COLLIN FM 455 (0816-04-050)

Items: 92

County: COLLIN
Length: N/A
Highway: FM 455
District: DALLAS
Control Number: 0816-04-050
DBE Goal: N/A
Project: BR 2019(009)
Guaranty: N/A
Time: 417 WORKING DAYS
Engineer's Estimate: $3,802,424.41
Date: 09/06/2018 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$3,802,424.41
$4,119,000.00
Over/Under Est: 8.33% $316,575.59
Over/Under Est: 16.5% $627,261.64
Amt Left: 7.54% $310,686.05
Over/Under Est: 17.46% $663,933.21
Amt Left: 8.43% $347,357.62
Delta: -0.83% -$36,671.57
Over/Under Est: 18.97% $721,144.60
Amt Left: 9.82% $404,569.01
Delta: -1.28% -$57,211.39
Over/Under Est: 32.61% $1,240,135.97
Amt Left: 22.42% $923,560.38
Delta: -11.47% -$518,991.37
Over/Under Est: 36.31% $1,380,599.71
Amt Left: 25.83% $1,064,024.12
Delta: -2.79% -$140,463.74
Over/Under Est: 41.93% $1,594,439.99
Amt Left: 31.02% $1,277,864.40
Delta: -4.13% -$213,840.28
Over/Under Est: 45.68% $1,736,885.58
Amt Left: 34.48% $1,420,309.99
Delta: -2.64% -$142,445.59
Over/Under Est: 49.58% $1,885,129.01
Amt Left: 38.08% $1,568,553.42
Delta: -2.68% -$148,243.43

Bid Items & Bid Tabulations

92 Total 0 of 92
COLLIN  |  FM 455  |  DALLAS  |  0816-04-050  |  09/06/2018  |  $3,802,424.41  |  BR 2019(009)  |  REPLACE BRIDGE AND APPROACHES  |  417 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PIERCE R & B LLC
HIGHWAY 19 CONSTRUCTION LLC
COPPELL CONSTRUCTION CO., INC.
IOWA BRIDGE & CULVERT, LC
HODGES AND SON CONSTRUCTION COMPANY, INC.
ACCELERATED CRITICAL PATH, INC.
STATELINE CONSTRUCTION, LLC
ED BELL CONSTRUCTION COMPANY
GHB EQUIPMENT COMPANY, L.L.C.
PREPARING ROW
STA 30.200 $4,000.000 $1,800.000 $1,000.000 $3,500.000 $3,000.000 $2,000.000 $5,450.500 $3,200.000 $11,000.000 $1,000.000
REMOVING STAB BASE AND ASPH PAV(7"-10")
SY 2,357.000 $7.000 $5.500 $6.000 $5.000 $5.460 $8.000 $6.000 $9.000 $5.600 $17.000
REMOVING STAB BASE & ASPH PAV (6" - 8")
SY 1,354.000 $4.100 $4.470 $5.000 $4.500 $5.360 $6.000 $5.000 $9.000 $4.550 $17.000
REMOVING STAB BASE AND ASPH PAV(8.5")
SY 2,150.000 $11.000 $9.650 $11.000 $10.000 $4.940 $12.000 $10.000 $9.000 $9.850 $17.000
EXCAVATION (ROADWAY)
CY 2,939.000 $10.000 $8.000 $10.000 $9.000 $11.430 $15.000 $4.000 $12.000 $10.000 $30.000
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 8,141.000 $12.000 $10.000 $15.000 $12.000 $20.810 $20.000 $19.000 $12.000 $25.000 $30.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 2,034.000 $20.000 $15.000 $17.000 $21.000 $26.520 $15.000 $29.000 $16.000 $30.000 $30.000
BACKFILL (TY A OR B)
STA 7.150 $800.000 $650.000 $650.000 $300.000 $700.400 $500.000 $500.000 $675.000 $420.000 $1,000.000
BLADING
STA 7.150 $250.000 $350.000 $500.000 $300.000 $119.480 $500.000 $350.000 $750.000 $735.000 $700.000
COMPOST MANUF TOPSOIL (4")
SY 12,751.000 $1.270 $1.950 $3.000 $1.500 $2.540 $1.100 $4.000 $3.000 $1.000 $1.500
BLOCK SODDING
SY 667.000 $4.500 $5.000 $5.000 $4.200 $4.330 $6.000 $4.000 $5.000 $5.250 $7.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 11,751.000 $0.200 $0.410 $0.390 $0.180 $0.190 $0.450 $0.200 $1.500 $1.050 $0.500
DRILL SEED (TEMP)(WARM OR COOL)
SY 11,751.000 $0.200 $0.320 $0.300 $0.170 $0.180 $0.350 $0.200 $1.500 $0.250 $0.500
VEGETATIVE WATERING
MG 1,913.000 $12.340 $5.000 $10.000 $44.000 $43.880 $1.000 $18.000 $15.000 $1.050 $37.000
FL BS (CMP IN PLC)(TY D GR1-2)(8")
SY 8,748.000 $11.550 $17.500 $27.000 $10.500 $10.300 $40.000 $18.000 $29.000 $14.000 $42.000
LIME (HYDRATED LIME (SLURRY))
