BOWIE VARIOUS (0919-19-088)

Items: 65

County: BOWIE
Length: 0.0000 MILES
Highway: VARIOUS
District: ATLANTA
Control Number: 0919-19-088
DBE Goal: 0.0%
Project: STP 2022(680)TAPS
Guaranty: $37,000.00
Time: 137 WORKING DAYS
Engineer's Estimate: $1,848,087.75
Date: 11/07/2024 (1 year ago)
Contract Number: 11243219
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Project ID: A00186167
Project Description: CONSTRUCT 5 FT CONCRETE SIDEWALK ALONG KENNEDY LANE FROM SH 93 TO ROBISON ROAD AND ALONG ROBISON ROAD TO FM 559. ALSO CONSTRUCT 10 FT ASPHALT SHARED USE PATH EXTENDING ALONG COWHORN CREEK TRAIL FROM KENNEDY LANE TO FM 559.
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$1,848,087.75
$1,777,958.06
Over/Under Est: -3.79% -$70,129.69
$1,879,754.72
Over/Under Est: 1.71% $31,666.97
Amt Left: 5.73% $101,796.66
Over/Under Est: 1.91% $35,271.25
Amt Left: 5.93% $105,400.94
Delta: -0.19% -$3,604.28
Over/Under Est: 7.32% $135,363.75
Amt Left: 11.56% $205,493.44
Delta: -5.31% -$100,092.50
$2,073,095.00
Over/Under Est: 12.18% $225,007.25
Amt Left: 16.6% $295,136.94
Delta: -4.52% -$89,643.50
Over/Under Est: 17.84% $329,650.75
Amt Left: 22.49% $399,780.44
Delta: -5.05% -$104,643.50
$2,647,837.56
Over/Under Est: 43.27% $799,749.81
Amt Left: 48.93% $869,879.50
Delta: -21.59% -$470,099.06
$2,950,254.00
Over/Under Est: 59.64% $1,102,166.25
Amt Left: 65.93% $1,172,295.94
Delta: -11.42% -$302,416.44
Subcontractor Percentage Amount
STRIPING TECHNOLOGY, L.P. 18.75% $327,779.64
J. H. ODEN CONTRACTING COMPANY 1.88% $32,865.37
SOUTHWEST ENVIRONMENT SERVICES LLC 1.01% $17,656.40
DIAMOND ELITE BARRICADES, LLC 0.89% $15,558.61
CARTHAGE DRILLING, LLC 0.87% $15,208.98
Total: 23.40% $409,069.00

Bid Items & Bid Tabulations

65 Total 0 of 65
BOWIE  |  VARIOUS  |  ATLANTA  |  0919-19-088  |  11/07/2024  |  $1,848,087.75  |  STP 2022(680)TAPS  |  BICYCLE AND PEDESTRIAN IMPRVS  |  137 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
TI-ZACK CONCRETE, LLC
TATUM EXCAVATING COMPANY, INC.
GARRET SHIELDS INFRASTRUCTURE
FNH CONSTRUCTION, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
C. E. BARKER, LTD.
SKYLINE BRIDGE LLC
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 15.000 $500.000 $1,500.000 $2,750.000 $1,200.000 $1,000.000 $5,000.000 $10,000.000 $17,500.000 $5,000.000
REMOV CONC (DRIVEWAYS)
SY 1,990.000 $20.000 $25.000 $24.060 $30.000 $20.000 $30.000 $50.000 $24.280 $25.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 54.000 $50.000 $25.000 $29.560 $40.000 $20.000 $30.000 $35.000 $32.000 $50.000
REMOV CONC (CURB)
LF 2,322.000 $20.000 $10.000 $10.310 $30.000 $10.000 $20.000 $10.000 $23.450 $18.000
REMOV CONC (CURB & GUTTER)
LF 251.000 $25.000 $10.000 $15.900 $60.000 $10.000 $30.000 $15.000 $35.860 $50.000
REMOV CONC (MISC)
EA 1.000 $1,000.000 $2,000.000 $7,980.000 $1,000.000 $1,000.000 $500.000 $1,000.000 $4,965.410 $12,000.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 90.000 $10.000 $10.000 $44.330 $25.000 $50.000 $100.000 $40.000 $20.970 $250.000
EXCAV (ROADWAY)
CY 1,990.000 $20.000 $20.000 $48.120 $35.000 $40.000 $30.000 $30.000 $19.860 $35.000
EMBANK (FNL)(DC)(TY C)
CY 309.000 $45.000 $20.000 $52.080 $35.000 $40.000 $50.000 $50.000 $26.840 $100.000
BLOCK SODDING
SY 1,778.000 $10.000 $8.100 $5.450 $8.000 $10.000 $10.000 $8.500 $9.830 $10.000
HYDRO MULCH SEED (OPT1)
SY 1,229.000 $2.000 $1.620 $1.030 $2.000 $1.500 $20.000 $2.000 $1.100 $15.000
