COLLINGSWORTH US 83 (0031-02-031)

Items: 50

County: COLLINGSWORTH
Length: 0.0000 MILES
Highway: US 83
District: CHILDRESS
Control Number: 0031-02-031
DBE Goal: 6.5%
Project: BR 2025(014)
Guaranty: $100,000.00
Time: 125 WORKING DAYS
Engineer's Estimate: $8,803,627.00
Date: 10/02/2024 (1 year ago)
Contract Number: 10243221
Type: BRIDGE MAINTENANCE
Project ID: A00195718
Project Description: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
MATTHEW HERBSTRITT
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$8,803,627.00
$7,277,549.57
Over/Under Est: -17.33% -$1,526,077.43
Over/Under Est: -12.34% -$1,086,259.00
Amt Left: 6.04% $439,818.43
$7,783,735.36
Over/Under Est: -11.58% -$1,019,891.64
Amt Left: 6.96% $506,185.79
Delta: -0.86% -$66,367.36
$8,160,216.00
Over/Under Est: -7.31% -$643,411.00
Amt Left: 12.13% $882,666.43
Delta: -4.84% -$376,480.64
$8,594,319.00
Over/Under Est: -2.38% -$209,308.00
Amt Left: 18.09% $1,316,769.43
Delta: -5.32% -$434,103.00
Over/Under Est: -1.88% -$165,311.69
Amt Left: 18.7% $1,360,765.74
Delta: -0.51% -$43,996.31
$10,857,030.00
Over/Under Est: 23.32% $2,053,403.00
Amt Left: 49.19% $3,579,480.43
Delta: -25.68% -$2,218,714.69
Over/Under Est: 31.05% $2,733,376.00
Amt Left: 58.53% $4,259,453.43
Delta: -6.26% -$679,973.00
Subcontractor Percentage Amount
MACIAS SPECIALTY CONTRACTING LLC 19.41% $1,450,959.53
ALAMO BROTHERS CONCRETE INC 12.77% $954,598.31
IBCTX, LLC 6.37% $476,177.86
TRP CONSTRUCTION GROUP, LLC 1.72% $128,575.50
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 1.02% $76,248.26
NELSON INDUSTRIAL SERVICES, INC. 0.41% $30,648.81
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 0.36% $26,911.15
DUSTROL, INC. 0.28% $20,930.89
BARRICADES UNLIMITED 0.24% $17,940.77
SOUTHEAST GRINDING AND GROOVING LLC 0.13% $9,717.92
Total: 42.71% $3,192,709.00

