BRAZOS US 190 (0049-09-096)

Items: 68

County: BRAZOS
Length: N/A
Highway: US 190
District: BRYAN
Control Number: 0049-09-096
DBE Goal: N/A
Project: BR 2023(632)
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $1,789,643.00
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,789,643.00
Over/Under Est: 5.53% $98,912.00
Over/Under Est: 17.19% $307,634.93
Amt Left: 11.05% $208,722.93
Over/Under Est: 20.17% $360,996.60
Amt Left: 13.88% $262,084.60
Delta: -2.54% -$53,361.67
Over/Under Est: 31.44% $562,580.50
Amt Left: 24.55% $463,668.50
Delta: -9.37% -$201,583.90
Subcontractor Percentage Amount
S & S BRIDGE PAINTING, INC. 18.09% $345,031.67
MACIAS SPECIALTY CONTRACTING LLC 10.66% $203,318.83
DIIBS SPECIALISTS, LLC 7.03% $134,083.62
CHEROKEE SERVICES 3.15% $60,080.14
SAPO ENGINEERING CONSULTANTS, LLC 2.70% $51,497.26
HIGHWAY 1 LLC 2.17% $41,388.54
STRUCTURAL INTEGRITY GROUP LLC 1.48% $28,228.13
BROCK CONSTRUCTION, LLC 1.01% $19,263.79
LONESTAR TRAFFIC SAFETY, LLC 0.74% $14,114.07
CEN TEX HYDROSEED, INC. 0.13% $2,479.50
AWP SAFETY 0.11% $2,098.04
Total: 47.27% $901,583.59

