Show Job Controls
Bid Cobra

DAWSON SH 349 (0380-06-019)

Items: 63

County: DAWSON
Length: 0.0000 MILES
Highway: SH 349
District: LUBBOCK
Control Number: 0380-06-019
DBE Goal: 500.0%
Project: F 2026(037)
Guaranty: $100,000.00
Time: 148 WORKING DAYS
Engineer's Estimate: $21,621,141.30
Date: 09/05/2025 (9 months ago) Changed
Contract Number: 9253238
Type: OVERLAY
Project ID: A00128981
Contract Type: Federal
Project Description: LEVEL UP WITH GLASSPAVE AND SMA OVERLAY.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEVE SISNEROS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$21,621,141.30
1
$17,135,619.03
Over/Under Est: -20.75% -$4,485,522.27
$17,912,513.59
Over/Under Est: -17.15% -$3,708,627.71
Amt Left: 4.53% $776,894.56
$18,566,646.08
Over/Under Est: -14.13% -$3,054,495.22
Amt Left: 8.35% $1,431,027.05
Delta: -3.65% -$654,132.49
$20,514,116.95
Over/Under Est: -5.12% -$1,107,024.35
Amt Left: 19.72% $3,378,497.92
Delta: -10.49% -$1,947,470.87
$21,098,029.54
Over/Under Est: -2.42% -$523,111.76
Amt Left: 23.12% $3,962,410.51
Delta: -2.85% -$583,912.59
Over/Under Est: -0.88% -$191,105.24
Amt Left: 25.06% $4,294,417.03
Delta: -1.57% -$332,006.52
$21,668,944.54
Over/Under Est: 0.22% $47,803.24
Amt Left: 26.46% $4,533,325.51
Delta: -1.11% -$238,908.48
$23,443,673.46
Over/Under Est: 8.43% $1,822,532.16
Amt Left: 36.81% $6,308,054.43
Delta: -8.19% -$1,774,728.92
Over/Under Est: 83.8% $18,118,143.49
Amt Left: 131.91% $22,603,665.76
Delta: -69.51% -$16,295,611.33
Subcontractor Percentage Amount
INDUSTRIAL FABRICS, INC. 13.34% $2,285,891.58
DOUBLE A CONTRACTING, L.P. 3.70% $634,017.90
MURRAY CONSTRUCTION 0.83% $142,225.64
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 0.48% $82,250.97
A BROTHERS MILLING, LLC 0.26% $44,552.61
BARRICADES UNLIMITED 0.23% $39,411.92
Total: 18.84% $3,228,350.62

