Bid Cobra

BURNET SH 29 (0151-02-026)

Items: 108

County: BURNET
Length: 4.1750 MILES
Highway: SH 29
District: AUSTIN
Control Number: 0151-02-026
DBE Goal: 0.0%
Project: F 2026(606)
Guaranty: $100,000.00
Time: 126 WORKING DAYS
Engineer's Estimate: $10,815,461.94
Date: 05/06/2026 (5 weeks ago) Changed
Contract Number: 5263207
Type: HIGHWAY IMPROVEMENT
Project ID: A00014772
Contract Type: Federal
Project Description: WIDEN WITH CONTINUOUS LEFT TURN LANE AND SHOULDERS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$10,815,461.94
$10,910,071.81
Over/Under Est: 0.87% $94,609.87
Over/Under Est: 3.75% $406,018.81
Amt Left: 2.85% $311,408.94
$12,382,171.31
Over/Under Est: 14.49% $1,566,709.37
Amt Left: 13.49% $1,472,099.50
Delta: -10.34% -$1,160,690.56
$12,420,418.15
Over/Under Est: 14.84% $1,604,956.21
Amt Left: 13.84% $1,510,346.34
Delta: -0.31% -$38,246.84
Over/Under Est: 17.97% $1,943,670.82
Amt Left: 16.95% $1,849,060.95
Delta: -2.73% -$338,714.61
Over/Under Est: 18.89% $2,042,559.24
Amt Left: 17.85% $1,947,949.37
Delta: -0.78% -$98,888.42
Over/Under Est: 20.91% $2,261,507.57
Amt Left: 19.86% $2,166,897.70
Delta: -1.70% -$218,948.33
$14,697,351.35
Over/Under Est: 35.89% $3,881,889.41
Amt Left: 34.71% $3,787,279.54
Delta: -12.39% -$1,620,381.84

Bid Items & Bid Tabulations

108 Total 0 of 108
BURNET  |  SH 29  |  AUSTIN  |  0151-02-026  |  05/06/2026  |  $10,815,461.94  |  F 2026(606)  |  HWY IMPRV  |  126 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
JOE BLAND CONSTRUCTION LLC
HUNTER INDUSTRIES, LTD.
ALLEN KELLER COMPANY
AARON CONCRETE CONTRACTORS, LLC
CAPITAL EXCAVATION COMPANY
ACME BRIDGE COMPANY, INC.
ICOS MANAGEMENT, LLC
PREPARING ROW
STA 210.180 $1,500.000 $496.000 $775.000 $854.700 $2,273.830 $1,919.000 $850.000 $2,050.000 $346.500
REMOV CONC (RIPRAP)
SY 721.000 $15.000 $18.000 $25.000 $29.700 $14.320 $17.000 $20.000 $22.600 $15.400
REMOV CONC (DRIVEWAYS)
SY 1,235.800 $29.000 $15.690 $40.000 $34.100 $20.880 $25.000 $31.000 $20.500 $20.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 1,831.000 $7.000 $12.500 $6.000 $8.160 $1.480 $11.000 $20.000 $40.000 $22.000
RMV (10"-14") TRT/UNTRT BASE & ASPH PAV
SY 274.000 $12.000 $9.750 $14.000 $16.500 $6.100 $22.000 $52.700 $27.200 $22.000
RMV (19"-23") TRT/UNTRT BASE & ASPH PAV
SY 21,095.000 $10.500 $8.390 $16.000 $15.250 $10.280 $23.000 $10.500 $10.600 $12.000
RMV (10") TRT/UNTRT BASE & ASPH PAV
SY 573.000 $18.000 $5.550 $12.000 $9.070 $4.420 $15.000 $19.600 $13.600 $12.000
EXCAV (ROADWAY)
CY 19,011.000 $15.250 $12.200 $11.000 $20.900 $25.600 $28.000 $17.550 $12.100 $22.000
EMBANK (FNL)(OC)(TY B)
CY 11,383.000 $16.750 $5.050 $6.000 $20.900 $10.560 $17.000 $36.000 $15.200 $44.000
FURN & PLACE TOPSOIL (4")
SY 58,779.000 $1.250 $3.200 $1.500 $1.800 $2.780 $2.000 $2.500 $0.970 $11.000
DRILL SEED (PERM_RURAL_CLAY)
SY 58,779.000 $0.200 $0.220 $0.300 $0.240 $0.320 $0.260 $0.250 $0.330 $0.550
VEGETATIVE WATERING
TGL 2,941.000 $24.000 $35.000 $4.000 $26.400 $33.000 $55.000 $34.000 $50.000 $11.000
SOIL RET BLKT(SL_STEEP_CLAY_LONG)
SY 58,779.000 $1.500 $0.890 $1.450 $0.970 $1.240 $1.000 $0.970 $0.900 $2.200
