Show Job Controls
Bid Cobra

CLAY FM 174 (0137-10-025)

Items: 13

County: CLAY
Length: N/A
Highway: FM 174
District: WICHITA FALLS
Control Number: 0137-10-025
DBE Goal: N/A
Project: STP 1902(144)HES
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $700,317.97
Date: 07/09/2019 (6 years ago)
Contract Number: N/A
Type: MILLED CENTERLINE RUMBLE STRIPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$700,317.97
$656,778.16
Over/Under Est: -6.22% -$43,539.81
$680,315.67
Over/Under Est: -2.86% -$20,002.30
Amt Left: 3.58% $23,537.51
Over/Under Est: 0.36% $2,520.72
Amt Left: 7.01% $46,060.53
Delta: -3.31% -$22,523.02
Over/Under Est: 11.16% $78,181.29
Amt Left: 18.53% $121,721.10
Delta: -10.76% -$75,660.57

Bid Items & Bid Tabulations

13 Total 0 of 13
CLAY  |  FM 174  |  WICHITA FALLS  |  0137-10-025  |  07/09/2019  |  $700,317.97  |  STP 1902(144)HES  |  MILLED CENTERLINE RUMBLE STRIPS  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, INC.
FLAT LINE, INC.
D. I. J. CONSTRUCTION, INC.
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $61,392.540 $24,350.000 $25,000.000 $23,500.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $200.000 $100.000 $100.000 $3,500.000
RUMBLE STRIPS (CENTERLINE)
LF 699,067.000 $0.140 $0.130 $0.220 $0.240 $0.230
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 12.000 $900.000 $845.000 $850.000 $625.000 $999.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 53.000 $700.000 $695.000 $750.000 $525.000 $491.000
REMOVE SM RD SN SUP&AM
EA 12.000 $85.000 $100.000 $125.000 $150.000 $112.000
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 113,034.000 $0.700 $0.545 $0.640 $0.690 $0.600
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 8,560.000 $1.000 $0.545 $0.660 $0.850 $0.700
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 93,350.000 $0.280 $0.350 $0.280 $0.350 $0.380
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,039,285.000 $0.250 $0.325 $0.275 $0.290 $0.330
REFL PAV MRKR TY II-A-A
EA 19,452.000 $2.750 $2.800 $2.850 $2.750 $3.450
TMA (STATIONARY)
DAY 10.000 $150.000 $10.000 $200.000 $100.000 $100.000
TMA (MOBILE OPERATION)
DAY 110.000 $350.000 $10.000 $20.000 $1.000 $50.000
Totals: $700,317.970 $656,778.165 $680,315.675 $702,838.690 $778,499.260