COMAL FM0306 (6335-01-001)

Items: 14

County: COMAL
Length: N/A
Highway: FM0306
District: SAN ANTONIO
Control Number: 6335-01-001
DBE Goal: N/A
Project: BPM - 633501001
Guaranty: N/A
Time: 35 W
Engineer's Estimate: $117,153.68
Date: 02/13/2019 (7 years ago)
Contract Number: N/A
Type: RIPRAP REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$117,153.68
Over/Under Est: -9.37% -$10,976.68
Over/Under Est: 18.42% $21,582.88
Amt Left: 30.67% $32,559.56
$141,835.00
Over/Under Est: 21.07% $24,681.32
Amt Left: 33.58% $35,658.00
Delta: -2.23% -$3,098.44
Over/Under Est: 34.45% $40,358.32
Amt Left: 48.35% $51,335.00
Delta: -11.05% -$15,677.00
Over/Under Est: 88.42% $103,586.32
Amt Left: 107.9% $114,563.00
Delta: -40.14% -$63,228.00
Over/Under Est: 95.62% $112,017.31
Amt Left: 115.84% $122,993.99
Delta: -3.82% -$8,430.99
Over/Under Est: 118.59% $138,928.32
Amt Left: 141.18% $149,905.00
Delta: -11.74% -$26,911.01

Bid Items & Bid Tabulations

14 Total 0 of 14
COMAL  |  FM0306  |  SAN ANTONIO  |  6335-01-001  |  02/13/2019  |  $117,153.68  |  BPM - 633501001  |  RIPRAP REPAIR  |  35 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
CURRAN CONTRACTING COMPANY
SHANNON-MONK, INC.
CHAMPION INFRASTRUCTURE, LLC
FNH CONSTRUCTION, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
TALBRAN ENTERPRISES LLC
REMOVING CONC (RIPRAP)
SY 305.000 $15.000 $28.000 $22.000 $17.000 $28.000 $30.000 $26.260 $50.000
COMPOST MANUF TOPSOIL (4")
SY 200.000 $1.170 $6.000 $6.450 $7.000 $12.000 $10.000 $7.160 $5.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 200.000 $1.200 $1.000 $5.150 $1.250 $2.000 $10.000 $1.660 $2.000
VEGETATIVE WATERING
MG 3.120 $19.640 $100.000 $100.000 $500.000 $100.000 $1,000.000 $178.970 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 200.000 $0.950 $5.000 $5.600 $6.000 $10.000 $10.000 $6.060 $5.000
RIPRAP (STONE PROTECTION)(30 IN)
CY 105.000 $150.000 $92.000 $280.000 $240.000 $280.000 $350.000 $306.200 $400.000
GABIONS (GALV)
CY 116.000 $300.000 $240.000 $150.000 $240.000 $340.000 $300.000 $297.230 $350.000
GABION MATTRESSES (GALV)(12 IN)
SY 453.000 $66.000 $80.000 $85.750 $105.000 $100.000 $150.000 $196.670 $100.000
MOBILIZATION
LS 1.000 $10,650.000 $9,000.000 $13,000.000 $12,900.000 $15,000.000 $20,000.000 $44,442.330 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $7,000.000 $1,900.000 $9,000.000 $1,300.000 $3,100.000 $8,500.000 $897.840 $10,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 80.000 $2.830 $10.000 $7.950 $12.000 $8.000 $15.000 $24.470 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 80.000 $0.800 $1.000 $4.750 $1.250 $4.000 $9.000 $15.120 $4.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.160 $6,500.000 $2,500.000 $12,994.150 $10,000.000 $3,500.000 $30,000.000 $23,852.300 $10,000.000
TMA (STATIONARY)
DAY 35.000 $155.000 $203.000 $243.850 $385.000 $200.000 $550.000 $248.130 $1,500.000
Totals: $117,153.677 $106,177.000 $138,736.564 $141,835.000 $157,512.000 $220,740.000 $229,171.004 $256,082.000