VEGETATIVE WATERING
TGL 17.000 $110.000 $20.000 $1.100 $110.000 $100.000 $50.000 $35.000 $24.550 $1.000
FL BS (CMP IN PLC)(TY D GR 3) (4")
SY 163.000 $20.000 $50.000 $9.790 $30.000 $30.000 $30.000 $35.000 $62.460 $250.000
CEMENT
TON 66.000 $300.000 $300.000 $330.000 $285.000 $260.000 $350.000 $320.000 $319.990 $500.000
CEMENT TRT (SUBGRADE)(12")
SY 1,828.000 $5.000 $5.750 $13.200 $14.000 $30.000 $20.000 $7.000 $8.280 $35.000
D-GR HMA TY-C PG64-22
TON 346.000 $230.000 $300.000 $330.000 $188.000 $200.000 $300.000 $250.000 $263.720 $500.000
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 22.000 $725.000 $1,620.000 $1,650.000 $1,100.000 $1,500.000 $1,650.000 $1,700.000 $827.570 $2,500.000
RIPRAP (CONC) (CL B) (6 IN)
CY 4.000 $550.000 $1,000.000 $831.290 $1,100.000 $1,000.000 $650.000 $1,000.000 $951.700 $4,000.000
RAIL (HANDRAIL)(TY E)
LF 238.000 $200.000 $163.690 $170.500 $188.000 $150.000 $200.000 $165.000 $170.690 $350.000
RC PIPE (CL III)(24 IN)
LF 24.000 $200.000 $100.000 $220.000 $150.000 $150.000 $150.000 $180.000 $131.970 $500.000
HEADWALL (CH - FW - 0) (DIA= 24 IN)
EA 2.000 $4,000.000 $8,000.000 $22,000.000 $9,325.000 $1,000.000 $3,500.000 $3,100.000 $6,344.690 $50,000.000
CAST-IN-PLACE TRENCH DRAIN
LF 35.000 $150.000 $150.000 $1,050.170 $340.000 $100.000 $1,000.000 $250.000 $733.780 $500.000
MOBILIZATION
LS 1.000 $150,000.000 $175,000.000 $161,519.490 $187,990.000 $150,000.000 $200,000.000 $215,000.000 $240,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $10,000.000 $6,613.920 $1,650.000 $8,300.000 $5,000.000 $8,500.000 $5,000.000 $14,305.910 $5,000.000
TMA (STATIONARY)
DAY 137.000 $250.000 $250.000 $1.100 $235.000 $300.000 $250.000 $200.000 $275.860 $500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,333.000 $5.500 $4.320 $0.110 $4.500 $6.000 $4.000 $5.000 $6.340 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,333.000 $2.000 $1.080 $0.110 $1.000 $1.000 $2.000 $1.500 $2.480 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 137.000 $9.500 $6.480 $1.100 $6.500 $10.000 $18.000 $7.000 $7.500 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 137.000 $3.250 $1.080 $1.100 $1.000 $1.000 $9.000 $1.500 $3.310 $8.000
CONC CURB (TY II)
LF 1,718.000 $50.000 $40.000 $51.670 $20.000 $40.000 $45.000 $15.000 $61.200 $125.000
CONC CURB & GUTTER (TY II)
LF 113.000 $65.000 $50.000 $51.670 $60.000 $40.000 $65.000 $45.000 $83.470 $200.000
DRIVEWAYS (CONC)
SY 2,759.000 $120.000 $95.000 $121.730 $105.000 $130.000 $95.000 $140.000 $179.470 $125.000
CONC SIDEWALKS (4")
SY 2,948.000 $120.000 $85.000 $95.550 $115.000 $130.000 $65.000 $120.000 $162.710 $150.000
CURB RAMPS (TY 1)
EA 2.000 $2,900.000 $3,500.000 $2,519.050 $1,500.000 $3,000.000 $3,250.000 $3,000.000 $5,241.270 $3,000.000
CURB RAMPS (TY 2)
EA 3.000 $3,000.000 $3,500.000 $2,519.050 $1,700.000 $3,000.000 $3,250.000 $3,000.000 $5,572.300 $2,800.000
CURB RAMPS (TY 7)
EA 3.000 $3,000.000 $3,500.000 $2,519.050 $1,750.000 $3,000.000 $3,250.000 $3,000.000 $5,737.810 $5,000.000
CURB RAMPS (TY 10)
EA 22.000 $2,800.000 $3,500.000 $2,519.050 $1,400.000 $3,000.000 $3,250.000 $3,000.000 $3,937.020 $3,000.000
RELOCATE EXISTING MAILBOX
EA 8.000 $610.000 $250.000 $495.000 $245.000 $500.000 $2,500.000 $350.000 $165.510 $500.000
CONDT (PVC) (SCH 40) (3")
LF 185.000 $30.000 $260.370 $176.000 $175.000 $200.000 $30.000 $176.000 $22.070 $200.000
CONDT (PVC) (SCH 40) (3") (BORE)
