| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0009-03-051 | DALLAS | SH 66 | 02/04/2026 | GARRET SHIELDS INFRASTRUCTURE | 05/26 | 04/26 | 63.15% | $451,143.60 | 6.00% | $714,400.00 |
| 0013-08-150 | WISE | US 81 | 09/05/2025 | RHINO EQUITY, LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 70.00% | $161,053.90 | 35.00% | $230,077.00 |
| 0047-14-094 | COLLIN | US 75 | 06/05/2025 | RHINO EQUITY, LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 66.00% | $222,366.32 | 95.00% | $336,918.67 |
| 6471-34-001 | ELLIS | BI0045G | 11/13/2024 | RHINO EQUITY, LLC | 11/25 | 08/25 | 07/25 | 06/25 | 05/25 | 0.00% | $0.00 | 90.00% | $225,950.00 |
| 6460-57-001 | GRIMES | SH0105 | 06/05/2024 | RHINO EQUITY, LLC | 04/25 | 02/25 | 01/25 | 12/24 | 11/24 | 0.00% | $0.00 | 113.00% | $270,970.00 |
| 0027-04-042 | WHARTON | US 90A | 08/05/2021 | SJ&J CONSTRUCTION, LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 7.38% | $278,625.92 | 97.00% | $3,775,419.00 |