PREPARING ROW
|
STA
|
906.000
|
$100.000
|
$153.170
|
$69.780
|
$45.000
|
$572.840
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
166.000
|
$25.000
|
$10.300
|
$63.520
|
$42.000
|
$26.040
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
906.000
|
$250.000
|
$893.430
|
$313.880
|
$600.000
|
$1,169.510
|
|
|
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
|
CY
|
2,124.000
|
$30.000
|
$16.140
|
$21.480
|
$16.000
|
$38.700
|
|
|
BLADING
|
HR
|
458.000
|
$150.000
|
$220.920
|
$299.790
|
$180.000
|
$251.790
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
120,760.000
|
$0.250
|
$0.130
|
$0.170
|
$0.130
|
$0.200
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
60,380.000
|
$0.150
|
$0.100
|
$0.140
|
$0.130
|
$0.170
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
60,380.000
|
$0.150
|
$0.110
|
$0.140
|
$0.130
|
$0.170
|
|
|
PROOF ROLLING
|
HR
|
165.000
|
$100.000
|
$75.190
|
$209.660
|
$123.000
|
$121.900
|
|
|
FL BS (RDWY DEL)(TY A GR 5)(FNAL POS)
|
CY
|
99,860.000
|
$30.000
|
$36.430
|
$42.410
|
$45.150
|
$85.700
|
|
|
CEMENT
|
TON
|
12,634.000
|
$175.000
|
$221.660
|
$179.230
|
$235.000
|
$180.280
|
|
|
CEMENT TREAT (NEW BASE) (8")
|
SY
|
487,389.000
|
$2.500
|
$2.400
|
$1.500
|
$1.500
|
$2.860
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
487,389.000
|
$2.500
|
$1.960
|
$1.860
|
$3.250
|
$2.670
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
164,560.000
|
$4.000
|
$3.830
|
$4.140
|
$3.800
|
$4.420
|
|
|
ASPH (A-R TYPE II)
|
GAL
|
246,845.000
|
$3.500
|
$4.240
|
$5.790
|
$3.800
|
$5.060
|
|
|
ASPH (RC-250)
|
GAL
|
111,800.000
|
$5.000
|
$4.980
|
$4.610
|
$5.000
|
$5.410
|
|
|
AGGR(TY-PB GR-3 SAC-A)
|
CY
|
4,839.000
|
$120.000
|
$132.130
|
$160.010
|
$144.000
|
$208.400
|
|
|
AGGR(TY-B GR-5 SAC-B)
|
CY
|
3,729.000
|
$75.000
|
$85.750
|
$160.260
|
$81.500
|
$170.180
|
|
|
AGGR(TY-PD GR-3 SAC-B)
|
CY
|
4,333.000
|
$80.000
|
$131.770
|
$188.850
|
$188.000
|
$162.920
|
|
|
TEMPORARY SPL SHORING
|
SF
|
3,198.000
|
$15.000
|
$15.450
|
$50.810
|
$53.000
|
$78.080
|
|
|
RIPRAP (CONC)(CL C)
|
CY
|
48.100
|
$750.000
|
$566.630
|
$698.680
|
$880.000
|
$953.720
|
|
|
CMP AR (GAL STL DES 4)
|
LF
|
43.000
|
$110.000
|
$77.270
|
$158.540
|
$352.000
|
$189.380
|
|
|
CMP AR (GAL STL DES 5)
|
LF
|
10.000
|
$150.000
|
$103.020
|
$158.540
|
$518.000
|
$542.340
|
|
|
CMP AR (GAL STL DES 7)
|
LF
|
4.000
|
$150.000
|
$154.540
|
$181.000
|
$690.000
|
$1,219.520
|
|
|
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
|
LF
|
38.500
|
$500.000
|
$772.670
|
$1,048.650
|
$935.000
|
$858.270
|
|
|
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
|
LF
|
39.500
|
$550.000
|
$824.190
|
$1,048.650
|
$1,000.000
|
$917.960
|
|
|
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
|
LF
|
31.000
|
$615.000
|
$978.720
|
$1,081.680
|
$1,100.000
|
$1,250.150
|
|
|
CONC BOX CULV (10 FT X 6 FT)(EXTEND)
|
LF
|
56.250
|
$640.000
|
$1,236.280
|
$1,136.170
|
$1,800.000
|
$1,449.310
|
|
|
CONC BOX CULV (10 FT X 8 FT)(EXTEND)
|
LF
|
18.500
|
$1,015.000
|
$1,545.350
|
$1,603.530
|
$2,800.000
|