TON 489.000 $150.000 $20.000 $170.000 $165.000 $169.950 $200.000 $190.000 $200.000 $55.700 $200.000
LIME TRT (SUBGRADE)(12")
SY 8,748.000 $6.000 $10.000 $7.000 $3.500 $4.940 $10.000 $7.000 $6.750 $9.450 $11.000
EMULS ASPH (PRIME)(MS-2 OR SS-1)
GAL 2,206.000 $3.440 $8.500 $11.000 $12.000 $12.360 $15.000 $4.500 $9.000 $14.000 $12.000
ASPH (CRS-2P)
GAL 5,514.000 $3.130 $8.900 $5.000 $5.500 $5.670 $6.000 $6.000 $8.000 $5.900 $6.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 4,632.000 $3.340 $7.500 $7.000 $7.400 $7.620 $8.000 $7.000 $8.000 $7.900 $8.000
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 107.000 $200.000 $540.000 $500.000 $600.000 $618.000 $700.000 $350.000 $900.000 $640.000 $700.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 1,213.000 $85.000 $148.000 $128.000 $130.000 $133.900 $135.000 $135.000 $165.000 $144.000 $135.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,965.000 $2.070 $8.000 $9.000 $8.000 $6.180 $10.000 $8.000 $9.000 $8.250 $17.000
PLANE ASPH CONC PAV(0" TO 6")
SY 310.000 $1.660 $15.500 $8.000 $16.000 $10.300 $20.000 $16.000 $9.000 $16.000 $21.000
TEMPORARY SPL SHORING
SF 4,916.000 $24.000 $27.000 $35.000 $21.000 $18.000 $30.000 $30.000 $23.000 $25.000 $37.000
DRILL SHAFT (36 IN)
LF 1,080.000 $135.000 $195.000 $175.000 $177.000 $200.000 $175.000 $270.000 $201.000 $211.000 $250.000
CL C CONC (ABUT)(HPC)
CY 144.400 $930.000 $925.000 $927.000 $1,280.000 $1,150.000 $1,200.000 $1,050.000 $990.000 $1,800.000 $900.000
CL C CONC (CAP)(HPC)
CY 88.000 $950.000 $1,025.000 $1,176.000 $1,250.000 $1,150.000 $1,200.000 $1,050.000 $1,225.000 $1,400.000 $900.000
CL C CONC (COLUMN)(HPC)
CY 59.300 $850.000 $925.000 $983.000 $1,481.000 $1,150.000 $1,300.000 $1,050.000 $1,350.000 $1,300.000 $1,200.000
REINF CONC SLAB (HPC)
SF 18,861.000 $16.000 $16.000 $19.000 $24.500 $21.000 $20.000 $21.000 $20.250 $30.000 $18.000
APPROACH SLAB (HPC)
CY 241.200 $450.000 $475.000 $400.000 $712.000 $500.000 $600.000 $550.000 $675.000 $525.000 $400.000
PRESTR CONC BOX BEAM (5XB20)
LF 2,845.140 $200.000 $228.000 $251.000 $240.000 $195.000 $300.000 $280.000 $210.000 $285.000 $250.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 448.000 $100.000 $110.000 $100.000 $132.000 $120.000 $115.000 $130.000 $135.000 $99.000 $95.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,724.000 $100.000 $100.000 $100.000 $119.000 $135.000 $120.000 $120.000 $140.000 $104.000 $110.000
RIPRAP (MOW STRIP)(4 IN)
CY 49.000 $451.220 $475.000 $400.000 $700.000 $500.000 $550.000 $800.000 $450.000 $525.000 $300.000
RAIL (TY T223)(HPC)
LF 940.000 $110.000 $105.000 $100.000 $129.000 $100.000 $100.000 $140.000 $115.000 $150.000 $45.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 275.500 $91.610 $90.000 $100.000 $91.000 $90.000 $75.000 $75.000 $95.000 $50.000 $66.000
RC PIPE (CL III)(18 IN)
LF 46.000 $54.470 $91.000 $45.000 $83.000 $100.000 $60.000 $100.000 $45.000 $63.000 $66.000
RC PIPE (CL III)(24 IN)
LF 26.000 $66.850 $99.000 $65.000 $118.000 $110.000 $80.000 $140.000 $60.000 $94.500 $77.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $741.860 $1,000.000 $600.000 $1,472.000 $1,500.000 $600.000 $1,000.000 $850.000 $735.000 $1,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,092.200 $1,200.000 $1,200.000 $1,900.000 $2,000.000 $800.000 $1,400.000 $1,000.000 $1,050.000 $1,600.000
REMOV STR (HEADWALL)
EA 4.000 $1,214.600 $1,000.000 $500.000 $2,000.000 $1,500.000 $2,000.000 $900.000 $5,500.000 $735.000 $600.000