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 20,123.000 $52.750 $45.500 $55.000 $63.460 $58.720 $53.000 $52.000 $86.200 $44.000
PRIME COAT (MULTI OPTION)
GAL 11,607.000 $3.850 $5.500 $3.750 $4.950 $5.160 $4.000 $3.800 $3.800 $6.640
D-GR HMA TY-B PG64-22
TON 21,819.000 $82.500 $93.000 $100.000 $100.100 $103.740 $100.000 $93.000 $93.600 $130.000
D-GR HMA TY-D PG76-22
TON 8,488.000 $102.500 $113.000 $124.000 $108.900 $110.180 $129.000 $117.000 $119.000 $178.000
D-GR HMA TY-D PG 76-22 (EXEMPT)
TON 849.000 $120.000 $113.000 $126.000 $117.700 $113.500 $127.000 $119.000 $119.000 $202.000
TOM-C PG76-22 SAC-B
TON 9,094.000 $120.000 $136.000 $145.000 $133.100 $119.630 $149.000 $137.000 $137.000 $172.240
FLOWABLE BACKFILL
CY 709.000 $215.000 $230.000 $255.000 $250.000 $173.740 $189.000 $221.000 $221.000 $275.000
TRENCH EXCAVATION PROTECTION
LF 24.000 $13.000 $100.000 $1,250.000 $128.000 $24.820 $5.000 $118.000 $172.000 $110.000
TEMPORARY SPL SHORING
SF 789.000 $40.000 $65.000 $50.000 $10.000 $19.860 $12.000 $22.700 $34.500 $27.500
RIPRAP (CONC)(5 IN)
CY 1,392.000 $435.000 $540.000 $395.000 $649.980 $471.570 $587.000 $675.000 $368.000 $682.000
RIPRAP (MOW STRIP)(4 IN)
CY 345.000 $585.000 $585.000 $495.000 $724.230 $699.910 $647.000 $1,050.000 $670.000 $660.000
RIRRAP (STONE COMMON)(DRY)(15 IN)
CY 25.000 $230.000 $300.000 $325.000 $235.000 $195.820 $205.000 $630.000 $276.000 $275.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 22.000 $700.000 $865.000 $750.000 $950.000 $729.690 $605.000 $590.000 $632.000 $472.500
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 29.000 $1,000.000 $920.000 $775.000 $750.000 $764.440 $635.000 $640.000 $747.000 $525.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 27.000 $1,000.000 $845.000 $825.000 $1,110.000 $828.970 $633.000 $630.000 $827.000 $577.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 20.000 $1,100.000 $1,330.000 $2,000.000 $1,700.000 $1,129.780 $1,076.000 $900.000 $1,260.000 $735.000
CONC BOX CULV (8 FT X 5 FT)(EXTEND)
LF 39.000 $1,400.000 $1,510.000 $2,200.000 $1,450.000 $898.460 $1,220.000 $1,060.000 $1,900.000 $945.000
RC PIPE (CL III)(18 IN)
LF 2,552.000 $72.500 $61.000 $115.000 $70.000 $106.230 $93.000 $78.900 $97.600 $115.000
RC PIPE (CL III)(24 IN)
LF 1,710.000 $100.000 $79.000 $135.000 $80.000 $122.110 $114.000 $107.000 $117.000 $115.000
RC PIPE (CL III)(30 IN)
LF 60.000 $150.000 $127.000 $165.000 $110.000 $109.210 $192.000 $148.000 $172.000 $189.000
RC PIPE (CL III)(36 IN)
LF 48.000 $250.000 $180.000 $220.000 $165.000 $178.700 $252.000 $191.000 $224.000 $252.000
RC PIPE (CL V)(24 IN)
LF 10.000 $225.000 $120.000 $240.000 $225.000 $129.060 $694.000 $450.000 $207.000 $294.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 1.000 $8,300.000 $6,000.000 $4,000.000 $5,500.000 $6,055.950 $5,182.000 $6,000.000 $14,400.000 $21,000.000
WINGWALL (PW - 1) (HW=3 FT)
EA 1.000 $12,000.000 $11,400.000 $8,000.000 $7,750.000 $9,530.670 $10,649.000 $6,900.000 $18,400.000 $18,000.000
