COLLIN FM 455 (2845-01-022)
Items: 96
County: COLLIN
Length: N/A
Highway: FM 455
District: DALLAS
Control Number: 2845-01-022
DBE Goal: N/A
Project: F 2021(742)
Guaranty: N/A
Time: 276 WORKING DAYS
Engineer's Estimate: $4,769,555.87
Date: 06/03/2021 (5 years ago)
Contract Number: N/A
Type: PROVIDE ADDITIONAL PAVED SURFACE WIDTH
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,769,555.87 | |||
| $4,616,813.49 |
-3.2%
-$152,742.38
|
|||
| $4,739,816.39 |
-0.62%
-$29,739.48
|
2.66%
$123,002.90
|
||
| $4,940,555.94 |
3.59%
$171,000.07
|
7.01%
$323,742.45
|
-4.24%
-$200,739.55
|
|
| $5,309,847.67 |
11.33%
$540,291.80
|
15.01%
$693,034.18
|
-7.47%
-$369,291.73
|
|
| $5,682,533.24 |
19.14%
$912,977.37
|
23.08%
$1,065,719.75
|
-7.02%
-$372,685.57
|
|
| $6,065,663.70 |
27.17%
$1,296,107.83
|
31.38%
$1,448,850.21
|
-6.74%
-$383,130.46
|
|
| $6,085,932.14 |
27.6%
$1,316,376.27
|
31.82%
$1,469,118.65
|
-0.33%
-$20,268.44
|
|
| $8,582,230.13 |
79.94%
$3,812,674.26
|
85.89%
$3,965,416.64
|
-41.02%
-$2,496,297.99
|
E
Engineer's Estimate
$4,769,555.87
1
Awarded
$4,616,813.49
Over/Under Est:
-3.2%
-$152,742.38
$4,739,816.39
Over/Under Est:
-0.62%
-$29,739.48
Amt Left:
2.66%
$123,002.90
$4,940,555.94
Over/Under Est:
3.59%
$171,000.07
Amt Left:
7.01%
$323,742.45
Delta:
-4.24%
-$200,739.55
$5,309,847.67
Over/Under Est:
11.33%
$540,291.80
Amt Left:
15.01%
$693,034.18
Delta:
-7.47%
-$369,291.73
$5,682,533.24
Over/Under Est:
19.14%
$912,977.37
Amt Left:
23.08%
$1,065,719.75
Delta:
-7.02%
-$372,685.57
$6,065,663.70
Over/Under Est:
27.17%
$1,296,107.83
Amt Left:
31.38%
$1,448,850.21
Delta:
-6.74%
-$383,130.46
$6,085,932.14
Over/Under Est:
27.6%
$1,316,376.27
Amt Left:
31.82%
$1,469,118.65
Delta:
-0.33%
-$20,268.44
$8,582,230.13
Over/Under Est:
79.94%
$3,812,674.26
Amt Left:
85.89%
$3,965,416.64
Delta:
-41.02%
-$2,496,297.99
Bid Items & Bid Tabulations
96
Total
0 of 96