CULBERSON IH 10 (0003-01-064)

Items: 68

County: CULBERSON
Length: N/A
Highway: IH 10
District: EL PASO
Control Number: 0003-01-064
DBE Goal: 0.0%
Project: F 2024(654)
Guaranty: N/A
Time: 160 WORKING DAYS
Engineer's Estimate: $27,260,465.42
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
ARMANDO RAMIREZ2
MONICA RUIZ
ALDO MADRID
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$27,260,465.42
$29,566,262.03
Over/Under Est: 8.46% $2,305,796.61
$35,946,333.70
Over/Under Est: 31.86% $8,685,868.28
Amt Left: 21.58% $6,380,071.67
Subcontractor Percentage Amount
TRI STATE ELECTRIC, LTD. 4.96% $1,465,593.30
PMI PAVEMENT MARKING, LLC 2.18% $644,151.89
MAJOR MOTION LOGISTICS, LLC 1.20% $354,579.02
HARDY HOLE DRILLING 0.58% $171,379.86
WEST TEXAS ROCK RESOURCES, LLC 0.12% $35,457.90
SOUTHEAST GRINDING AND GROOVING LLC 0.02% $5,909.65
Total: 9.06% $2,677,071.62

Bid Items & Bid Tabulations

68 Total 0 of 68
CULBERSON  |  IH 10  |  EL PASO  |  0003-01-064  |  01/05/2024  |  $27,260,465.42  |  F 2024(654)  |  PREVENT MAINT  |  160 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
A. L. HELMCAMP, INC.
PREPARING ROW
AC 0.360 $12,000.000 $22,000.000 $55,000.000
EXCAVATION (SPECIAL)
CY 4.000 $1,200.000 $1,255.000 $1,400.000
BACKFILL (TY A OR B)
STA 1,607.000 $218.620 $200.000 $400.000
EMULS ASPH (EROSN CONT)(MULTI)
GAL 4,015.000 $4.500 $8.500 $5.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 36,344.000 $53.000 $53.650 $80.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 19,778.000 $4.340 $4.250 $2.000
PLANE ASPH CONC PAV(0" TO 1")
SY 7,193.000 $3.400 $5.250 $4.000
PLANE ASPH CONC PAV(MICRO-MLLING)(1")
SY 718,671.000 $0.850 $1.100 $1.800
PAV JT UNDERSEAL (24")
LF 352.000 $60.000 $230.000 $35.000
DRILL SHAFT (42 IN)
LF 105.000 $1,000.000 $1,160.000 $1,300.000
DRILL SHAFT (48 IN)
LF 90.000 $1,100.000 $1,380.000 $1,500.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 576.000 $200.000 $265.000 $120.000
RIPRAP (CONC)(4 IN)
CY 12.000 $1,000.000 $1,250.000 $1,500.000
RIPRAP (MOW STRIP)(4 IN)
CY 39.000 $850.000 $750.000 $1,600.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 1,724.000 $44.290 $32.000 $50.000
MOBILIZATION
LS 1.000 $391,541.930 $645,000.000 $2,500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $13,857.140 $10,000.000 $15,000.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 324,256.000 $0.190 $0.130 $0.200
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $80.000 $42.000 $50.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $2,000.000 $1,500.000 $2,100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $4,000.000 $3,200.000 $3,500.000
CONDT (PVC) (SCH 40) (2")
LF 370.000 $32.000 $32.000 $35.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 960.000 $38.000 $39.600 $44.000
ELEC CONDR (NO.6) INSULATED
LF 3,045.000 $3.500 $3.150 $3.500
ELEC CONDR (NO.4) INSULATED
LF 780.000 $4.500 $4.700 $5.200
ELEC CONDR (NO.2) INSULATED
LF 1,180.000 $4.500 $5.900 $6.500
GROUND BOX TY A (122311)W/APRON
EA 17.000 $1,500.000 $1,955.250 $2,200.000
ELC SRV TY D 120/240 060(NS)GS(N)GC(O)
EA 1.000 $9,125.000 $9,125.000 $10,000.000
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
EA 2.000 $11,000.000 $10,700.000 $12,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $1,050.000 $1,060.000 $1,200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 4.000 $3,200.000 $5,500.000 $6,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 88.000 $1,350.000 $1,440.000 $1,600.000
REMOVE SM RD SN SUP&AM
EA 59.000 $225.000 $275.000 $300.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 5.000 $220.000 $115.000 $125.000
INS OH SN SUP(30 FT BAL TEE)
EA 3.000 $55,000.000 $56,000.000 $62,000.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 40,533.000 $0.500 $0.320 $1.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 168,187.000 $0.550 $0.260 $0.700
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 162,129.000 $0.600 $0.260 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 14,228.000 $1.180 $2.260 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 320.000 $1.260 $2.000 $3.700
REFL PAV MRK TY I (W)(NUMBER)(090MIL)
EA 8.000 $280.000 $150.000 $340.000
REFL PAV MRK TY I(W)(ENTR GORE)(090MIL)
EA 9.000 $1,000.000 $1,100.000 $1,000.000
REFL PAV MRK TY I(W)(EXIT GORE)(090MIL)
EA 9.000 $812.690 $1,450.000 $2,000.000
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 40,533.000 $1.000 $0.900 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 168,187.000 $1.190 $0.800 $1.000
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 212,733.000 $1.190 $0.900 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 162,129.000 $1.000 $0.800 $1.000
REFL PAV MRKR TY I-R
EA 392.000 $15.810 $4.900 $6.000
REFL PAV MRKR TY II-C-R
EA 3,062.000 $4.190 $4.900 $6.000
D-GR HMA TY-C PG76-22 (LEVEL-UP)
TON 3.000 $109.320 $2,150.000 $2,200.000
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 98,818.000 $145.830 $162.000 $180.000
TACK COAT
GAL 105,934.000 $4.000 $6.000 $4.500
TBWC (MEMBRANE)
GAL 156,806.000 $5.060 $5.000 $5.000
TBWC PG76-22 SAC-A TY C
TON 33,944.000 $160.000 $165.000 $187.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 160.000 $100.000 $135.000 $280.000
ITS SYSTEM SUPPORT EQUIPMENT
LS 1.000 $24,544.300 $15,000.000 $17,000.000
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
EA 5.000 $2,500.000 $7,600.000 $8,500.000
CONDUIT (PREPARE)
LF 10.000 $3.150 $15.000 $17.000
GROUND BOX (PREPARE)
EA 1.000 $650.000 $680.000 $750.000
INSTALL DMS (POLE MTD CABINET)
EA 3.000 $38,000.000 $43,500.000 $48,000.000
ITS POLE (55 FT)(90 MPH)
EA 5.000 $26,700.000 $29,000.000 $32,000.000
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 5.000 $8,500.000 $8,555.000 $9,500.000
MODIFY EXISTING ELECTRICAL SERVICE
EA 1.000 $6,500.000 $4,300.000 $4,800.000
TMA (STATIONARY)
DAY 160.000 $190.360 $195.000 $280.000
TMA (MOBILE OPERATION)
DAY 30.000 $286.580 $325.000 $400.000
SYSTEM INTEGRATION
LS 1.000 $40,000.000 $36,500.000 $40,000.000
INSTALLATION OF CELLULAR MODEM
EA 8.000 $2,500.000 $2,900.000 $3,200.000
BACKLIT W/ PERIMETER LED RDSD SGN
EA 36.000 $8,000.000 $8,000.000 $8,800.000
Totals: $27,260,465.420 $29,566,262.030 $35,946,333.700