REMOV STR (PIPE)
LF 60.000 $20.400 $14.050 $10.000 $23.000 $25.000 $40.000 $20.000 $210.000 $10.500 $30.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $25,000.000 $18,000.000 $20,000.000 $20,000.000 $22,500.000 $40,000.000 $30,000.000 $25,000.000 $17,500.000 $50,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $50,000.000 $25,000.000 $60,000.000 $33,000.000 $30,000.000 $80,000.000 $40,000.000 $42,500.000 $25,000.000 $70,000.000
MOBILIZATION
LS 1.000 $336,195.340 $379,500.000 $200,000.000 $267,500.000 $452,000.000 $400,000.000 $510,000.000 $485,000.000 $495,102.370 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $5,000.000 $2,000.000 $1,250.000 $1,040.000 $1,490.930 $1,000.000 $3,900.000 $4,500.000 $15,750.000 $1,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 135.000 $25.910 $26.500 $25.000 $21.000 $21.630 $10.000 $35.000 $40.000 $22.500 $77.000
ROCK FILTER DAMS (REMOVE)
LF 135.000 $8.420 $11.000 $10.000 $8.000 $8.240 $10.000 $8.000 $12.000 $8.500 $11.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,221.000 $19.380 $21.000 $20.000 $19.250 $19.830 $1.000 $25.000 $28.000 $20.500 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 1,221.000 $7.680 $9.000 $10.000 $8.000 $8.240 $1.000 $8.000 $10.000 $8.500 $7.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,900.000 $2.380 $2.650 $2.550 $1.620 $3.000 $2.000 $2.700 $3.000 $1.750 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,900.000 $0.640 $0.540 $0.500 $0.500 $1.000 $1.000 $0.600 $1.000 $0.550 $1.000
CONSTRUCTING DETOURS
SY 712.000 $80.000 $100.000 $85.000 $130.000 $135.000 $115.000 $110.000 $148.000 $85.000 $200.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 20.000 $5,000.000 $3,000.000 $6,000.000 $7,000.000 $4,500.000 $3,000.000 $7,900.000 $5,500.000 $5,500.000 $4,000.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 2,520.000 $20.000 $39.000 $120.000 $35.000 $50.000 $70.000 $50.000 $85.000 $13.650 $77.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 2,130.000 $5.560 $9.000 $15.000 $8.000 $12.000 $10.000 $7.000 $25.000 $13.650 $7.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 2,520.000 $8.070 $15.000 $15.000 $10.000 $15.000 $15.000 $8.000 $28.000 $4.200 $11.000
DRIVEWAYS (ACP)(TYPE 1)
SY 213.000 $36.410 $60.000 $45.000 $50.000 $55.000 $60.000 $40.000 $52.000 $53.250 $70.000
MTL W-BEAM GD FEN (TIM POST)
LF 337.500 $19.860 $22.000 $21.000 $21.000 $19.660 $26.000 $25.000 $30.000 $20.330 $21.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $1,652.700 $1,600.000 $1,550.000 $1,550.000 $1,493.500 $1,600.000 $1,700.000 $1,800.000 $1,796.450 $16,000.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 25.000 $11.700 $17.000 $15.000 $15.000 $19.660 $25.000 $9.000 $55.000 $20.330 $15.000
SHORT RADIUS
LF 25.000 $30.700 $48.000 $45.000 $45.000 $21.830 $60.000 $55.000 $55.000 $22.570 $45.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $727.600 $1,109.000 $1,000.000 $1,000.000 $643.750 $1,200.000 $950.000 $1,800.000 $665.630 $1,000.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $2.510 $2.180 $2.000 $2.000 $4.120 $20.000 $4.000 $4.000 $4.260 $7.000
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $188.590 $213.000 $250.000 $200.000 $154.500 $200.000 $250.000 $400.000 $159.750 $400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $2,288.980 $2,600.000 $2,465.000 $2,500.000 $2,600.750 $2,500.000 $3,000.000 $2,850.000 $2,689.130 $3,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $1,685.200 $2,090.000 $795.000 $875.000 $1,000.000 $800.000 $1,300.000 $2,800.000 $3,150.000 $12,000.000
