COLORADO FM 1093 (0446-04-014)
Items: 73
County: COLORADO
Length: N/A
Highway: FM 1093
District: YOAKUM
Control Number: 0446-04-014
DBE Goal: N/A
Project: F 2022(359)
Guaranty: N/A
Time: 255 WORKING DAYS
Engineer's Estimate: $5,918,232.48
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,918,232.48 | |||
| $5,576,114.35 |
-5.78%
-$342,118.13
|
|||
| $6,779,604.79 |
14.55%
$861,372.31
|
21.58%
$1,203,490.44
|
||
| $7,280,609.32 |
23.02%
$1,362,376.84
|
30.57%
$1,704,494.97
|
-7.39%
-$501,004.53
|
|
| $7,321,302.06 |
23.71%
$1,403,069.58
|
31.3%
$1,745,187.71
|
-0.56%
-$40,692.74
|
|
| $7,614,628.50 |
28.66%
$1,696,396.02
|
36.56%
$2,038,514.15
|
-4.01%
-$293,326.44
|
|
| $7,838,443.96 |
32.45%
$1,920,211.48
|
40.57%
$2,262,329.61
|
-2.94%
-$223,815.46
|
|
| $8,864,044.81 |
49.78%
$2,945,812.33
|
58.96%
$3,287,930.46
|
-13.08%
-$1,025,600.85
|
E
Engineer's Estimate
$5,918,232.48
1
Awarded
$5,576,114.35
Over/Under Est:
-5.78%
-$342,118.13
$6,779,604.79
Over/Under Est:
14.55%
$861,372.31
Amt Left:
21.58%
$1,203,490.44
$7,280,609.32
Over/Under Est:
23.02%
$1,362,376.84
Amt Left:
30.57%
$1,704,494.97
Delta:
-7.39%
-$501,004.53
$7,321,302.06
Over/Under Est:
23.71%
$1,403,069.58
Amt Left:
31.3%
$1,745,187.71
Delta:
-0.56%
-$40,692.74
$7,614,628.50
Over/Under Est:
28.66%
$1,696,396.02
Amt Left:
36.56%
$2,038,514.15
Delta:
-4.01%
-$293,326.44
$7,838,443.96
Over/Under Est:
32.45%
$1,920,211.48
Amt Left:
40.57%
$2,262,329.61
Delta:
-2.94%
-$223,815.46
$8,864,044.81
Over/Under Est:
49.78%
$2,945,812.33
Amt Left:
58.96%
$3,287,930.46
Delta:
-13.08%
-$1,025,600.85
Bid Items & Bid Tabulations
73
Total
0 of 73