Bid Items & Bid Tabulations

63 Total 0 of 63
DAWSON  |  SH 349  |  LUBBOCK  |  0380-06-019  |  09/05/2025  |  $21,621,141.30  |  F 2026(037)  |  OVERLAY  |  148 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
A. L. HELMCAMP, INC.
DUININCK, INC.
OVERLAND CORPORATION
ZACK BURKETT CO.
JAMES HAMILTON CONSTRUCTION CO.
CI CONSTRUCTORS, INC.
GILVIN-TERRILL, LTD.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
RMV (6") TRT/UNTRT BASE & ASPH PAV
SY 353.900 $10.000 $11.860 $20.000 $20.500 $18.000 $9.500 $42.000 $20.000 $35.000 $5.980
SUBGR WIDEN (DC)
SY 261.500 $10.000 $27.850 $30.000 $24.500 $33.000 $25.500 $64.000 $14.000 $55.000 $35.130
BACKFILL (TY B)
STA 659.000 $250.000 $108.890 $150.000 $110.000 $145.000 $180.000 $400.000 $420.000 $110.000 $348.540
BLADING
STA 659.000 $125.000 $139.000 $50.000 $49.500 $86.000 $74.500 $400.000 $210.000 $110.000 $345.000
REWORK BS MTL (TY C)(6")(DENS CONT)
SY 353.900 $11.000 $19.110 $10.000 $22.500 $15.610 $9.500 $22.000 $21.000 $150.000 $19.400
PRIME COAT (MC-30)
GAL 123.100 $7.000 $24.360 $50.000 $12.000 $18.100 $10.000 $8.000 $20.000 $9.340 $65.360
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 97,472.300 $4.300 $3.210 $2.000 $1.750 $3.240 $2.000 $3.600 $4.000 $3.750 $6.770
FOG SEAL (CSS-1H)
GAL 7,906.400 $5.000 $3.680 $2.000 $2.250 $3.790 $2.000 $4.000 $5.000 $3.750 $7.800
D-GR HMA TY-C PG 70-28 (EXEMPT)
TON 283.100 $200.000 $243.440 $200.000 $400.000 $314.550 $225.000 $400.000 $235.000 $260.000 $425.080
D-GR HMA TY-D SAC-B PG70-28
TON 17,263.900 $150.000 $112.120 $140.000 $144.000 $150.840 $163.000 $154.000 $137.000 $161.500 $183.820
TACK COAT
GAL 69,780.000 $4.500 $3.540 $4.000 $2.000 $2.750 $4.000 $4.000 $4.000 $5.510 $7.880
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
TON 58,741.900 $180.000 $147.190 $160.000 $163.000 $180.000 $180.500 $172.000 $169.000 $197.500 $241.280
TACK COAT
GAL 16,389.700 $5.000 $7.750 $4.000 $2.000 $2.750 $4.000 $4.300 $6.000 $5.510 $7.880
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 4,978.100 $30.000 $28.700 $29.000 $28.000 $31.000 $40.000 $26.000 $45.000 $124.000 $44.310
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 4,978.100 $55.000 $69.990 $78.000 $80.000 $77.000 $86.500 $63.000 $110.000 $149.000 $131.000
PLANE ASPH CONC PAV(0" TO 3")
SY 1,511.100 $30.000 $13.680 $4.000 $18.000 $13.000 $5.000 $8.000 $20.000 $7.140 $11.810
MOBILIZATION
LS 1.000 $1,966,000.000 $750,253.680 $900,000.000 $1,275,000.000 $1,800,000.000 $1,500,000.000 $2,000,000.000 $2,150,000.000 $2,310,000.000 $9,600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $15,000.000 $14,380.000 $9,100.000 $22,000.000 $5,000.000 $8,200.000 $30,000.000 $35,000.000 $50,000.000 $97,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 296.000 $125.000 $107.090 $80.000 $100.000 $85.000 $100.000 $45.000 $200.000 $150.000 $750.000
TMA (STATIONARY)
DAY 296.000 $250.000 $237.080 $100.000 $250.000 $320.000 $260.000 $325.000 $250.000 $500.000 $375.000
TMA (MOBILE OPERATION)
DAY 50.000 $500.000 $506.940 $25.000 $905.000 $1,000.000 $0.010 $900.000 $240.000 $500.000 $1,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 378.000 $40.000 $55.120 $10.000 $52.500 $42.000 $30.000 $35.000 $40.000 $52.000 $40.010
CONSTRUCTION EXITS (REMOVE)
SY 378.000 $15.000 $24.380 $3.000 $23.000 $16.000 $10.000 $7.500 $20.000 $23.000 $32.030
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 5,990.000 $7.000 $6.770 $6.000 $6.400 $9.000 $20.000 $7.000 $10.000 $6.390 $42.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,210.000 $3.500 $1.160 $1.000 $1.100 $2.000 $4.200 $3.500 $3.000 $1.090 $17.750
INTERSECTIONS (ACP)
SY 4,970.800 $115.000 $19.220 $38.000 $44.000 $46.000 $61.500 $70.000 $35.000 $45.000 $103.140
DRIVEWAYS (ACP)
SY 2,000.400 $75.000 $23.320 $38.000 $72.500 $64.000 $68.800 $90.000 $45.000 $45.000 $76.320
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 131,774.000 $0.160 $0.190 $0.250 $0.120 $0.160 $0.210 $0.300 $0.200 $0.990 $0.340
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 65,887.000 $0.180 $0.220 $0.250 $0.140 $0.160 $0.250 $0.400 $0.200 $0.110 $0.440
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 73.000 $750.000 $636.000 $620.000 $605.000 $590.000 $714.000 $660.000 $850.000 $600.000 $822.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 36.000 $940.000 $689.000 $730.000 $655.000 $700.000 $773.500 $715.000 $980.000 $650.000 $960.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 30.000 $910.000 $742.000 $730.000 $705.000 $700.000 $833.000 $770.000 $1,100.000 $700.000 $956.400
