CALDWELL SH 21 (0471-04-030)

Items: 110

County: CALDWELL
Length: N/A
Highway: SH 21
District: AUSTIN
Control Number: 0471-04-030
DBE Goal: N/A
Project: NH 1902(253)
Guaranty: N/A
Time: 336 WORKING DAYS
Engineer's Estimate: $12,289,976.95
Date: 10/03/2019 (6 years ago)
Contract Number: N/A
Type: SUPER-2 HIGHWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$12,289,976.95
$12,225,105.21
Over/Under Est: -0.53% -$64,871.74
$12,774,997.09
Over/Under Est: 3.95% $485,020.14
Amt Left: 4.5% $549,891.88
$14,708,233.79
Over/Under Est: 19.68% $2,418,256.84
Amt Left: 20.31% $2,483,128.58
Delta: -15.13% -$1,933,236.70
Over/Under Est: 20.99% $2,579,130.66
Amt Left: 21.63% $2,644,002.40
Delta: -1.09% -$160,873.82
Over/Under Est: 25.99% $3,194,281.94
Amt Left: 26.66% $3,259,153.68
Delta: -4.14% -$615,151.28
Over/Under Est: 30.18% $3,709,643.88
Amt Left: 30.88% $3,774,515.62
Delta: -3.33% -$515,361.94

Bid Items & Bid Tabulations

110 Total 0 of 110
CALDWELL  |  SH 21  |  AUSTIN  |  0471-04-030  |  10/03/2019  |  $12,289,976.95  |  NH 1902(253)  |  SUPER-2 HWY  |  336 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANGEL BROTHERS HOLDINGS CORP.
HUNTER INDUSTRIES, LTD.
DEAN WORD COMPANY, LTD.
AARON CONCRETE CONTRACTORS, L.P.
JAMES CONSTRUCTION GROUP, L.L.C.
CURRAN CONTRACTING COMPANY
PREPARING ROW
STA 375.000 $1,000.000 $750.000 $1,245.420 $723.393 $500.000 $2,835.000 $3,700.000
REMOVING CONC (DRIVEWAYS)
SY 319.000 $14.000 $14.000 $17.880 $21.440 $32.000 $12.310 $14.440
REMOV STAB BASE AND ASPH PAV (2"-15")
SY 16,798.000 $5.000 $6.700 $7.540 $9.462 $18.000 $3.060 $9.870
EXCAVATION (ROADWAY)
CY 16,533.000 $6.500 $11.750 $14.550 $12.711 $16.000 $5.560 $16.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 5,646.000 $9.000 $7.250 $14.550 $7.492 $16.000 $20.440 $2.910
FURNISHING AND PLACING TOPSOIL (4")
SY 69,171.000 $0.700 $1.000 $1.320 $1.175 $1.600 $0.530 $8.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 14.290 $730.000 $800.000 $925.000 $656.250 $980.000 $675.000 $714.470
VEGETATIVE WATERING
MG 1,185.000 $12.000 $16.000 $24.360 $20.091 $35.000 $32.000 $24.250
SOIL RETENTION BLANKETS (CL 2) (TY E)
SY 21.000 $1.550 $10.750 $2.500 $29.400 $16.000 $30.000 $27.480
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 22,339.000 $47.000 $51.000 $52.010 $53.122 $66.000 $57.400 $63.000
LIME TRT (EXST MATL)(8")
SY 80,386.000 $2.500 $2.750 $3.420 $3.990 $4.500 $4.960 $2.980
LIME (HYD, COM OR QK)(SLURRY)
TON 1,593.000 $185.000 $160.000 $162.750 $174.698 $180.000 $181.560 $159.790
PRIME COAT (MULTI OPTION)
GAL 10,505.000 $3.500 $4.200 $3.950 $3.981 $4.000 $3.560 $3.750
D-GR HMA TY-C PG64-22
TON 34,850.000 $70.000 $69.000 $70.050 $85.790 $96.000 $83.930 $79.000
D-GR HMA TY-D PG76-22
TON 25,413.000 $80.000 $73.700 $71.790 $88.662 $94.000 $83.930 $86.000
TOM (ASPHALT) PG 76-22
TON 738.000 $87.000 $102.000 $110.820 $104.046 $120.000 $106.810 $121.000
TOM - C (AGGREGATE) SAC - B
TON 11,252.000 $87.000 $102.000 $110.820 $104.046 $120.000 $106.810 $121.000
TACK COAT
GAL 15,693.000 $3.000 $2.500 $3.080 $2.912 $3.500 $3.050 $3.350
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 17,200.000 $30.000 $30.000 $27.940 $41.317 $45.000 $40.690 $35.460
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 163,783.000 $1.500 $1.600 $1.720 $2.880 $3.000 $2.110 $1.270
TEMPORARY SPL SHORING