$2,085.520
|
|
|
WINGWALL (FW - 0) (HW=7 FT)
|
EA
|
2.000
|
$14,000.000
|
$37,088.330
|
$16,198.740
|
$12,000.000
|
$37,807.170
|
|
|
WINGWALL (FW - 0) (HW=9 FT)
|
EA
|
2.000
|
$14,000.000
|
$43,269.720
|
$18,832.750
|
$19,000.000
|
$34,239.140
|
|
|
SET (TY I)(S=10 FT)(HW=7FT)(3:1)(C)
|
EA
|
6.000
|
$8,500.000
|
$12,877.890
|
$12,686.180
|
$13,000.000
|
$21,763.690
|
|
|
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
|
EA
|
8.000
|
$6,000.000
|
$9,272.080
|
$9,114.170
|
$7,600.000
|
$11,877.570
|
|
|
SET (TY II) (DES 4) (CMP) (3: 1) (C)
|
EA
|
8.000
|
$2,000.000
|
$3,090.690
|
$2,221.160
|
$2,600.000
|
$6,019.420
|
|
|
SET (TY II) (DES 5) (CMP) (3: 1) (C)
|
EA
|
2.000
|
$2,500.000
|
$3,605.810
|
$2,673.640
|
$3,200.000
|
$7,861.640
|
|
|
SET (TY II) (DES 7) (CMP) (6: 1) (C)
|
EA
|
2.000
|
$4,000.000
|
$4,326.970
|
$4,568.540
|
$5,600.000
|
$8,122.780
|
|
|
REMOV STR (WINGWALL)
|
EA
|
10.000
|
$1,100.000
|
$1,802.910
|
$1,733.990
|
$3,000.000
|
$3,187.150
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,225,754.450
|
$1,492,433.180
|
$2,026,748.000
|
$1,800,000.000
|
$3,305,063.530
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
24.000
|
$20,000.000
|
$5,081.980
|
$30,000.000
|
$5,000.000
|
$4,945.510
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
78.000
|
$25.000
|
$46.360
|
$57.160
|
$61.000
|
$51.540
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
78.000
|
$10.000
|
$10.300
|
$12.700
|
$25.000
|
$13.040
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
500.000
|
$5.000
|
$4.120
|
$5.080
|
$10.000
|
$4.720
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
500.000
|
$2.000
|
$1.030
|
$1.270
|
$5.000
|
$1.420
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
900.000
|
$5.000
|
$6.180
|
$7.620
|
$8.000
|
$6.780
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
900.000
|
$2.000
|
$1.030
|
$1.270
|
$1.500
|
$1.280
|
|
|
PTB (FUR & INST)(STEEL)
|
LF
|
200.000
|
$75.000
|
$231.800
|
$317.580
|
$250.000
|
$77.670
|
|
|
PTB (MOVE)(STEEL)
|
LF
|
800.000
|
$7.000
|
$10.300
|
$31.760
|
$5.500
|
$19.260
|
|
|
PTB (STKPL)(STEEL)
|
LF
|
200.000
|
$20.000
|
$15.450
|
$25.410
|
$13.000
|
$38.510
|
|
|
INTERSECTIONS (SURF TREAT)
|
SY
|
695.000
|
$15.000
|
$87.310
|
$40.830
|
$108.000
|
$50.690
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
2,733.000
|
$15.000
|
$66.340
|
$29.260
|
$120.000
|
$45.160
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
500.000
|
$25.000
|
$30.390
|
$41.030
|
$40.000
|
$55.320
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
4.000
|
$1,500.000
|
$1,365.060
|
$1,841.960
|
$1,800.000
|
$1,689.830
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,650.000
|
$3.000
|
$3.610
|
$4.830
|
$5.000
|
$3.950
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$215.000
|
$412.090
|
$587.520
|
$536.000
|
$294.910
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,600.000
|
$3,090.690
|
$4,049.150
|
$4,026.000
|
$3,649.910
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
8.000
|
$250.000
|
$360.580
|
$524.010
|
$470.000
|