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $18,000.000 $17,100.000 $9,500.000 $12,750.000 $11,044.670 $13,947.000 $11,400.000 $21,800.000 $19,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 3.000 $19,000.000 $17,700.000 $10,500.000 $14,600.000 $12,906.120 $12,642.000 $11,400.000 $25,300.000 $21,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 4.000 $22,500.000 $16,150.000 $17,500.000 $25,250.000 $13,159.280 $26,099.000 $20,800.000 $34,500.000 $23,000.000
WINGWALL (PW - 1) (HW=11 FT)
EA 1.000 $60,000.000 $154,000.000 $65,000.000 $160,000.000 $87,806.300 $141,143.000 $120,276.300 $68,900.000 $26,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 102.000 $1,700.000 $1,050.000 $2,250.000 $1,600.000 $1,742.330 $2,405.000 $2,700.000 $1,670.000 $1,575.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $2,200.000 $1,000.000 $2,500.000 $1,300.000 $2,591.160 $2,507.000 $2,470.000 $1,950.000 $1,680.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $2,600.000 $1,110.000 $2,500.000 $1,700.000 $3,588.900 $2,503.000 $3,030.000 $2,760.000 $1,785.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 55.000 $1,650.000 $1,390.000 $2,750.000 $2,200.000 $1,945.850 $2,810.000 $3,090.000 $1,900.000 $1,995.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $3,900.000 $2,320.000 $4,500.000 $2,650.000 $3,310.920 $3,254.000 $3,560.000 $3,040.000 $5,775.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $6,000.000 $4,100.000 $9,000.000 $5,800.000 $9,431.400 $6,277.000 $5,900.000 $8,610.000 $8,400.000
SET(TY II)(24 IN)(RCP)(4:1)(P)
EA 7.000 $2,000.000 $2,300.000 $2,500.000 $1,700.000 $2,164.260 $2,600.000 $3,030.000 $1,720.000 $2,625.000
SET(TY II)(24 IN)(RCP)(3:1)(P)
EA 2.000 $2,000.000 $2,100.000 $2,500.000 $1,550.000 $1,548.730 $2,555.000 $2,470.000 $1,490.000 $2,520.000
SET (TY II) (18") (RCP) (4:1) (P)
EA 2.000 $1,800.000 $2,000.000 $2,250.000 $1,750.000 $1,499.090 $2,242.000 $2,300.000 $1,490.000 $2,520.000
SET (TY II)(36 IN)(4:1)(P)
EA 1.000 $5,000.000 $5,200.000 $7,500.000 $5,200.000 $9,083.930 $5,959.000 $5,700.000 $8,040.000 $4,725.000
CLEAN EXIST CULVERTS
EA 8.000 $3,800.000 $3,100.000 $2,000.000 $3,000.000 $4,963.890 $3,410.000 $760.000 $3,450.000 $5,250.000
MOBILIZATION
LS 1.000 $791,200.000 $665,000.000 $225,000.000 $953,038.640 $1,180,000.000 $505,826.000 $603,000.000 $1,220,000.000 $687,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $9,000.000 $1,500.000 $7,250.000 $10,060.250 $13,437.990 $2,911.000 $7,500.000 $5,080.000 $13,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $6,400.000 $13,500.000 $3,811.290 $6,822.600 $11,709.000 $21,400.000 $8,300.000 $15,750.000
TMA (STATIONARY)
DAY 70.000 $250.000 $11.000 $200.000 $136.120 $291.800 $352.000 $330.000 $301.000 $315.000
TMA (MOBILE OPERATION)
DAY 75.000 $400.000 $600.000 $1,100.000 $272.240 $832.630 $59.000 $1,070.000 $689.000 $525.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 715.000 $45.000 $63.990 $50.000 $69.390 $41.700 $75.000 $69.450 $45.400 $31.500
ROCK FILTER DAMS (REMOVE)
