DALLAS US 67 (0261-02-083)

Items: 61

County: DALLAS
Length: 5.2950 MILES
Highway: US 67
District: DALLAS
Control Number: 0261-02-083
DBE Goal: 0.0%
Project: BR 2025(893)
Guaranty: $100,000.00
Time: 196 CALENDAR DAYS
Engineer's Estimate: $6,466,325.75
Date: 07/01/2025 (11 months ago) Changed
Contract Number: 7253209
Type: BRIDGE MAINTENANCE
Project ID: A00205962
Contract Type: Federal
Project Description: BRIDGE REPAIR
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NATHAN PETTER
DUNG NGUYEN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$6,466,325.75
$4,922,876.30
Over/Under Est: -23.87% -$1,543,449.45
Over/Under Est: -15.3% -$989,163.23
Amt Left: 11.26% $554,286.22
Over/Under Est: -8.01% -$517,805.70
Amt Left: 20.83% $1,025,643.75
Delta: -8.61% -$471,357.53
Over/Under Est: 0.7% $45,279.30
Amt Left: 32.27% $1,588,728.75
Delta: -9.47% -$563,085.00
Over/Under Est: 8.41% $543,595.25
Amt Left: 42.39% $2,087,044.70
Delta: -7.65% -$498,315.95
Over/Under Est: 47.58% $3,076,635.98
Amt Left: 93.85% $4,620,085.43
Delta: -36.14% -$2,533,040.73
Subcontractor Percentage Amount
UNIFIED SPECIALTIES LLC 18.27% $899,409.50
HYDRO TECHNOLOGIES, INC. 2.48% $122,087.33
FORTSON CONTRACTING, INC. 1.83% $90,088.64
A-CORE CONCRETE CUTTING, INC. 1.16% $57,105.37
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 1.13% $55,628.50
TEXOP CONSTRUCTION 0.68% $33,475.56
ELITE STRIPING, LLC 0.51% $25,106.67
MONARREZ TRUCKING LLC. 0.01% $492.29
Total: 26.07% $1,283,393.86