$624.910
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
16.000
|
$1,500.000
|
$2,060.460
|
$889.220
|
$520.000
|
$969.620
|
|
|
CRASH CUSH ATTEN (STKPL)
|
EA
|
4.000
|
$1,200.000
|
$2,060.460
|
$762.190
|
$650.000
|
$1,689.830
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$7,000.000
|
$9,272.080
|
$12,068.040
|
$9,600.000
|
$13,239.830
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
36.000
|
$415.000
|
$643.890
|
$875.110
|
$850.000
|
$457.700
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
20.000
|
$100.000
|
$66.970
|
$82.570
|
$88.000
|
$76.430
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
12.000
|
$30.000
|
$41.210
|
$61.390
|
$54.000
|
$576.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
188.000
|
$1.000
|
$3.010
|
$2.540
|
$2.800
|
$2.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,640.000
|
$1.000
|
$2.920
|
$2.540
|
$2.400
|
$1.230
|
|
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
|
LF
|
460.000
|
$1.000
|
$1.030
|
$1.160
|
$2.000
|
$1.350
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
1,880.000
|
$0.200
|
$0.210
|
$0.240
|
$0.300
|
$0.290
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
365,774.000
|
$0.150
|
$0.130
|
$0.240
|
$0.200
|
$0.220
|
|
REFL PAV MRK TY II (Y) 4" (BRK)
|
LF
|
39,220.000
|
$0.150
|
$0.300
|
$0.240
|
$0.200
|
$0.230
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
80,372.000
|
$0.150
|
$0.290
|
$0.240
|
$0.200
|
$0.220
|
|
REFL PAV MRK TY II (Y) 8" (SLD)
|
LF
|
920.000
|
$0.400
|
$0.520
|
$0.470
|
$1.000
|
$0.580
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
|
LF
|
182,887.000
|
$0.450
|
$0.690
|
$1.220
|
$1.000
|
$1.070
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
|
LF
|
40,186.000
|
$0.500
|
$0.690
|
$1.220
|
$1.000
|
$1.070
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
|
LF
|
19,610.000
|
$0.600
|
$0.840
|
$1.220
|
$1.000
|
$1.090
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
940.000
|
$0.400
|
$0.820
|
$0.520
|
$1.000
|
$0.620
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
99.000
|
$3.000
|
$14.940
|
$18.310
|
$18.500
|
$17.460
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
4.000
|
$50.000
|
$61.820
|
$35.310
|
$74.000
|
$70.410
|
|
REFL PAV MRKR TY I-C
|
EA
|
97.000
|
$5.000
|
$5.670
|
$2.350
|
$6.000
|
$3.680
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,508.000
|
$3.000
|
$3.760
|
$2.350
|
$5.000
|
$2.140
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
1,234.000
|
$100.000
|
$12.820
|
$37.060
|
$60.000
|
$74.430
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
160.000
|
$4.000
|
$18.540
|
$12.560
|
$40.000
|
$11.870
|
|
|
PREFORMED CENTERLINE RUMBLE STRIP
|
LF
|
8,008.000
|
$4.000
|
$5.670
|
$20.170
|
$8.000
|
$17.490
|
|
|
TMA (STATIONARY)
|
DAY
|
544.000
|
$150.000
|
$246.730
|
$238.810
|
$240.000
|
$95.890
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
24.000
|
$200.000
|
$618.140
|
$737.080
|
$800.000
|
$1,477.980
|
|
Totals: |
$14,208,777.500
|
$16,675,319.988
|
$18,180,707.856
|
$18,476,731.450
|
$25,847,013.784
|