LF 75.000 $40.000 $221.400 $225.500 $225.000 $210.000 $150.000 $226.000 $38.620 $250.000
ELEC CONDR (NO.8) INSULATED
LF 340.000 $2.250 $4.050 $4.130 $4.000 $4.000 $6.000 $5.000 $3.310 $15.000
GROUND BOX TY D (162922)W/APRON
EA 3.000 $1,600.000 $6,480.000 $1,100.000 $6,600.000 $7,000.000 $2,000.000 $6,600.000 $1,986.170 $8,000.000
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
EA 1.000 $7,200.000 $15,336.000 $15,620.000 $15,600.000 $15,000.000 $11,000.000 $16,000.000 $6,620.550 $20,000.000
ALUMINUM SIGNS (TY A)
SF 46.000 $50.000 $50.000 $110.000 $25.000 $40.000 $50.000 $50.000 $25.930 $800.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 10.000 $600.000 $549.720 $165.000 $650.000 $1,000.000 $1,500.000 $750.000 $656.540 $1,500.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 32.000 $600.000 $417.960 $495.000 $530.000 $500.000 $1,100.000 $700.000 $535.160 $500.000
REMOVE SM RD SN SUP&AM
EA 1.000 $170.000 $142.560 $165.000 $135.000 $500.000 $250.000 $150.000 $137.930 $500.000
RE PM TY II (R) 12" (FIRE LANE)
LF 436.000 $10.000 $21.600 $9.350 $1.250 $25.000 $20.000 $22.000 $18.120 $25.000
PREFAB PM TY C (W)(24")(SLD)
LF 1,214.000 $20.000 $27.000 $18.150 $16.000 $25.000 $20.000 $28.000 $39.610 $30.000
ELIM EXT PM & MRKS (4")
LF 20.000 $1.250 $10.800 $3.300 $5.500 $10.000 $3.000 $11.000 $32.000 $15.000
ELIM EXT PM & MRKS (24")
LF 190.000 $5.500 $10.800 $4.950 $2.200 $10.000 $20.000 $11.000 $25.820 $15.000
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $42,000.000 $20,520.000 $20,900.000 $20,900.000 $20,000.000 $35,000.000 $21,000.000 $6,620.550 $30,000.000
INSTALL HWY TRF SIG (UPGRADE)
EA 2.000 $17,000.000 $6,480.000 $6,600.000 $6,600.000 $7,000.000 $35,000.000 $6,600.000 $6,620.550 $10,000.000
VEH SIG SEC (12")LED(YEL)
EA 4.000 $330.000 $657.720 $669.900 $670.000 $700.000 $350.000 $670.000 $651.020 $1,000.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $330.000 $675.000 $687.500 $685.000 $700.000 $350.000 $690.000 $651.020 $1,000.000
PED SIG SEC (LED)(COUNTDOWN)
EA 8.000 $1,000.000 $648.000 $660.000 $660.000 $1,000.000 $5,500.000 $660.000 $937.910 $1,000.000
TRF SIG CBL (TY A)(12 AWG)(3 CONDR)
LF 649.000 $2.250 $4.860 $4.950 $5.000 $5.000 $3.000 $5.000 $2.760 $8.000
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 937.000 $3.250 $5.400 $5.500 $6.000 $5.000 $3.000 $5.500 $3.860 $8.000
TRF SIG CBL (TY A)(12 AWG)(20 CONDR)
LF 115.000 $14.000 $28.890 $29.430 $29.000 $30.000 $4.000 $30.000 $9.930 $35.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 2.000 $14,000.000 $13,284.000 $13,530.000 $13,530.000 $13,000.000 $12,500.000 $14,000.000 $9,919.790 $18,000.000
INS TRF SIG PL AM(S)1 ARM(50')
EA 1.000 $36,000.000 $52,342.200 $53,311.500 $53,300.000 $50,000.000 $60,000.000 $54,000.000 $30,895.900 $65,000.000
PED POLE ASSEMBLY
EA 7.000 $3,300.000 $2,000.160 $2,037.200 $2,000.000 $2,000.000 $4,500.000 $2,050.000 $2,758.560 $3,000.000
PED DETECT PUSH BUTTON (APS)
EA 8.000 $1,200.000 $2,106.000 $2,145.000 $2,145.000 $2,000.000 $1,850.000 $2,200.000 $1,048.250 $3,000.000
PED DETECTOR CONTROLLER UNIT
EA 3.000 $4,000.000 $11,448.000 $11,660.000 $11,660.000 $11,000.000 $6,500.000 $11,750.000 $3,972.330 $15,000.000
SPOT TREE TRIMMING / BRUSH REMOVAL
LF 125.000 $10.000 $35.000 $1.100 $83.000 $100.000 $100.000 $140.000 $231.720 $250.000
Totals: $1,848,087.750 $1,777,958.060 $1,879,754.720 $1,883,359.000 $1,983,451.500 $2,073,095.000 $2,177,738.500 $2,647,837.560 $2,950,254.000