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 10.000 $1,150.000 $901.000 $890.000 $855.000 $850.000 $1,011.500 $935.000 $1,450.000 $850.000 $1,197.600
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 1.000 $700.000 $636.000 $730.000 $605.000 $700.000 $714.000 $660.000 $900.000 $600.000 $666.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 6.000 $1,100.000 $954.000 $940.000 $905.000 $900.000 $1,071.000 $990.000 $1,415.000 $900.000 $1,282.800
IN SM RD SN SUP&AM TYS80(2)SA(P)
EA 13.000 $1,950.000 $1,590.000 $1,600.000 $1,500.000 $1,500.000 $1,785.000 $1,650.000 $2,300.000 $1,500.000 $1,894.800
REMOVE SM RD SN SUP&AM
EA 150.000 $112.000 $106.000 $110.000 $100.000 $100.000 $119.000 $110.000 $140.000 $100.000 $241.550
REMOVE LRSA
EA 1.000 $680.000 $1,060.000 $1,000.000 $1,000.000 $950.000 $1,190.000 $1,100.000 $1,700.000 $1,000.000 $10,699.870
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 40.000 $90.000 $106.000 $88.000 $100.000 $85.000 $119.000 $110.000 $123.000 $100.000 $98.400
REMOVE DELIN & OBJECT MARKER ASSMS
EA 40.000 $20.000 $15.900 $25.000 $15.000 $20.000 $17.850 $16.500 $24.000 $15.000 $120.770
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 64,620.000 $0.300 $0.190 $0.180 $0.210 $0.180 $0.210 $0.200 $0.250 $0.210 $0.250
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 259,596.000 $0.300 $0.180 $0.170 $0.200 $0.170 $0.200 $0.200 $0.240 $0.200 $0.240
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 792.000 $0.400 $2.120 $2.000 $0.300 $2.000 $2.380 $0.300 $3.000 $0.300 $0.360
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 507,042.000 $0.230 $0.170 $0.160 $0.200 $0.160 $0.190 $0.200 $0.200 $0.200 $0.240
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 29,745.000 $1.300 $3.100 $0.500 $1.500 $0.740 $1.400 $1.200 $1.900 $0.080 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 39,530.000 $1.300 $3.100 $0.500 $1.500 $0.770 $1.400 $1.200 $1.900 $0.080 $5.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 70.000 $1.000 $3.180 $3.200 $1.000 $3.000 $3.570 $1.100 $3.750 $1.000 $1.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 396.000 $1.000 $2.120 $2.200 $1.000 $2.000 $2.380 $1.100 $2.600 $1.000 $1.200
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 1.000 $400.000 $159.000 $160.000 $400.000 $150.000 $178.500 $440.000 $200.000 $400.000 $480.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 32,310.000 $0.700 $0.690 $0.660 $0.600 $0.650 $0.770 $0.650 $0.800 $0.600 $0.720
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 129,798.000 $0.700 $0.650 $0.620 $0.590 $0.610 $0.730 $0.650 $0.750 $0.590 $0.710
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 253,521.000 $0.650 $0.690 $0.660 $0.590 $0.650 $0.770 $0.650 $0.800 $0.590 $0.710
PREFAB PM TY C (W)(24")(SLD)
LF 651.000 $20.000 $13.780 $13.500 $12.000 $13.000 $15.470 $13.000 $17.000 $12.000 $14.400
PREFAB PM TY C (W)(36")(YLD TRI)
EA 12.000 $70.000 $53.000 $55.000 $50.500 $50.000 $59.500 $55.000 $65.000 $50.000 $60.000
REFL PAV MRKR TY I-C
EA 1,617.000 $3.000 $4.240 $4.500 $4.250 $4.000 $4.760 $4.700 $5.000 $4.250 $5.100
REFL PAV MRKR TY II-A-A
EA 6,390.000 $4.000 $4.240 $4.500 $4.250 $4.000 $4.760 $4.700 $5.000 $4.250 $5.100
ELIM EXT PM & MRKS (6")
LF 81,054.000 $0.750 $0.800 $0.600 $0.650 $0.750 $0.890 $0.700 $1.000 $0.650 $5.780
ELIM EXT PM & MRKS (8")
LF 198.000 $1.250 $2.120 $0.750 $0.750 $2.000 $2.380 $0.800 $2.600 $0.750 $0.900
FULL - WIDTH MOWING
CYC 2.000 $20,000.000 $19,080.000 $4,000.000 $7,000.000 $15,000.000 $21,420.000 $15,400.000 $4,500.000 $2,000.000 $127,580.280
LITTER REMOVAL
CYC 2.000 $5,000.000 $20,935.000 $2,000.000 $3,500.000 $8,500.000 $23,502.500 $5,000.000 $3,500.000 $2,000.000 $55,469.700
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 387,459.200 $6.500 $6.320 $6.200 $5.900 $6.250 $7.020 $6.600 $7.250 $6.000 $12.500
ASPH FOR REINF FAB (PG76-28)
GAL 58,118.900 $5.000 $6.090 $4.600 $3.000 $4.500 $3.750 $5.000 $7.000 $0.100 $10.690
TEMP SPEED MONITOR SYS
EA 2.000 $12,500.000 $10,987.380 $12,000.000 $10,000.000 $7,000.000 $15,000.000 $21,000.000 $20,000.000 $10,000.000 $60,000.000
Totals: $21,621,141.300 $17,135,619.023 $17,912,513.590 $18,566,646.075 $20,514,116.933 $21,098,029.539 $21,430,036.060 $21,668,944.540 $23,443,673.460 $39,739,284.781
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $54,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $11,000.00
Total: $65,000.00