LF 715.000 $16.000 $14.040 $25.000 $15.240 $9.930 $16.000 $15.250 $9.500 $10.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,957.000 $3.600 $4.670 $5.000 $5.060 $4.470 $5.000 $5.050 $6.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,957.000 $0.900 $0.920 $1.000 $1.000 $0.990 $1.000 $1.000 $1.150 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,620.000 $6.000 $7.800 $6.000 $8.460 $5.460 $9.000 $8.450 $6.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,620.000 $1.400 $0.920 $2.000 $1.000 $0.990 $1.000 $1.000 $1.150 $5.000
INTERSECTIONS (ACP)
SY 1,364.000 $55.000 $129.000 $90.000 $71.500 $103.220 $103.000 $120.000 $177.000 $71.500
DRIVEWAYS (CONC)
SY 1,237.000 $100.000 $152.000 $145.000 $116.520 $124.870 $141.000 $130.000 $108.000 $315.000
DRIVEWAYS (ACP)
SY 5,698.000 $57.500 $87.000 $55.000 $66.000 $53.430 $61.000 $95.000 $101.000 $56.990
TURNOUTS (ACP)
SY 291.000 $140.000 $174.000 $80.000 $52.800 $60.270 $57.000 $168.000 $109.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 6,250.000 $22.500 $25.500 $30.000 $25.200 $23.820 $34.000 $25.750 $27.000 $27.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,600.000 $1,600.000 $1,500.000 $1,364.960 $1,290.620 $2,198.000 $1,400.000 $1,690.000 $2,100.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,400.000 $1,450.000 $1,500.000 $1,417.460 $1,340.250 $1,810.000 $1,450.000 $1,530.000 $2,100.000
REMOVE METAL BEAM GUARD FENCE
LF 1,380.000 $3.100 $3.000 $3.000 $2.620 $2.480 $3.000 $2.700 $3.150 $4.500
GUARDRAIL END TREATMENT (INSTALL)
EA 29.000 $3,000.000 $3,060.000 $4,250.000 $3,307.400 $3,127.250 $3,880.000 $3,380.000 $3,240.000 $3,400.000
GUARDRAIL END TREATMENT (REMOVE)
EA 7.000 $280.000 $275.000 $200.000 $262.490 $248.190 $259.000 $270.000 $291.000 $450.000
WIRE FENCE (TY C)
LF 150.000 $45.000 $55.600 $16.000 $21.000 $24.820 $29.000 $33.150 $26.400 $22.000
WIRE FENCE (REMOVE)
LF 150.000 $3.000 $21.200 $8.000 $5.250 $1.990 $4.000 $12.650 $5.300 $12.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 29.000 $380.000 $250.000 $275.000 $453.590 $248.190 $293.000 $270.000 $264.000 $275.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000 $380.000 $275.000 $305.000 $510.280 $273.010 $322.000 $300.000 $291.000 $302.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 6.000 $800.000 $550.000 $615.000 $881.970 $546.030 $644.000 $600.000 $582.000 $605.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 32.000 $750.000 $650.000 $725.000 $734.980 $645.300 $761.000 $710.000 $687.000 $715.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $800.000 $750.000 $825.000 $906.120 $744.580 $878.000 $810.000 $793.000 $825.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 1.000 $1,600.000 $950.000 $1,050.000 $1,326.110 $943.150 $1,112.000 $1,030.000 $1,000.000 $1,045.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 5.000 $500.000 $400.000 $450.000 $625.780 $397.110 $468.000 $430.000 $423.000 $440.000
REMOVE SM RD SN SUP&AM
EA 37.000 $110.000 $85.000 $95.000 $134.400 $84.390 $100.000 $159.000 $89.900 $93.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 91.000 $45.000 $55.000 $30.000 $48.300 $22.830 $59.000 $27.100 $26.400 $27.500
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 11.000 $110.000 $90.000 $135.000 $85.050 $124.100 $146.000 $136.000 $132.000 $137.500