SF 801.000 $13.000 $15.750 $15.140 $47.250 $38.000 $49.440 $29.580
RIPRAP (CONC)(5 IN)
CY 498.000 $425.000 $445.000 $434.320 $555.510 $500.000 $448.370 $366.720
RIPRAP (STONE PROTECTION)(18 IN)
CY 26.000 $110.000 $258.000 $170.000 $232.600 $130.000 $210.830 $207.260
RIPRAP (MOW STRIP)(4 IN)
CY 501.000 $425.000 $464.000 $468.550 $608.010 $450.000 $595.830 $508.780
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 15.000 $425.000 $500.000 $513.750 $509.250 $1,030.000 $532.900 $493.250
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 20.000 $550.000 $590.000 $605.250 $525.000 $1,045.000 $549.390 $581.100
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 8.000 $515.000 $645.000 $660.380 $525.000 $1,300.000 $549.390 $634.020
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 11.000 $590.000 $590.000 $600.840 $551.250 $1,150.000 $576.850 $576.870
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 9.000 $625.000 $835.000 $856.620 $630.000 $1,410.000 $659.260 $822.430
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 6.000 $680.000 $875.000 $918.360 $735.000 $1,300.000 $769.140 $1,890.260
CONC BOX CULV (8 FT X 5 FT)(EXTEND)
LF 12.000 $900.000 $890.000 $918.360 $945.000 $1,480.000 $988.890 $881.710
RC PIPE (CL III)(18 IN)
LF 2,095.000 $52.000 $66.000 $66.140 $52.500 $95.000 $54.940 $63.500
RC PIPE (CL III)(36 IN)
LF 9.000 $150.000 $480.000 $489.500 $262.500 $470.000 $274.690 $469.960
RC PIPE (ARCH)(CL III)(DES 1)
LF 444.000 $120.000 $160.000 $173.800 $194.250 $180.000 $203.270 $166.870
RC PIPE (ARCH)(CL III)(DES 2)
LF 32.000 $240.000 $190.000 $206.160 $210.000 $184.000 $219.750 $197.930
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $8,700.000 $4,825.000 $4,950.080 $7,875.000 $17,845.000 $8,240.780 $5,661.180
WINGWALL (PW - 1) (HW=3 FT)
EA 5.000 $4,400.000 $3,850.000 $3,957.860 $5,775.000 $9,200.000 $6,043.230 $4,217.020
WINGWALL (PW - 1) (HW=4 FT)
EA 3.000 $7,200.000 $5,150.000 $5,280.820 $7,350.000 $11,100.000 $7,691.390 $5,845.240
WINGWALL (PW - 1) (HW=5 FT)
EA 4.000 $9,500.000 $6,400.000 $6,603.780 $9,450.000 $14,100.000 $9,888.930 $7,681.680
WINGWALL (PW - 1) (HW=6 FT)
EA 5.000 $16,000.000 $9,300.000 $9,580.440 $14,175.000 $19,100.000 $14,833.390 $10,661.150
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $17,000.000 $11,800.000 $12,116.110 $18,900.000 $25,400.000 $19,777.850 $13,798.240
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 86.000 $1,200.000 $975.000 $981.200 $945.000 $1,800.000 $988.890 $942.040
SET (TY II) (36 IN) (CMP) (6: 1) (P)
EA 2.000 $2,800.000 $3,750.000 $4,398.840 $4,200.000 $3,100.000 $4,395.080 $4,406.040
SET (TY II) (DES 1) (RCP) (6: 1) (P)
EA 30.000 $4,500.000 $2,350.000 $2,193.910 $945.000 $2,400.000 $988.890 $2,151.480
SET (TY II) (DES 2) (CMP) (6: 1) (P)
EA 2.000 $780.000 $1,800.000 $2,193.910 $1,260.000 $1,540.000 $1,318.530 $2,174.040
REMOV STR (SET)
EA 76.000 $700.000 $400.000 $417.840 $630.000 $500.000 $659.260 $434.670
REMOV STR (WINGWALL)
EA 17.000 $1,200.000 $1,170.000 $1,201.690 $1,050.000 $1,000.000 $1,098.770 $777.290
REMOV STR (HEADWALL)
EA 1.000 $1,300.000 $1,170.000 $1,201.690 $1,050.000 $1,000.000 $1,098.770 $1,347.020
REMOV STR (PIPE)
LF 1,872.000 $14.000 $17.000 $16.430 $31.500 $32.000 $32.960 $17.650
MOBILIZATION
