Bid Cobra

DEWITT US 87 (0143-09-069)

Items: 22

County: DEWITT
Length: N/A
Highway: US 87
District: YOAKUM
Control Number: 0143-09-069
DBE Goal: N/A
Project: NH 2017(831)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $2,021,176.12
Date: 03/08/2017 (9 years ago)
Contract Number: N/A
Type: ACP OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,021,176.12
$1,812,578.62
Over/Under Est: -10.32% -$208,597.50
$2,005,138.24
Over/Under Est: -0.79% -$16,037.88
Amt Left: 10.62% $192,559.62
Over/Under Est: 2.37% $47,835.08
Amt Left: 14.15% $256,432.58
Delta: -3.19% -$63,872.96
Over/Under Est: 4.56% $92,194.78
Amt Left: 16.59% $300,792.28
Delta: -2.14% -$44,359.70

Bid Items & Bid Tabulations

22 Total 0 of 22
DEWITT  |  US 87  |  YOAKUM  |  0143-09-069  |  03/08/2017  |  $2,021,176.12  |  NH 2017(831)  |  ACP OVERLAY  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
AUSTIN MATERIALS, LLC
DEAN WORD COMPANY, LTD.
ANGEL BROTHERS HOLDINGS CORP.
BACKFILL (TY A OR B)
STA 387.000 $125.000 $106.050 $112.000 $128.231 $148.000
BLADING
HR 10.000 $100.000 $86.640 $74.000 $110.212 $72.250
PRIME COAT (RC-250)
GAL 5,160.000 $3.500 $3.830 $3.550 $3.434 $4.250
AGGR(TY-PB GR-4 SAC-B)
CY 1,379.000 $60.000 $69.950 $108.000 $97.883 $100.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 60,940.000 $3.500 $2.610 $2.150 $2.446 $2.450
D-GR HMA TY-D SAC-B PG70-22
TON 19,919.000 $60.000 $57.780 $67.000 $68.249 $68.300
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 5,610.000 $30.000 $14.250 $20.000 $18.163 $18.150
PLANE ASPH CONC PAV(0" TO 2")
SY 7,046.000 $2.300 $1.710 $1.200 $3.240 $2.250
CLEANING AND SEALING EXISTING JOINTS
LF 352.000 $25.000 $29.570 $30.000 $35.020 $38.300
MOBILIZATION
LS 1.000 $200,000.000 $174,348.070 $134,000.000 $143,814.328 $136,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $1,509.670 $1,000.000 $3,208.963 $14,000.000
RUMBLE STRIPS (SHOULDER)
LF 77,960.000 $0.150 $0.180 $0.090 $0.145 $0.150
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 9,746.000 $0.200 $0.500 $0.280 $0.288 $0.500
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,200.000 $0.250 $0.650 $0.280 $0.288 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 5,848.000 $1.000 $1.600 $1.000 $1.149 $2.800
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,200.000 $0.620 $0.650 $0.670 $0.690 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 9,746.000 $0.320 $0.270 $0.360 $0.371 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 38,980.000 $0.320 $0.270 $0.360 $0.371 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 39,890.000 $0.320 $0.270 $0.360 $0.371 $0.350
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 234.000 $35.000 $22.000 $33.000 $33.990 $17.900
REFL PAV MRKR TY II-A-A
EA 52.000 $2.750 $10.000 $4.000 $4.120 $5.350
REFL PAV MRKR TY II-C-R
EA 620.000 $3.500 $4.000 $4.000 $4.120 $3.250
Totals: $2,021,176.120 $1,812,578.620 $2,005,138.240 $2,069,011.248 $2,113,370.900