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 44,686.000 $0.250 $0.210 $0.250 $0.230 $0.210 $0.250 $0.200 $0.220 $0.220
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 10,730.000 $0.270 $0.210 $0.250 $0.230 $0.210 $0.250 $0.200 $0.220 $0.220
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 44,116.000 $0.290 $0.210 $0.250 $0.230 $0.210 $0.250 $0.200 $0.220 $0.220
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 87.000 $3.000 $7.350 $8.000 $8.020 $7.290 $9.000 $5.250 $7.800 $22.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 17,874.000 $1.000 $0.950 $1.250 $1.720 $3.610 $2.000 $8.950 $2.050 $1.100
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 28,376.000 $1.000 $0.950 $1.250 $1.720 $3.640 $2.000 $8.950 $2.050 $1.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 530.000 $1.050 $1.050 $1.250 $1.150 $1.040 $1.000 $1.100 $1.100 $1.100
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 164.000 $8.500 $11.000 $12.250 $12.000 $10.920 $13.000 $7.050 $11.600 $7.940
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 13.000 $180.000 $200.000 $225.000 $218.180 $198.560 $234.000 $217.000 $211.000 $220.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 3.000 $240.000 $250.000 $275.000 $272.720 $248.190 $293.000 $217.000 $264.000 $220.000
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 41,206.000 $0.700 $0.810 $1.000 $0.880 $0.810 $1.000 $0.900 $0.860 $1.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 9,802.000 $0.700 $0.550 $0.750 $0.600 $0.550 $1.000 $0.650 $0.580 $0.670
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 9,681.000 $0.600 $0.550 $0.750 $0.600 $0.550 $1.000 $0.650 $0.580 $0.670
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 40,878.000 $0.600 $0.550 $0.750 $0.600 $0.550 $1.000 $0.650 $0.580 $0.670
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 41,108.000 $4.000 $0.810 $1.000 $0.880 $0.810 $1.000 $3.800 $0.860 $3.850
REFL PAV MRKR TY I-C
EA 150.000 $4.000 $7.000 $8.000 $7.640 $6.950 $8.000 $3.800 $7.400 $6.050
REFL PAV MRKR TY II-A-A
EA 1,066.000 $4.000 $7.000 $8.000 $7.640 $6.950 $8.000 $3.800 $7.400 $6.050
ELIM EXT PM & MRKS (4")
LF 101,490.000 $0.350 $0.100 $0.150 $0.110 $0.100 $0.120 $0.430 $0.110 $0.440
ELIM EXT PM & MRKS (8")
LF 120.000 $1.000 $1.000 $1.250 $1.090 $0.990 $1.000 $0.550 $1.050 $0.550
ELIM EXT PM & MRKS (ARROW)
EA 1.000 $70.000 $175.000 $195.000 $190.910 $173.740 $205.000 $108.000 $185.000 $150.000
ELIM EXT PM & MRKS (WORD)
EA 1.000 $90.000 $175.000 $195.000 $190.910 $173.740 $205.000 $108.000 $185.000 $150.000
BONDING COURSE
GAL 29,227.000 $3.250 $4.750 $4.000 $3.520 $4.380 $4.000 $3.800 $3.800 $6.000
SUBSURFACE UTIL LOCATE (NON-PAVED AREA)
EA 50.000 $1,000.000 $315.000 $1,750.000 $2,500.000 $493.950 $1,983.000 $610.000 $1,060.000 $2,500.000
Totals: $10,815,461.940 $10,910,071.812 $11,221,480.750 $12,382,171.306 $12,420,418.153 $12,759,132.760 $12,858,021.180 $13,076,969.510 $14,697,351.350
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $7,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $120,689.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $35,000.00
Total: $162,689.00