DEAF SMITH US 385 (0226-05-072)
Items: 81
County: DEAF SMITH
Length: N/A
Highway: US 385
District: AMARILLO
Control Number: 0226-05-072
DBE Goal: 700.0%
Project: F 2B24(155)
Guaranty: N/A
Time: 140 WORKING DAYS
Engineer's Estimate: $6,151,364.20
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
JOE CHAPPELL
CC SYSOMBATH
KIT BLACK
DARRELL CALDWELL
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,151,364.20 | |||
| $5,281,885.17 |
-14.13%
-$869,479.03
|
|||
| $5,824,999.99 |
-5.31%
-$326,364.21
|
10.28%
$543,114.82
|
||
| $6,743,776.50 |
9.63%
$592,412.30
|
27.68%
$1,461,891.33
|
-15.77%
-$918,776.51
|
|
| $6,980,346.29 |
13.48%
$828,982.09
|
32.16%
$1,698,461.12
|
-3.51%
-$236,569.79
|
E
Engineer's Estimate
$6,151,364.20
1
Awarded
$5,281,885.17
Over/Under Est:
-14.13%
-$869,479.03
$5,824,999.99
Over/Under Est:
-5.31%
-$326,364.21
Amt Left:
10.28%
$543,114.82
$6,743,776.50
Over/Under Est:
9.63%
$592,412.30
Amt Left:
27.68%
$1,461,891.33
Delta:
-15.77%
-$918,776.51
$6,980,346.29
Over/Under Est:
13.48%
$828,982.09
Amt Left:
32.16%
$1,698,461.12
Delta:
-3.51%
-$236,569.79
| Subcontractor | Percentage | Amount |
|---|---|---|
| ONE WAY CONCRETE CONSTRUCTION, LLC | 30.33% | $1,616,363.85 |
| PENHALL COMPANY | 5.38% | $286,714.06 |
| PBJ CONSTRUCTION | 4.67% | $248,876.33 |
| TRP CONSTRUCTION GROUP, LLC | 3.50% | $186,524.02 |
| KING & GEORGE, LLC | 3.36% | $179,063.06 |
| GP7 CONSTRUCTION INC. | 3.14% | $167,338.69 |
| BARRICADES UNLIMITED | 0.31% | $16,520.70 |
| ROBIN STEEL LLC | 0.06% | $3,197.55 |
| Total: | 50.75% | $2,704,598.26 |
Bid Items & Bid Tabulations
81
Total
0 of 81