Show Job Controls
Bid Cobra

DELTA SH 24 (0136-03-065)

Items: 34

County: DELTA
Length: N/A
Highway: SH 24
District: PARIS
Control Number: 0136-03-065
DBE Goal: N/A
Project: STP 1902(104)HES
Guaranty: N/A
Time: 127 WORKING DAYS
Engineer's Estimate: $1,468,011.00
Date: 07/10/2019 (6 years ago)
Contract Number: N/A
Type: IMPROVE GUARDRAIL TO DESIGN STANDARDS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,468,011.00
$1,347,221.00
Over/Under Est: -8.23% -$120,790.00
$1,844,599.00
Over/Under Est: 25.65% $376,588.00
Amt Left: 36.92% $497,378.00
$1,853,875.16
Over/Under Est: 26.28% $385,864.16
Amt Left: 37.61% $506,654.16
Delta: -0.50% -$9,276.16
$1,882,488.00
Over/Under Est: 28.23% $414,477.00
Amt Left: 39.73% $535,267.00
Delta: -1.54% -$28,612.84
$2,073,910.00
Over/Under Est: 41.27% $605,899.00
Amt Left: 53.94% $726,689.00
Delta: -10.17% -$191,422.00

Bid Items & Bid Tabulations

34 Total 0 of 34
DELTA  |  SH 24  |  PARIS  |  0136-03-065  |  07/10/2019  |  $1,468,011.00  |  STP 1902(104)HES  |  IMPROVE GUARDRAIL TO DESIGN STANDARD...  |  127 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
3LW CIVIL LLC
CDM HOLDINGS, LLC
SJ&J CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
EXCAVATION (CHANNEL)
CY 24.000 $7.000 $24.000 $37.000 $50.000 $12.000 $40.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 584.000 $24.000 $40.000 $44.000 $15.000 $20.000 $40.000
BLOCK SODDING
SY 600.000 $5.500 $11.000 $8.000 $5.000 $6.000 $6.000
VEGETATIVE WATERING
MG 2.000 $10.000 $130.000 $220.000 $1,000.000 $40.000 $500.000
TEMPORARY SPL SHORING
SF 400.000 $13.000 $65.000 $30.000 $35.000 $20.000 $45.000
RIPRAP (MOW STRIP)(4 IN)
CY 882.600 $445.000 $325.000 $515.000 $591.140 $650.000 $550.000
RAIL (TY T631)
LF 300.000 $88.000 $110.000 $175.000 $91.000 $180.000 $185.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 24.000 $590.000 $1,190.000 $2,000.000 $656.000 $700.000 $1,000.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 24.000 $700.000 $1,235.000 $2,000.000 $699.000 $800.000 $1,000.000
WINGWALL (FW - 0) (HW=5 FT)
EA 1.000 $8,000.000 $8,780.000 $15,000.000 $29,588.000 $12,000.000 $15,000.000
WINGWALL (FW - 0) (HW=6 FT)
EA 2.000 $8,500.000 $8,650.000 $15,000.000 $38,054.000 $13,000.000 $18,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 1.000 $12,500.000 $8,160.000 $15,000.000 $37,421.000 $16,000.000 $21,000.000
REMOV STR (WINGWALL)
EA 4.000 $1,200.000 $250.000 $3,000.000 $1,250.000 $1,200.000 $5,000.000
MOBILIZATION
LS 1.000 $140,000.000 $139,000.000 $150,000.000 $185,000.000 $200,000.000 $190,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $4,000.000 $3,800.000 $15,000.000 $14,500.000 $6,000.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 160.000 $2.500 $3.000 $4.000 $5.000 $3.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 160.000 $1.000 $1.000 $2.000 $2.000 $1.000 $2.000
MTL W-BEAM GD FEN (STEEL POST)
LF 12,400.000 $25.000 $22.500 $31.000 $25.030 $31.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 43.000 $2,000.000 $2,100.000 $1,800.000 $2,035.000 $1,900.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,150.000 $1,170.000 $1,250.000 $1,430.000 $1,800.000 $1,850.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 200.000 $65.000 $47.000 $30.000 $27.500 $60.000 $35.000
REMOVE METAL BEAM GUARD FENCE
LF 13,300.000 $3.150 $1.250 $3.500 $3.300 $4.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $250.000 $100.000 $280.000 $137.500 $600.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 43.000 $295.000 $250.000 $250.000 $220.000 $500.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 81.000 $2,700.000 $2,800.000 $2,800.000 $2,722.500 $2,600.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 88.000 $350.000 $60.000 $300.000 $247.500 $700.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 57.000 $20.000 $15.000 $20.000 $30.800 $30.000 $100.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 58.000 $17.000 $15.000 $18.000 $30.800 $30.000 $100.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 14.000 $95.000 $60.000 $62.000 $55.000 $70.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 132.000 $27.000 $15.000 $27.000 $49.500 $40.000 $100.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 60.000 $23.000 $15.000 $22.000 $49.500 $40.000 $100.000
CONC RAIL REPAIR(REMOVE AND REPL RAIL)
LF 30.000 $500.000 $900.000 $500.000 $300.000 $400.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $4,930.000 $9,500.000 $16,000.000 $7,000.000 $16,500.000
TMA (STATIONARY)
DAY 120.000 $190.000 $200.000 $260.000 $300.000 $160.000 $550.000
Totals: $1,468,011.000 $1,347,221.000 $1,844,599.000 $1,853,875.164 $1,882,488.000 $2,073,910.000