LS 1.000 $1,117,300.000 $1,064,730.000 $1,130,178.910 $1,482,003.662 $150,000.000 $1,500,000.000 $1,532,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 42.000 $5,000.000 $2,400.000 $2,451.320 $4,878.485 $1,100.000 $9,904.340 $8,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,380.000 $24.000 $23.000 $23.500 $24.675 $33.000 $22.750 $24.080
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 75.000 $24.000 $28.500 $29.500 $30.975 $36.000 $67.500 $71.450
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 205.000 $47.000 $50.000 $75.000 $78.750 $66.000 $49.500 $52.390
ROCK FILTER DAMS (REMOVE)
LF 1,660.000 $11.000 $10.500 $12.500 $13.125 $18.000 $15.000 $15.880
TEMP SEDMT CONT FENCE (INSTALL)
LF 32,627.000 $2.200 $1.600 $1.890 $1.985 $3.500 $2.300 $2.430
TEMP SEDMT CONT FENCE (REMOVE)
LF 32,627.000 $0.600 $0.650 $0.250 $0.263 $1.300 $0.950 $1.010
DRIVEWAYS (ACP)
SY 7,491.000 $35.000 $34.750 $35.040 $34.048 $40.000 $54.030 $47.010
DRIVEWAYS (CONC) (HES)
SY 270.000 $95.000 $89.000 $85.550 $136.500 $95.000 $61.150 $66.410
MTL W-BEAM GD FEN (TIM POST)
LF 7,075.000 $18.500 $22.000 $19.390 $20.700 $22.000 $21.460 $22.710
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $150.000 $62.000 $53.870 $52.500 $59.000 $58.140 $61.540
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $2,125.000 $2,154.740 $2,011.800 $1,600.000 $1,575.000 $1,667.090
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 9.000 $995.000 $1,175.000 $1,023.500 $997.500 $1,150.000 $1,125.000 $1,190.780
REMOVE METAL BEAM GUARD FENCE
LF 4,908.000 $2.500 $1.000 $2.150 $2.100 $1.000 $1.000 $1.990
GUARDRAIL END TREATMENT (INSTALL)
EA 41.000 $2,250.000 $2,900.000 $2,477.960 $2,415.000 $2,800.000 $2,761.000 $2,922.440
GUARDRAIL END TREATMENT (REMOVE)
EA 42.000 $250.000 $155.000 $215.470 $210.000 $152.000 $150.000 $158.770
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 33.000 $220.000 $160.000 $250.000 $183.750 $158.000 $175.000 $165.070
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 9.000 $240.000 $275.000 $275.000 $206.850 $266.000 $197.000 $277.520
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 5.000 $360.000 $450.000 $550.000 $357.000 $431.000 $340.000 $132.310
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 17.000 $470.000 $475.000 $425.000 $481.950 $465.000 $459.000 $484.900
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 29.000 $530.000 $550.000 $450.000 $511.350 $543.000 $487.000 $566.310
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 2.000 $730.000 $775.000 $600.000 $601.650 $751.000 $573.000 $783.360
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $560.000 $625.000 $700.000 $653.100 $612.000 $622.000 $638.520
REMOVE SM RD SN SUP&AM
EA 38.000 $80.000 $75.000 $65.000 $94.500 $101.000 $90.000 $105.850
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 3.000 $50.000 $43.000 $65.000 $75.600 $42.000 $72.000 $43.340
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 14.000 $55.000 $49.000 $75.000 $75.600 $48.000 $72.000 $50.120
INSTL OM ASSM (OM-3L)(FLX)SRF
EA 18.000 $180.000 $240.000 $85.000 $183.750 $233.000 $175.000 $243.450
INSTL OM ASSM (OM-3R)(FLX)SRF
EA 23.000 $180.000 $240.000 $85.000 $183.750 $233.000 $175.000 $243.450
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 13.000 $14.000 $20.000 $15.000 $26.250 $19.000 $25.000 $19.850
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 104.000 $14.000 $20.000 $15.000 $26.250 $19.000 $25.000 $19.320
