COLLIN US 75 (0047-14-094)

Items: 18

County: COLLIN
Length: 0.0000 MILES
Highway: US 75
District: DALLAS
Control Number: 0047-14-094
DBE Goal: 0.0%
Project: F 2025(802)
Guaranty: $8,000.00
Time: 60 WORKING DAYS
Engineer's Estimate: $399,646.00
Date: 06/05/2025 (1 year ago)
Contract Number: 6253234
Type: LANDSCAPE DEVELOPMENT
Project ID: A00210994
Contract Type: Federal
Project Description: TREES, SHRUBS, GROUNDCOVER AND IRRIGATION
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JENNIFER VORSTER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$399,646.00
$336,918.67
Over/Under Est: -15.7% -$62,727.33
Over/Under Est: -9.04% -$36,144.76
Amt Left: 7.89% $26,582.57
Over/Under Est: -2.41% -$9,647.00
Amt Left: 15.75% $53,080.33
Delta: -7.29% -$26,497.76
Over/Under Est: 4.84% $19,359.75
Amt Left: 24.36% $82,087.08
Delta: -7.44% -$29,006.75
Over/Under Est: 8.93% $35,669.00
Amt Left: 29.2% $98,396.33
Delta: -3.89% -$16,309.25
Over/Under Est: 19.73% $78,856.33
Amt Left: 42.02% $141,583.66
Delta: -9.92% -$43,187.33
Subcontractor Percentage Amount
GV LANDSCAPE AND CONSTRUCTION LLC 66.00% $222,366.32
Total: 66.00% $222,366.32

Bid Items & Bid Tabulations

18 Total 0 of 18
COLLIN  |  US 75  |  DALLAS  |  0047-14-094  |  06/05/2025  |  $399,646.00  |  F 2025(802)  |  LANDSCAPE DEVELOPMENT  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RHINO EQUITY, LLC
SCOUT 5 CONSTRUCTION LLC
CENTRAL NORTH CONSTRUCTION, LLC
ABESCAPE LANDSCAPING, LLC
TIGHT LINE CONSTRUCTION, LLC
RARE EARTH LANDSCAPE SOLUTIONS LLC
PREPARING ROW
AC 1.750 $12,000.000 $1,500.000 $10,000.000 $25,000.000 $325.000 $2,500.000 $45,546.860
VEGETATIVE WATERING
TGL 50.000 $200.000 $150.000 $100.000 $1.000 $800.000 $50.000 $100.000
IRRIGATION SYSTEM
LS 1.000 $30,000.000 $60,000.000 $35,000.000 $129,145.000 $92,000.000 $60,000.000 $43,866.000
MULCH
CY 305.000 $20.000 $60.000 $75.000 $38.000 $60.000 $45.000 $42.050
PLANT BED PREP
SY 2,746.000 $6.000 $0.900 $5.000 $3.000 $2.000 $15.000 $14.400
LANDSCAPE EDGE (CONC)
LF 745.000 $40.000 $8.000 $10.000 $38.000 $5.000 $25.000 $40.200
LOOSE AGGR GRND COVER
CY 546.000 $200.000 $60.000 $300.000 $140.000 $70.000 $225.000 $135.000
PLANT MATERIAL (1 GAL)
EA 3,195.000 $10.000 $8.000 $9.000 $6.000 $25.000 $10.000 $7.250
PLANT MATERIAL (5 GAL)
EA 773.000 $40.000 $29.990 $30.000 $22.000 $55.000 $30.000 $29.280
PLANT MATERIAL (MIN 3" CAL)
EA 7.000 $1,000.000 $1,000.000 $700.000 $800.000 $600.000 $650.000 $985.000
RDSIDE AMENITY (TYPE 1)
EA 9.000 $800.000 $1,500.000 $100.000 $1,500.000 $550.000 $2,000.000 $500.000
RDSIDE AMENITY (TYPE 2)
EA 34.000 $500.000 $1,500.000 $100.000 $500.000 $450.000 $950.000 $325.000
MOBILIZATION
LS 1.000 $40,000.000 $40,000.000 $33,000.000 $12,300.000 $60.000 $30,000.000 $47,000.120
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,000.000 $2,500.000 $0.010 $500.000 $10,000.000 $3,500.000 $9,859.240
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $150.000 $1.000 $0.010 $40.000 $180.000 $100.000 $107.890
TMA (STATIONARY)
DAY 60.000 $300.000 $500.000 $0.010 $25.000 $250.000 $1.000 $400.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,000.000 $5.000 $5.000 $3.000 $1.000 $6.000 $10.000 $6.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $3.000 $2.000 $1.000 $1.000 $2.000 $2.000 $2.250
Totals: $399,646.000 $336,918.670 $363,501.240 $389,999.000 $419,005.750 $435,315.000 $478,502.325
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
Total: $42,000.00