Bid Items & Bid Tabulations

50 Total 0 of 50
COLLINGSWORTH  |  US 83  |  CHILDRESS  |  0031-02-031  |  10/02/2024  |  $8,803,627.00  |  BR 2025(014)  |  BRIDGE MAINT  |  125 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GIBSON & ASSOCIATES, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
C. E. BARKER, LTD.
GILVIN-TERRILL, LTD.
TI-ZACK CONCRETE, LLC
MB WESTERN INDUSTRIAL CONTRACTING CO.
EARTH BUILDERS, L.P.
SOUTHERN ROAD & BRIDGE, LLC
REMOV CONC (MOWSTRIP)
LF 860.000 $15.000 $74.000 $30.000 $83.430 $20.000 $12.000 $25.000 $50.000 $125.000
EMBANK (FNL)(OC)(TY A)
CY 100.000 $60.000 $225.000 $25.000 $35.750 $350.000 $300.000 $120.000 $65.000 $95.000
PLANE ASPH CONC PAV(3")
SY 1,734.000 $8.000 $10.980 $20.000 $81.040 $24.000 $30.000 $17.730 $40.000 $10.000
FLOWABLE BACKFILL
CY 10.000 $500.000 $1,100.000 $400.000 $286.030 $500.000 $1,200.000 $450.000 $500.000 $1,500.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 960.000 $85.000 $10.000 $30.000 $97.130 $60.000 $66.000 $100.000 $25.000 $125.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 1,650.000 $65.000 $18.010 $32.000 $32.180 $25.000 $28.800 $38.340 $40.000 $55.000
CONC STR REPAIR (EPOXY MORTAR)
SF 100.000 $250.000 $200.000 $300.000 $306.290 $125.000 $480.000 $364.940 $200.000 $245.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 6,300.000 $240.000 $226.000 $275.000 $303.910 $250.000 $212.400 $311.100 $225.000 $315.000
RIPRAP (MOW STRIP)(4 IN)
CY 60.000 $700.000 $720.000 $750.000 $673.370 $850.000 $780.000 $884.500 $750.000 $925.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 150.000 $250.000 $322.300 $300.000 $266.860 $500.000 $150.000 $300.000 $300.000 $225.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 280.000 $65.000 $50.000 $55.000 $58.400 $75.000 $90.000 $69.580 $130.000 $50.000
MULTI-LAYER POLYMER OVERLAY
SY 13,839.000 $45.000 $41.000 $55.000 $44.940 $70.000 $78.000 $49.450 $100.000 $55.000
POLYESTER POLYMER CONC OVERLAY (3")
SY 1,734.000 $600.000 $352.000 $337.000 $420.710 $550.000 $510.000 $564.930 $600.000 $455.000
RETROFIT RAIL (TY SSTR)
LF 6,316.000 $260.000 $172.000 $230.000 $247.890 $275.000 $240.000 $242.820 $470.000 $248.000
MOBILIZATION
LS 1.000 $766,340.000 $1,187,000.000 $770,000.000 $800,000.000 $810,000.000 $647,500.000 $850,000.000 $1,100,000.000 $950,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $22,000.000 $21,275.000 $2,500.000 $6,554.900 $20,000.000 $18,000.000 $10,000.000 $25,000.000 $11,500.000
TMA (STATIONARY)
DAY 120.000 $450.000 $360.000 $300.000 $476.720 $460.000 $120.000 $250.000 $250.000 $325.000
TMA (MOBILE OPERATION)
DAY 6.000 $450.000 $750.000 $300.000 $119.180 $460.000 $6,000.000 $250.000 $700.000 $1,450.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 4.000 $6,000.000 $11,000.000 $20,000.000 $5,318.410 $6,000.000 $12,000.000 $10,000.000 $10,000.000 $8,500.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 4,770.000 $65.000 $35.200 $120.000 $107.860 $100.000 $108.000 $134.200 $170.000 $135.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 4,770.000 $15.000 $26.400 $30.000 $8.340 $5.000 $78.000 $18.300 $35.000 $22.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 4,770.000 $20.000 $33.000 $30.000 $10.730 $10.000 $78.000 $24.400 $25.000 $30.000
MTL W-BEAM GD FEN (STEEL POST)
LF 600.000 $40.000 $33.000 $35.000 $33.370 $28.000 $126.000 $45.800 $38.000 $45.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $2,500.000 $2,249.500 $2,600.000 $2,979.500 $2,200.000 $9,000.000 $4,153.500 $2,800.000 $4,200.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,500.000 $1,243.000 $2,000.000 $1,787.700 $1,500.000 $9,000.000 $1,988.000 $1,800.000 $1,850.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $1,100.000 $1,386.000 $1,300.000 $1,191.800 $1,000.000 $4,200.000 $1,704.000 $1,250.000 $1,650.000
REMOVE METAL BEAM GUARD FENCE
LF 6,600.000 $5.000 $2.200 $3.000 $3.580 $3.000 $8.400 $2.840 $5.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $250.000 $220.000 $250.000 $357.540 $300.000 $3,000.000 $426.000 $300.000 $5,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,500.000 $3,014.000 $3,900.000 $3,813.760 $3,200.000 $14,400.000 $4,544.000 $4,000.000 $4,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $300.000 $330.000 $300.000 $357.540 $300.000 $3,000.000 $426.000 $500.000 $500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $2,000.000 $1,650.000 $3,250.000 $4,171.300 $5,000.000 $6,000.000 $3,550.000 $4,500.000 $4,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,500.000 $2,200.000 $1,500.000 $1,489.750 $2,000.000 $6,000.000 $2,130.000 $1,500.000 $2,250.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $11,000.000 $1,300.000 $12,215.950 $5,000.000 $30,000.000 $12,070.000 $15,000.000 $115,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 35.000 $30.000 $24.200 $25.000 $29.800 $25.000 $30.000 $28.400 $50.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $30.000 $30.800 $32.000 $38.140 $32.000 $30.000 $49.700 $75.000 $45.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
EA 25.000 $30.000 $24.750 $25.000 $29.800 $25.000 $30.000 $28.400 $50.000 $30.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BI)
EA 10.000 $30.000 $30.800 $32.000 $38.140 $32.000 $30.000 $49.700 $75.000 $45.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 600.000 $5.000 $8.800 $8.000 $9.530 $8.000 $6.600 $8.520 $5.000 $5.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 40.000 $10.000 $22.000 $20.000 $23.840 $20.000 $16.500 $21.300 $20.000 $15.000
RE PM TY II (W) 4" (SLD)
LF 17,000.000 $0.500 $1.930 $1.400 $2.090 $1.750 $1.170 $1.510 $1.200 $2.000
RE PM TY II (Y) 4" (SLD)
LF 10,000.000 $0.500 $1.930 $1.400 $2.090 $1.750 $1.200 $1.550 $1.200 $2.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 1,500.000 $1.200 $2.480 $2.700 $2.680 $2.250 $2.260 $2.910 $3.000 $2.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 8,500.000 $1.200 $2.480 $2.500 $2.680 $2.250 $2.200 $2.840 $3.000 $2.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 500.000 $1.200 $2.480 $2.500 $2.680 $2.250 $2.260 $2.910 $3.000 $2.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 7,000.000 $1.200 $2.480 $2.500 $2.680 $2.250 $2.200 $2.840 $3.000 $2.000
ELIM EXT PM & MRKS (4")
LF 42,500.000 $1.200 $0.940 $0.650 $1.010 $0.850 $0.430 $0.550 $1.200 $2.000
ELIM EXT PM & MRKS (24")
LF 40.000 $5.000 $11.000 $4.250 $11.920 $10.000 $11.000 $4.620 $5.000 $6.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 150.000 $85.000 $165.000 $200.000 $73.490 $200.000 $588.000 $125.000 $200.000 $165.000
BRIDGE JOINT REPLACEMENT (ARMOR)
LF 1,672.000 $700.000 $577.000 $400.000 $264.580 $300.000 $186.000 $450.000 $350.000 $1,850.000
CARBON FIBER REINF POLYMER PROTECTION
SF 2,150.000 $350.000 $88.000 $100.000 $84.620 $100.000 $174.000 $100.820 $150.000 $125.000
Totals: $8,803,627.000 $7,277,549.570 $7,717,368.000 $7,783,735.360 $8,160,216.000 $8,594,319.000 $8,638,315.310 $10,857,030.000 $11,537,003.000