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 73,700.000 $0.150 $0.230 $0.220 $0.231 $0.220 $0.220 $0.260
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 89,400.000 $0.200 $0.230 $0.220 $0.231 $0.220 $0.220 $0.260
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,848.000 $3.500 $3.150 $3.000 $3.150 $3.050 $3.000 $3.180
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,000.000 $1.000 $1.000 $1.250 $1.441 $0.840 $0.750 $7.820
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,000.000 $1.000 $1.000 $1.250 $1.441 $1.700 $0.790 $7.820
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 73,700.000 $1.100 $0.950 $1.500 $1.232 $1.350 $1.070 $0.070
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,515.000 $0.750 $0.520 $0.500 $0.525 $0.500 $0.500 $2.650
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,971.000 $0.750 $0.700 $0.670 $0.704 $0.700 $0.670 $1.010
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 14.000 $150.000 $125.000 $121.000 $127.050 $123.000 $121.000 $158.770
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 10.000 $510.000 $375.000 $366.000 $384.300 $370.000 $366.000 $264.620
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 14.000 $140.000 $140.000 $137.000 $143.850 $139.000 $137.000 $185.230
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 81,696.000 $0.400 $0.660 $0.640 $0.672 $0.650 $0.640 $0.790
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 96,270.000 $0.400 $0.660 $0.640 $0.672 $0.650 $0.640 $0.790
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 6,020.000 $0.400 $0.380 $0.360 $0.378 $0.370 $0.360 $0.370
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 84.000 $15.000 $13.000 $12.000 $12.600 $12.170 $12.000 $9.530
REFL PAV MRKR TY I-C
EA 452.000 $3.000 $4.150 $4.000 $4.200 $4.060 $4.000 $5.290
REFL PAV MRKR TY II-A-A
EA 2,693.000 $3.000 $3.500 $3.370 $3.539 $3.420 $3.370 $5.290
ELIM EXT PAV MRK & MRKS (4")
LF 8,066.000 $1.500 $0.650 $0.630 $0.662 $0.640 $0.630 $0.530
PAV SURF PREP FOR MRK (4")
LF 185,504.000 $0.200 $0.060 $0.050 $0.053 $0.050 $0.050 $0.010
PAV SURF PREP FOR MRK (8")
LF 2,971.000 $0.700 $0.160 $0.150 $0.158 $0.150 $0.150 $0.020
PAV SURF PREP FOR MRK (24")
LF 84.000 $2.000 $1.050 $1.000 $1.050 $1.010 $1.000 $0.060
PAV SURF PREP FOR MRK (ARROW)
EA 24.000 $11.000 $37.000 $35.000 $36.750 $35.490 $35.000 $5.290
PAV SURF PREP FOR MRK (WORD)
EA 14.000 $35.000 $37.000 $35.000 $36.750 $35.490 $35.000 $5.290
SPALLING REPAIR (HYDRAULIC CEMENT)
CF 58.000 $220.000 $250.000 $250.000 $1,207.500 $425.000 $872.930 $405.540
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 20.000 $130.000 $230.000 $100.000 $346.500 $350.000 $414.820 $529.620
BONDING COURSE
GAL 19,107.000 $2.000 $2.800 $3.290 $3.984 $3.400 $3.050 $3.940
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 80.000 $60.000 $75.000 $261.970 $280.000 $76.000 $150.300 $190.000
TMA (STATIONARY)
EA 2.000 $7,500.000 $25,000.000 $7,858.980 $28,000.000 $51,000.000 $19,238.190 $10,200.000
TMA (STATIONARY)
DAY 80.000 $200.000 $200.000 $209.570 $252.000 $51.000 $105.210 $180.000
TMA (MOBILE OPERATION)
DAY 20.000 $250.000 $350.000 $366.750 $504.000 $76.000 $637.400 $650.000
Totals: $12,289,976.950 $12,225,105.210 $12,774,997.090 $14,708,233.916 $14,869,107.610 $15,484,258.890 $15,999,620.836