Bid Items & Bid Tabulations

68 Total 0 of 68
BRAZOS  |  US 190  |  BRYAN  |  0049-09-096  |  05/05/2023  |  $1,789,643.00  |  BR 2023(632)  |  BRIDGE MAINT  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
RAGLE CONSTRUCTION, INC.
SCR CIVIL CONSTRUCTION, LLC
CROSS PLUS CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 49.000 $100.000 $50.000 $150.000 $200.000 $275.000
REMOVING CONC (RETAINING WALLS)
SY 12.000 $100.000 $90.000 $1,000.000 $540.000 $550.000
EXCAVATION (ROADWAY)
CY 9.000 $30.000 $450.000 $290.000 $210.000 $550.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 158.000 $60.000 $100.000 $120.000 $110.000 $55.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 200.000 $60.000 $30.000 $120.000 $110.000 $55.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 5,573.000 $1.000 $1.000 $1.000 $0.350 $5.500
FERTILIZER
TON 0.350 $1,500.000 $1,000.000 $3,000.000 $1,355.000 $2,200.000
VEGETATIVE WATERING
MG 112.000 $40.000 $100.000 $59.000 $100.000 $110.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(24")
SY 40.000 $200.000 $200.000 $322.000 $1,020.000 $165.000
FLOWABLE BACKFILL
CY 96.000 $400.000 $250.000 $273.000 $610.000 $330.000
TEMPORARY SPL SHORING
SF 170.000 $50.000 $100.000 $169.000 $470.000 $220.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 319.000 $50.000 $30.000 $45.000 $50.000 $44.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 963.000 $325.000 $229.000 $350.000 $260.000 $154.000
RIPRAP (CONC)(5 IN)
CY 4.000 $850.000 $800.000 $1,405.000 $1,630.000 $192.500
RIPRAP (STONE PROTECTION)(18 IN)
CY 512.000 $200.000 $220.000 $235.000 $295.000 $192.500
RIPRAP (MOW STRIP)(4 IN)
CY 111.000 $850.000 $550.000 $710.000 $1,200.000 $550.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 826.000 $50.000 $55.000 $31.000 $50.000 $82.500
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 568.000 $45.000 $44.000 $48.000 $46.000 $82.500
MULTI-LAYER POLYMER OVERLAY
SY 234.000 $75.000 $50.000 $200.000 $107.000 $550.000
CLEAN & PAINT EXIST STR (SYSTEM I-A)
LS 1.000 $300,000.000 $347,908.000 $280,000.000 $338,000.000 $440,000.000
RETROFIT RAIL (TY T131RC)
LF 217.000 $250.000 $267.000 $275.000 $325.000 $275.000
GABIONS (GALV)
CY 213.000 $400.000 $200.000 $335.000 $310.000 $330.000
SHOT BLASTING
SY 234.000 $7.000 $10.000 $15.000 $70.000 $38.500
MOBILIZATION
LS 1.000 $165,000.000 $200,000.000 $210,000.000 $214,000.000 $220,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $10,000.000 $2,343.000 $21,250.000 $5,800.000 $5,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 672.000 $30.000 $35.000 $40.000 $50.000 $82.500
CONSTRUCTION EXITS (REMOVE)
SY 672.000 $8.000 $10.000 $20.000 $22.000 $27.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,708.000 $5.000 $5.000 $4.000 $7.000 $16.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,708.000 $1.000 $2.000 $1.000 $1.150 $5.500
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 1.000 $5,000.000 $6,000.000 $2,500.000 $10,000.000 $5,500.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 510.000 $70.000 $90.000 $175.000 $90.000 $165.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 510.000 $10.000 $15.000 $10.000 $18.000 $55.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 510.000 $18.000 $20.000 $25.000 $90.000 $55.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,225.000 $30.000 $38.000 $23.750 $27.000 $38.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $2,500.000 $3,076.000 $1,840.000 $2,350.000 $2,420.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,800.000 $6,383.000 $1,245.000 $1,500.000 $1,320.000
REMOVE METAL BEAM GUARD FENCE
LF 650.000 $7.000 $16.000 $3.000 $3.000 $5.500
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $3,500.000 $4,702.000 $2,945.000 $3,400.000 $4,400.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $300.000 $4,579.000 $335.000 $290.000 $275.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,500.000 $8,528.000 $1,395.000 $3,500.000 $5,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,400.000 $7,313.000 $670.000 $3,000.000 $550.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $40,847.000 $8,090.000 $9,000.000 $38,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 3.000 $40.000 $2,885.000 $20.000 $25.000 $11.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $35.000 $2,173.000 $21.000 $30.000 $11.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 3.000 $35.000 $2,885.000 $20.000 $25.000 $11.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 3.000 $45.000 $2,893.000 $30.000 $26.000 $11.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 30.000 $45.000 $328.000 $32.000 $30.000 $11.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 3.000 $50.000 $2,890.000 $32.000 $30.000 $11.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 576.000 $5.000 $18.000 $3.000 $7.000 $5.500
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 4,951.000 $3.000 $4.000 $1.550 $2.300 $5.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $15.000 $371.000 $12.500 $11.500 $5.500
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 11,506.000 $1.500 $3.000 $1.550 $2.100 $5.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 508.000 $2.000 $5.000 $0.920 $4.000 $5.500
REFL PAV MRKR TY II-A-A
EA 134.000 $7.000 $76.000 $10.000 $11.500 $11.000
POTHOLE REPAIR (STANDARD)
SY 1.000 $100.000 $1,200.000 $675.000 $550.000 $1,100.000
JT / CRCK ROUT / SEAL(RUBBER - ASPHALT)
LF 110.000 $15.000 $36.000 $30.000 $20.000 $110.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
CYC 1.000 $4,000.000 $2,500.000 $2,050.000 $3,000.000 $11,000.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.500 $10,000.000 $48,600.000 $79,250.000 $55,000.000 $27,500.000
REPAIR RAIL ELEMENT (W - BEAM) (LABOR)
LF 10.000 $15.000 $200.000 $120.000 $70.000 $44.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 7.000 $100.000 $148.000 $115.000 $100.000 $82.500
BRIDGE JOINT REPAIR (HEADER)
LF 4.000 $300.000 $948.000 $755.000 $1,300.000 $5.500
CARBON FIBER REINF POLYMER PROTECTION
SF 79.000 $175.000 $156.000 $128.000 $70.000 $275.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 70.000 $120.000 $100.000 $82.000 $118.000 $165.000
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 2,633.000 $2.000 $3.000 $3.330 $2.300 $5.500
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 5,155.000 $2.000 $3.000 $3.330 $2.300 $5.500
MULTIPOLYMER PAV MRK (Y)(4")(BRK)
LF 1,371.000 $1.000 $3.000 $3.330 $2.300 $5.500
TMA (STATIONARY)
DAY 170.000 $300.000 $50.000 $340.000 $300.000 $275.000
TMA (MOBILE OPERATION)
DAY 4.000 $350.000 $250.000 $855.000 $1,000.000 $1,100.000
Totals: $1,789,643.000 $1,888,555.000 $2,097,277.930 $2,150,639.600 $2,352,223.500