Bid Items & Bid Tabulations

61 Total 0 of 61
DALLAS  |  US 67  |  DALLAS  |  0261-02-083  |  07/01/2025  |  $6,466,325.75  |  BR 2025(893)  |  BRIDGE MAINT  |  196 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
GIBSON & ASSOCIATES, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SILVER CREEK CONSTRUCTION, INC.
GREY SKY CONSTRUCTION LLC
INDUS ROAD & BRIDGE, INC.
REMOV CONC (MOWSTRIP)
CY 96.210 $300.000 $195.000 $332.200 $25.000 $300.000 $500.000 $140.000
REMOV CONC (RIPRAP)
SY 1.500 $20.000 $130.000 $652.300 $25.000 $75.000 $1,000.000 $140.000
COMPOST MANUF TOPSOIL (4")
SY 2,195.000 $2.250 $1.750 $6.600 $5.000 $4.000 $10.000 $3.200
BLOCK SODDING
SY 2,195.000 $4.000 $12.000 $7.430 $9.000 $7.000 $10.000 $7.000
VEGETATIVE WATERING
TGL 328.000 $5.000 $10.000 $80.000 $250.000 $99.000 $50.000 $0.100
FULL-DEPTH REP(BR APPR SLAB)(9"-13")
CY 9.200 $850.000 $2,450.000 $1,000.000 $1,800.000 $2,400.000 $5,000.000 $2,800.000
FLOWABLE BACKFILL
CY 2.000 $450.000 $700.000 $608.300 $500.000 $650.000 $650.000 $450.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 11,653.000 $15.000 $4.500 $12.250 $10.000 $17.000 $15.000 $44.450
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 378.000 $85.000 $45.000 $91.000 $325.000 $200.000 $500.000 $110.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 38.000 $140.000 $165.000 $400.000 $400.000 $900.000 $500.000 $180.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 2,013.000 $245.000 $150.000 $187.000 $275.000 $249.000 $265.000 $250.000
RIPRAP (CONC)(4 IN)
CY 2.000 $100.000 $1,180.000 $1,320.000 $2,500.000 $1,500.000 $650.000 $2,800.000
RIPRAP (MOW STRIP)(4 IN)
CY 77.010 $700.000 $680.000 $797.500 $850.000 $975.000 $550.000 $865.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 105.000 $300.000 $215.000 $301.400 $350.000 $450.000 $250.000 $310.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 168.000 $35.000 $35.000 $16.500 $65.000 $64.000 $100.000 $56.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 544.000 $30.000 $40.000 $33.000 $65.000 $42.000 $100.000 $65.000
CLEANING AND SEALING JOINTS (FOAM)
LF 971.000 $90.000 $55.000 $104.500 $140.000 $100.000 $500.000 $155.000
CLEANING & SEALING EXISTING JOINT (SEJ)
LF 76.000 $100.000 $100.000 $121.000 $65.000 $200.000 $100.000 $118.000
CONCRETE OVERLAY (2 IN)
SY 3,263.000 $140.000 $100.000 $125.000 $165.000 $100.000 $45.000 $88.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 8,430.000 $150.000 $107.000 $108.000 $130.000 $135.000 $130.000 $208.000
SPOT CLEAN & PNT EXT STR(SPL PROT SYS)
LS 1.000 $1,507,440.000 $1,475,000.000 $1,381,820.000 $1,300,000.000 $1,400,000.000 $1,500,000.000 $1,751,135.580
RETROFIT RAIL (TY T402)
LF 72.000 $155.000 $515.000 $1,250.000 $150.000 $220.000 $350.000 $750.000
MILLING CONCRETE SLAB (1 IN)
SY 3,263.000 $16.500 $14.500 $21.730 $20.000 $26.000 $25.000 $15.000
HYDRO-DEMOLITION (1 IN)
SY 3,263.000 $130.000 $90.000 $125.000 $140.000 $63.000 $140.000 $170.000
RAISING EXIST STRUCT
EA 1.000 $50,000.000 $17,500.000 $37,000.000 $50,000.000 $175,000.000 $145,000.000 $250,000.000
ADJUST STL SHOES
EA 1.000 $2,000.000 $18,500.000 $15,500.000 $5,000.000 $18,000.000 $16,500.000 $25,000.000
MOBILIZATION
LS 1.000 $650,000.000 $490,000.000 $420,000.000 $500,000.000 $650,000.000 $700,000.000 $950,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $55,000.000 $30,333.000 $24,700.000 $4,000.000 $40,000.000 $15,000.000 $165,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $20,000.000 $15,000.000 $15,500.000 $4,000.000 $25,000.000 $20,000.000 $40,000.000
TMA (STATIONARY)
DAY 400.000 $225.000 $100.000 $160.000 $300.000 $500.000 $250.000 $260.000
TMA (MOBILE OPERATION)
DAY 54.000 $225.000 $100.000 $160.000 $350.000 $1,000.000 $550.000 $740.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,500.000 $5.000 $3.600 $4.400 $7.000 $6.000 $4.000 $3.700
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,500.000 $2.500 $1.250 $1.100 $2.000 $1.250 $2.000 $1.300
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 2,500.000 $10.000 $6.500 $8.800 $20.000 $10.000 $18.000 $6.600
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,500.000 $5.000 $1.250 $1.100 $5.000 $1.250 $9.000 $1.300
MTL W-BEAM GD FEN (TIM POST)
LF 1,518.750 $30.000 $24.000 $26.400 $30.000 $30.000 $30.000 $35.000
MTL W-BEAM GD FEN (STEEL POST)
LF 262.500 $30.000 $30.000 $33.000 $36.000 $40.000 $50.000 $44.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $2,300.000 $2,000.000 $2,200.000 $3,200.000 $2,600.000 $1,850.000 $2,400.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,500.000 $1,200.000 $1,320.000 $2,000.000 $1,900.000 $1,850.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 2,100.000 $3.000 $5.000 $5.500 $7.000 $4.000 $3.000 $7.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $200.000 $250.000 $275.000 $500.000 $550.000 $500.000 $370.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 43.000 $45.000 $25.000 $27.500 $35.000 $28.000 $100.000 $35.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 551.000 $0.500 $2.000 $1.380 $2.500 $1.250 $3.000 $4.200
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 1,650.000 $0.500 $2.000 $1.380 $2.500 $1.250 $3.000 $4.200
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 1,650.000 $0.500 $2.000 $1.380 $2.500 $1.250 $3.000 $4.200
PAVEMENT SLER 6"
LF 14,891.000 $0.500 $0.300 $0.770 $0.500 $0.700 $3.000 $0.500
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 551.000 $0.500 $3.000 $1.930 $4.000 $1.750 $3.000 $6.700
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 7,170.000 $0.500 $1.500 $1.650 $2.000 $1.500 $3.000 $3.300
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 7,055.000 $0.500 $1.500 $1.650 $2.000 $1.500 $3.000 $3.300
REFL PAV MRKR TY II-C-R
EA 44.000 $5.000 $13.000 $55.000 $17.000 $50.000 $6.000 $28.000
ELIM EXT PM & MRKS (4")
LF 8,281.000 $0.500 $1.000 $2.750 $1.300 $2.500 $2.000 $2.200
PAV SURF PREP FOR MRK (6")
LF 14,891.000 $0.500 $0.500 $0.660 $1.000 $0.600 $3.000 $1.100
LONGT CRACK CLEANING AND SEALING (CRCP)
LF 30.000 $25.000 $10.000 $100.000 $8.000 $20.000 $200.000 $74.000
TREE TRIMMING / BRUSH REMOVAL
MI 0.900 $10,000.000 $5,000.000 $12,000.000 $5,000.000 $15,000.000 $10,000.000 $17,700.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 45.000 $1,250.000 $400.000 $550.000 $350.000 $210.000 $350.000 $1,000.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 1,125.000 $45.000 $25.000 $16.500 $25.000 $50.000 $100.000 $50.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 57.000 $120.000 $25.000 $150.000 $125.000 $210.000 $100.000 $180.000
REP STL BRIDGE MBR (WELD REPAIR)
EA 2.000 $2,000.000 $2,500.000 $1,500.000 $3,000.000 $10,000.000 $15,000.000 $12,500.000
BRIDGE JOINT REPAIR (ARMOR)
LF 75.000 $60.000 $175.000 $915.000 $750.000 $1,000.000 $1,000.000 $1,200.000
BRIDGE JOINT REPLACEMENT (SEJ)
LF 111.000 $425.000 $400.000 $917.000 $650.000 $1,200.000 $1,000.000 $500.000
BENT CAP/ABUTMENT CAP CLEANING
EA 8.000 $2,000.000 $1,200.000 $1,100.000 $1,500.000 $2,000.000 $6,500.000 $3,600.000
Totals: $6,466,325.750 $4,922,876.300 $5,477,162.517 $5,948,520.050 $6,511,605.050 $7,009,921.000 $9,542,961.730
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $250,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $175,000.00
Total: $475,000.00