Show Job Controls
Bid Cobra

COLLIN SH0078 (6487-69-001)

Items: 32

County: COLLIN
Length: 0.0100 MILES
Highway: SH0078
District: DALLAS
Control Number: 6487-69-001
DBE Goal: 0.0%
Project: RMC - A00216760
Guaranty: $11,000.00
Time: 14 WORKING DAYS
Engineer's Estimate: $451,670.00
Date: 10/15/2025 (7 months ago)
Contract Number: 10251810
Type: CULVERT REPLACEMENT
Project ID: A00216760
Project Description: CULVERT REPLACEMENT
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
DERICK DAVIS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$451,670.00
$461,459.00
Over/Under Est: 2.17% $9,789.00
Over/Under Est: 13.53% $61,108.00
Amt Left: 11.12% $51,319.00
Over/Under Est: 28.18% $127,275.00
Amt Left: 25.46% $117,486.00
Delta: -12.90% -$66,167.00
Over/Under Est: 29% $130,977.00
Amt Left: 26.26% $121,188.00
Delta: -0.64% -$3,702.00
Subcontractor Percentage Amount
SJ&J CONSTRUCTION, LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

32 Total 0 of 32
COLLIN  |  SH0078  |  DALLAS  |  6487-69-001  |  10/15/2025  |  $451,670.00  |  RMC - A00216760  |  CULVERT REPL  |  14 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AAD CONTRACTING INC.
HIGHWAY 19 CONSTRUCTION LLC
ED BELL CONSTRUCTION COMPANY
GARRET SHIELDS INFRASTRUCTURE
PREPARING ROW
STA 1.000 $3,500.000 $1,500.000 $5,000.000 $31,000.000 $5,000.000
EXCAV (ROADWAY)
CY 226.000 $30.000 $19.000 $25.000 $5.000 $50.000
EMBANK (FNL)(DC)(TY C)
CY 240.000 $20.000 $70.000 $50.000 $40.000 $50.000
BLOCK SODDING
SY 435.000 $7.750 $8.000 $10.000 $15.000 $10.000
VEGETATIVE WATERING
TGL 65.000 $1.000 $10.000 $50.000 $10.000 $50.000
CUT & RESTORING PAV
SY 176.000 $245.000 $150.000 $350.000 $200.000 $250.000
CEM STABIL BKFL
CY 210.000 $207.000 $250.000 $350.000 $350.000 $300.000
FLOWABLE BACKFILL
CY 134.000 $366.000 $250.000 $350.000 $350.000 $400.000
TRENCH EXCAVATION PROTECTION
LF 41.000 $18.000 $30.000 $5.000 $75.000 $15.000
TEMPORARY SPL SHORING
SF 2,606.000 $6.010 $15.000 $22.000 $1.000 $40.000
RIPRAP (CONC)(4 IN)
CY 13.000 $588.000 $600.000 $750.000 $800.000 $600.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 24.000 $225.000 $180.000 $180.000 $300.000 $300.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 74.000 $225.000 $220.000 $180.000 $300.000 $300.000
RC PIPE (CL III)(48 IN)
LF 345.000 $310.000 $275.000 $253.000 $350.000 $280.000
HEADWALL (CH - FW - 45) (DIA= 48 IN)
EA 2.000 $25,000.000 $25,000.000 $12,000.000 $25,000.000 $20,000.000
REMOV STR (HEADWALL)
EA 2.000 $2,000.000 $2,000.000 $1,000.000 $5,000.000 $2,000.000
REMOV STR (PIPE)
LF 468.000 $50.000 $50.000 $50.000 $35.000 $20.000
MOBILIZATION
LS 1.000 $37,293.730 $50,000.000 $50,000.000 $57,500.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $2,000.000 $7,000.000 $5,000.000 $42,000.000 $20,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $200.000 $350.000 $100.000 $75.000 $100.000
TMA (STATIONARY)
DAY 14.000 $400.000 $350.000 $500.000 $100.000 $300.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 75.000 $53.000 $20.000 $45.000 $88.000 $30.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 25.000 $65.900 $25.000 $80.000 $100.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $24.670 $1.000 $10.000 $50.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 206.000 $8.020 $4.000 $5.000 $6.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 206.000 $3.240 $1.000 $1.000 $3.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 10.000 $5.940 $4.500 $10.000 $10.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 10.000 $1.350 $1.000 $1.000 $5.000 $1.000
DRIVEWAYS (ACP)
SY 95.000 $80.000 $110.000 $75.000 $125.000 $120.000
RELOCATE EXISTING MAILBOX
EA 1.000 $350.000 $300.000 $250.000 $500.000 $500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $850.000 $300.000 $350.000 $800.000 $1,000.000
INSTL OM ASSM (OM-2Z)(WFLX)GNDLL
EA 2.000 $50.000 $90.000 $35.000 $300.000 $60.000
Totals: $451,670.000 $461,459.000 $512,778.000 $578,945.000 $582,647.000