CAMERON ODOMS LN (0921-06-355)
Items: 52
County: CAMERON
Length: 0.0000 MILES
Highway: ODOMS LN
District: PHARR
Control Number: 0921-06-355
DBE Goal: 4.0%
Project: STP 2025(933)HES
Guaranty: $26,000.00
Time: 224 WORKING DAYS
Engineer's Estimate: $1,337,871.27
Date: 08/08/2025 (10 months ago)
Contract Number: 8253220
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184386
Contract Type: Federal
Project Description: WIDEN LANES & CONSTRUCT PAVED SHOULDERS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ANDRES ESPINOZA
GABRIEL VILLARREAL
CAMERON ODOMS LN (0921-06-355)
Project Name: N/A
Project: STP 2025(933)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: ON ODOMS RD., FROM BAKER POTTS RD.
Limits To: 0.18 MILES EAST OF ALTAS PALMAS RD.
Project Description: WIDEN LANES & CONSTRUCT PAVED SHOULDERS
CAMERON REYES RD (0921-06-358)
Project Name: CENTERLINE RD.
Project: STP 2025(934)HRR
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: ON CENTERLINE RD, FROM FERNANDO RD.
Limits To: COUNTY ROAD 544
Project Description: WIDEN LANES & CONSTRUCT PAVED SHOULDERS (1-4')
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,337,871.27 | |||
| $978,047.44 |
-26.9%
-$359,823.83
|
|||
| $1,488,576.99 |
11.26%
$150,705.72
|
52.2%
$510,529.55
|
||
| $1,691,066.50 |
26.4%
$353,195.23
|
72.9%
$713,019.06
|
-13.60%
-$202,489.51
|
|
| $1,697,893.00 |
26.91%
$360,021.73
|
73.6%
$719,845.56
|
-0.40%
-$6,826.50
|
|
| $1,927,543.65 |
44.08%
$589,672.38
|
97.08%
$949,496.21
|
-13.53%
-$229,650.65
|
|
| $2,056,429.50 |
53.71%
$718,558.23
|
110.26%
$1,078,382.06
|
-6.69%
-$128,885.85
|
E
Engineer's Estimate
$1,337,871.27
1
Awarded
$978,047.44
Over/Under Est:
-26.9%
-$359,823.83
$1,488,576.99
Over/Under Est:
11.26%
$150,705.72
Amt Left:
52.2%
$510,529.55
$1,691,066.50
Over/Under Est:
26.4%
$353,195.23
Amt Left:
72.9%
$713,019.06
Delta:
-13.60%
-$202,489.51
$1,697,893.00
Over/Under Est:
26.91%
$360,021.73
Amt Left:
73.6%
$719,845.56
Delta:
-0.40%
-$6,826.50
$1,927,543.65
Over/Under Est:
44.08%
$589,672.38
Amt Left:
97.08%
$949,496.21
Delta:
-13.53%
-$229,650.65
$2,056,429.50
Over/Under Est:
53.71%
$718,558.23
Amt Left:
110.26%
$1,078,382.06
Delta:
-6.69%
-$128,885.85
| Subcontractor | Percentage | Amount |
|---|---|---|
| TEXAS HIGHWAY SYSTEMS, INC. | 3.07% | $30,026.06 |
| TEXAS ICON CONSTRUCTION, LLC | 2.55% | $24,940.21 |
| PAVEMENT MARKINGS INC. | 1.66% | $16,235.59 |
| Total: | 7.28% | $71,201.86 |
Bid Items & Bid Tabulations
52
Total
0 of 52
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $61,938.48 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $24,775.39 |
| Total: | $86,713.87 |