48 IN) (RCP) (3: 1) (C)
EA 2.000 $3,800.000 $2,320.000 $3,133.000 $4,500.000 $4,100.000 $4,000.000 $5,660.200 $3,425.200 $5,500.000 $3,550.000 $3,000.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 10.000 $1,500.000 $875.000 $1,241.500 $1,300.000 $1,250.000 $1,400.000 $1,671.150 $1,156.600 $1,750.000 $1,950.000 $1,500.000
REMOV STR (SMALL)
EA 29.000 $500.000 $665.000 $1,500.000 $930.000 $2,500.000 $100.000 $390.250 $1,600.000 $250.000 $1,000.000 $1,300.000
REMOVE STR (RAIL)
LF 50.000 $20.000 $15.000 $50.000 $62.200 $5.000 $10.000 $20.800 $12.000 $4.000 $5.000 $18.000
MOBILIZATION
LS 1.000 $85,000.000 $84,000.000 $90,000.000 $63,956.620 $75,000.000 $100,000.000 $119,509.359 $243,065.000 $100,000.000 $123,560.610 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $3,500.000 $4,620.000 $3,000.000 $5,200.000 $6,000.000 $2,000.000 $7,402.573 $1,102.400 $8,000.000 $1,746.850 $4,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 580.000 $30.000 $20.000 $31.120 $37.800 $40.000 $30.000 $18.720 $30.110 $35.000 $45.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 580.000 $10.000 $8.000 $15.050 $8.750 $15.000 $9.000 $5.200 $14.560 $10.000 $5.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,000.000 $2.500 $2.400 $2.710 $2.950 $2.500 $2.250 $1.820 $2.650 $4.000 $1.750 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,000.000 $0.500 $0.750 $1.340 $0.750 $1.000 $2.500 $0.624 $1.300 $1.000 $0.600 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 625.000 $20.000 $18.550 $25.060 $28.200 $22.500 $25.000 $24.232 $24.230 $20.000 $22.480 $23.300
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 100.000 $20.000 $18.550 $25.060 $31.000 $35.000 $30.000 $24.232 $24.230 $22.000 $22.480 $23.300
REMOVE METAL BEAM GUARD FENCE
LF 725.000 $2.250 $3.100 $4.830 $3.100 $3.500 $2.000 $4.680 $4.680 $3.000 $3.750 $4.500
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $200.000 $80.000 $188.120 $310.000 $150.000 $100.000 $182.000 $182.000 $100.000 $93.670 $175.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,200.000 $2,165.000 $2,719.750 $2,500.000 $3,500.000 $2,800.000 $2,631.200 $2,631.200 $2,250.000 $2,622.820 $2,530.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $250.000 $255.000 $537.500 $350.000 $250.000 $250.000 $520.000 $520.000 $275.000 $312.240 $750.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 48.000 $55.000 $35.000 $21.500 $22.000 $40.000 $70.000 $57.200 $88.720 $40.000 $50.000 $20.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 48.000 $10.000 $19.000 $50.000 $20.000 $5.000 $18.000 $15.600 $25.000 $20.000 $15.000 $5.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $30.000 $26.000 $125.000 $9.500 $20.000 $30.000 $20.800 $20.800 $25.000 $25.000 $20.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 2,200.000 $0.600 $0.700 $0.530 $1.550 $1.000 $1.000 $0.520 $1.560 $1.000 $1.130 $1.000
REFL PAV MRK TY II (Y) 4" (BRK)
LF 825.000 $0.600 $0.700 $0.810 $1.550 $1.000 $2.000 $0.780 $1.560 $1.000 $1.130 $1.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 1,100.000 $0.600 $0.700 $0.530 $1.550 $1.000 $2.000 $0.520 $1.560 $1.000 $1.130 $1.000
REFL PAV MRKR TY II-A-A
EA 44.000 $10.000 $7.000 $21.500 $10.500 $50.000 $25.000 $20.800 $20.800 $25.000 $11.820 $50.000
Totals: $967,039.250 $856,905.050 $919,638.470 $943,510.320 $1,066,567.000 $1,078,373.520 $1,195,182.781 $1,205,252.010 $1,228,895.300 $1,245,666.540 $1,248,740.900