CRASH CUSH ATTEN (REMOVE)
EA 10.000 $796.990 $839.010 $500.000 $550.000 $1,250.000 $700.000 $700.000 $2,800.000 $315.000 $500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $8,000.000 $8,800.000 $5,000.000 $4,600.000 $6,750.000 $6,500.000 $9,500.000 $12,500.000 $7,350.000 $5,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 9.000 $500.160 $470.000 $630.000 $500.000 $468.650 $500.000 $500.000 $800.000 $436.650 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 9.000 $554.640 $600.000 $525.000 $645.000 $602.550 $600.000 $600.000 $800.000 $559.130 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $497.510 $798.990 $700.000 $835.000 $471.740 $800.000 $800.000 $800.000 $718.880 $800.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $783.680 $1,015.000 $950.000 $1,042.000 $973.350 $1,000.000 $1,000.000 $800.000 $798.750 $1,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 14.000 $35.740 $19.000 $28.000 $15.000 $29.870 $30.000 $17.000 $28.000 $30.890 $33.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $36.020 $26.000 $45.000 $20.000 $35.020 $50.000 $23.310 $28.000 $36.210 $33.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,746.000 $1.000 $2.100 $2.000 $2.000 $2.200 $2.000 $3.000 $1.000 $2.130 $4.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 6,964.000 $1.000 $1.050 $1.000 $1.000 $1.100 $1.500 $1.000 $1.000 $1.070 $3.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 70.000 $9.000 $13.000 $12.000 $12.000 $13.200 $15.000 $16.000 $6.000 $12.780 $13.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 24,024.000 $1.000 $0.830 $0.800 $0.800 $0.880 $0.850 $1.000 $1.000 $0.850 $3.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 1,084.000 $1.000 $1.100 $1.000 $1.000 $1.100 $1.100 $1.100 $1.000 $1.070 $2.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 1,084.000 $1.000 $1.100 $1.000 $1.000 $1.100 $1.100 $1.100 $1.000 $1.070 $1.100
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 7,697.000 $0.500 $0.630 $0.600 $0.600 $0.660 $0.650 $0.600 $1.000 $0.640 $0.660
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 420.000 $0.500 $1.190 $1.000 $1.000 $1.100 $1.000 $2.700 $2.000 $1.070 $1.100
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 30,540.000 $0.500 $0.520 $0.500 $0.500 $0.550 $0.550 $0.600 $1.000 $0.530 $0.550
REFL PAV MRKR TY II-A-A
EA 400.000 $2.730 $4.300 $1.000 $4.000 $4.400 $4.000 $7.000 $5.000 $4.260 $4.400
ELIM EXT PAV MRK & MRKS (4")
LF 31,809.000 $0.340 $0.500 $0.480 $0.480 $0.530 $0.500 $0.700 $1.000 $0.510 $1.000
PAV SURF PREP FOR MRK (4")
LF 36,493.000 $0.150 $0.110 $0.100 $0.100 $0.110 $0.110 $0.300 $0.500 $0.110 $1.000
FULL - WIDTH MOWING
AC 8.000 $145.290 $440.000 $500.000 $220.000 $500.000 $1,000.000 $200.000 $1,500.000 $211.000 $440.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $6,500.000 $5,000.000 $8,800.000 $12,500.000 $4,500.000 $8,900.000 $15,000.000 $15,000.000 $7,000.000
TMA (STATIONARY)
EA 2.000 $527.570 $13,500.000 $15,000.000 $8,800.000 $2,500.000 $3,000.000 $4,900.000 $30,000.000 $4,500.000 $9,000.000
TMA (MOBILE OPERATION)
HR 60.000 $13.090 $19.990 $50.000 $15.000 $50.000 $15.000 $50.000 $225.000 $95.000 $100.000
Totals: $3,802,424.415 $4,119,000.000 $4,429,686.050 $4,466,357.620 $4,523,569.012 $5,042,560.380 $5,183,024.120 $5,396,864.400 $5,539,309.995 $5,687,553.420