COLORADO US 90 (0026-06-033)
Items: 64
County: COLORADO
Length: 0.2320 MILES
Highway: US 90
District: YOAKUM
Control Number: 0026-06-033
DBE Goal: 0.0%
Project: BR 2026(338)
Guaranty: $100,000.00
Time: WORKING DAYS
Engineer's Estimate: $5,159,024.00
Date: 02/05/2026 (4 months ago)
Contract Number: 2263208
Type: BRIDGE REPLACEMENT
Project ID: A00130025
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RYAN SIMPER
PAUL RODRIGUEZ
COLORADO US 90 (0026-06-033)
Project Name: N/A
Project: BR 2026(338)
Length: 0.2320 MILES
Project Type: CONSTRUCTION
Limits From: AT COLORADO RIVER RELIEF
Limits To: STR# 0026-06-039
Project Description: REPLACE BRIDGE AND APPROACHES
Bidders (14)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,159,024.00 | |||
| $3,715,521.15 |
-27.98%
-$1,443,502.85
|
|||
| $3,846,184.65 |
-25.45%
-$1,312,839.35
|
3.52%
$130,663.50
|
||
| $3,732,568.92 |
-27.65%
-$1,426,455.08
|
0.46%
$17,047.77
|
2.95%
$113,615.73
|
|
| $4,776,100.98 |
-7.42%
-$382,923.02
|
28.54%
$1,060,579.83
|
-27.96%
-$1,043,532.06
|
|
| $4,068,075.76 |
-21.15%
-$1,090,948.24
|
9.49%
$352,554.61
|
14.82%
$708,025.22
|
|
| $4,207,138.60 |
-18.45%
-$951,885.40
|
13.23%
$491,617.45
|
-3.42%
-$139,062.84
|
|
| $4,687,091.00 |
-9.15%
-$471,933.00
|
26.15%
$971,569.85
|
-11.41%
-$479,952.40
|
|
| $4,619,301.50 |
-10.46%
-$539,722.50
|
24.32%
$903,780.35
|
1.45%
$67,789.50
|
|
| $4,575,062.61 |
-11.32%
-$583,961.39
|
23.13%
$859,541.46
|
0.96%
$44,238.89
|
|
| $4,520,855.40 |
-12.37%
-$638,168.60
|
21.67%
$805,334.25
|
1.18%
$54,207.21
|
|
| $5,228,646.95 |
1.35%
$69,622.95
|
40.72%
$1,513,125.80
|
-15.66%
-$707,791.55
|
|
| $5,053,121.35 |
-2.05%
-$105,902.65
|
36%
$1,337,600.20
|
3.36%
$175,525.60
|
|
| $5,865,235.19 |
13.69%
$706,211.19
|
57.86%
$2,149,714.04
|
-16.07%
-$812,113.84
|
|
| $5,410,539.79 |
4.88%
$251,515.79
|
45.62%
$1,695,018.64
|
7.75%
$454,695.40
|
E
Engineer's Estimate
$5,159,024.00
1
Awarded
$3,715,521.15
Over/Under Est:
-27.98%
-$1,443,502.85
$3,846,184.65
Over/Under Est:
-25.45%
-$1,312,839.35
Amt Left:
3.52%
$130,663.50
$3,732,568.92
Over/Under Est:
-27.65%
-$1,426,455.08
Amt Left:
0.46%
$17,047.77
Delta:
2.95%
$113,615.73
$4,776,100.98
Over/Under Est:
-7.42%
-$382,923.02
Amt Left:
28.54%
$1,060,579.83
Delta:
-27.96%
-$1,043,532.06
$4,068,075.76
Over/Under Est:
-21.15%
-$1,090,948.24
Amt Left:
9.49%
$352,554.61
Delta:
14.82%
$708,025.22
$4,207,138.60
Over/Under Est:
-18.45%
-$951,885.40
Amt Left:
13.23%
$491,617.45
Delta:
-3.42%
-$139,062.84
$4,687,091.00
Over/Under Est:
-9.15%
-$471,933.00
Amt Left:
26.15%
$971,569.85
Delta:
-11.41%
-$479,952.40
$4,619,301.50
Over/Under Est:
-10.46%
-$539,722.50
Amt Left:
24.32%
$903,780.35
Delta:
1.45%
$67,789.50
$4,575,062.61
Over/Under Est:
-11.32%
-$583,961.39
Amt Left:
23.13%
$859,541.46
Delta:
0.96%
$44,238.89
$4,520,855.40
Over/Under Est:
-12.37%
-$638,168.60
Amt Left:
21.67%
$805,334.25
Delta:
1.18%
$54,207.21
$5,228,646.95
Over/Under Est:
1.35%
$69,622.95
Amt Left:
40.72%
$1,513,125.80
Delta:
-15.66%
-$707,791.55
$5,053,121.35
Over/Under Est:
-2.05%
-$105,902.65
Amt Left:
36%
$1,337,600.20
Delta:
3.36%
$175,525.60
$5,865,235.19
Over/Under Est:
13.69%
$706,211.19
Amt Left:
57.86%
$2,149,714.04
Delta:
-16.07%
-$812,113.84
$5,410,539.79
Over/Under Est:
4.88%
$251,515.79
Amt Left:
45.62%
$1,695,018.64
Delta:
7.75%
$454,695.40
Bid Items & Bid Tabulations
64
Total
0 of 64
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) | $500.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $6,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $7,500.00 |