CULBERSON VA (0924-08-007)
Items: 24
County: CULBERSON
Length: N/A
Highway: VA
District: EL PASO
Control Number: 0924-08-007
DBE Goal: N/A
Project: F 2B23(126)
Guaranty: N/A
Time: 80 WORKING DAYS
Engineer's Estimate: $657,328.47
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: INFRASTRUCTURE IMPROVEMENTS
Mail/Deliver Bids To: N/A
Bidders (1)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$657,328.47 | |||
| $752,598.00 |
14.49%
$95,269.53
|
E
Engineer's Estimate
$657,328.47
1
Awarded
$752,598.00
Over/Under Est:
14.49%
$95,269.53
| Subcontractor | Percentage | Amount |
|---|---|---|
| SYNERGY PROJECT CONTRACTORS, INC. | 7.89% | $59,379.98 |
| GUERREROS NEW STAR CONSTRUCTION, LLC | 0.93% | $6,999.16 |
| Total: | 8.82% | $66,379.14 |
Bid Items & Bid Tabulations
24
Total
0 of 24