BOWIE SH 98 (0330-01-033)

Items: 79

County: BOWIE
Length: N/A
Highway: SH 98
District: ATLANTA
Control Number: 0330-01-033
DBE Goal: N/A
Project: BR 2019(848)
Guaranty: N/A
Time: 287 WORKING DAYS
Engineer's Estimate: $4,498,344.10
Date: 06/05/2020 (6 years ago)
Contract Number: N/A
Type: REPLACE BRIDGES AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$4,498,344.10
$3,919,948.80
Over/Under Est: -12.86% -$578,395.30
Over/Under Est: -9.63% -$433,220.63
Amt Left: 3.7% $145,174.67
Over/Under Est: -2.37% -$106,803.00
Amt Left: 12.03% $471,592.30
Delta: -8.03% -$326,417.63
Over/Under Est: -0.01% -$381.10
Amt Left: 14.75% $578,014.20
Delta: -2.42% -$106,421.90
$4,854,854.85
Over/Under Est: 7.93% $356,510.75
Amt Left: 23.85% $934,906.05
Delta: -7.93% -$356,891.85
$5,194,759.85
Over/Under Est: 15.48% $696,415.75
Amt Left: 32.52% $1,274,811.05
Delta: -7.00% -$339,905.00

Bid Items & Bid Tabulations

79 Total 0 of 79
BOWIE  |  SH 98  |  ATLANTA  |  0330-01-033  |  06/05/2020  |  $4,498,344.10  |  BR 2019(848)  |  REPLACE BRIDGES AND APPROACHES  |  287 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
R & G CONSTRUCTION, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PIERCE R & B LLC
CDM HOLDINGS, LLC
PREPARING ROW
STA 25.400 $2,500.000 $2,000.000 $1,552.340 $1,200.000 $3,800.000 $1,400.000 $1,250.000
REMOVING CONC (RIPRAP)
SY 1,389.000 $9.000 $10.000 $25.220 $9.500 $10.000 $15.000 $18.500
REMOVING CONC (APPR SLAB)
SY 241.000 $28.000 $5.000 $25.000 $14.000 $100.000 $20.000 $80.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 159.000 $10.000 $10.000 $3.000 $8.000 $12.000 $20.000 $15.000
REMOVING STAB BASE AND ASPH PAV(8")
SY 2,569.000 $13.000 $6.000 $9.560 $4.750 $8.000 $11.000 $8.000
EXCAVATION (ROADWAY)
CY 365.000 $7.000 $9.000 $4.000 $12.000 $10.000 $12.000 $23.000
EXCAVATION (CHANNEL)
CY 985.000 $11.000 $9.000 $20.000 $14.000 $15.000 $12.000 $23.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 487.000 $25.000 $9.000 $15.000 $16.000 $30.000 $12.000 $21.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 15,549.000 $9.000 $9.000 $11.790 $10.500 $10.000 $12.000 $29.000
FURNISHING AND PLACING TOPSOIL (4")
SY 28,700.000 $2.500 $1.000 $1.900 $1.750 $1.000 $2.500 $3.100
BROADCAST SEED (TEMP) (WARM)
SY 14,350.000 $0.150 $0.150 $0.170 $0.110 $0.500 $0.300 $0.320
BROADCAST SEED (TEMP) (COOL)
SY 14,350.000 $0.150 $0.110 $0.120 $0.110 $0.500 $0.300 $0.320
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 28,700.000 $0.800 $0.770 $0.770 $1.050 $0.800 $1.000 $0.900
VEGETATIVE WATERING
MG 460.000 $11.000 $7.000 $7.000 $1.000 $1.000 $15.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 2,513.000 $2.000 $2.000 $1.700 $2.250 $2.500 $2.000 $1.700
CEMENT
TON 112.000 $160.000 $155.000 $165.000 $195.000 $170.000 $200.000 $160.000
CEMENT TREAT (SUBGRADE) (8")
SY 8,146.000 $4.500 $3.000 $5.500 $2.750 $5.000 $7.500 $4.750
PRIME COAT (MC-30)
GAL 2,523.000 $5.000 $5.000 $6.000 $4.750 $8.000 $8.250 $8.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 322.000 $4.500 $6.000 $10.000 $6.250 $8.000 $15.000 $10.000
PLANE ASPH CONC PAV (2")
SY 12,827.000 $1.500 $2.250 $1.550 $3.250 $2.000 $7.000 $1.250
CEM STABIL BKFL
CY 331.000 $191.000 $150.000 $162.000 $230.000 $150.000 $200.000 $235.000
TEMPORARY SPL SHORING
SF 285.000 $32.000 $50.000 $43.000 $70.000 $50.000 $40.000 $38.000
DRILL SHAFT (18 IN)
LF 204.000 $120.000 $75.000 $85.000 $140.000 $100.000 $90.000 $72.000
DRILL SHAFT (36 IN)
LF 1,044.000 $192.000 $215.000 $240.000 $235.000 $170.000 $235.000 $210.000
CL C CONC (ABUT)(HPC)
CY 130.000 $1,300.000 $950.000 $965.000 $1,050.000 $1,000.000 $1,100.000 $1,000.000
CL C CONC (CAP)(HPC)
CY 79.400 $1,300.000 $950.000 $965.000 $1,050.000 $1,000.000 $1,200.000 $1,000.000
CL C CONC (COLUMN)(HPC)
CY 56.600 $1,200.000 $950.000 $1,120.000 $975.000 $1,000.000 $1,200.000 $875.000
REINF CONC SLAB (HPC)
SF 18,860.000 $23.000 $19.000 $21.400 $20.000 $22.000 $22.000 $24.000
APPROACH SLAB (HPC)
CY 221.300 $718.000 $550.000 $625.000 $540.000 $800.000 $550.000 $545.000
RETAINING WALL (TEMP WALL)
SF 4,007.000 $25.000 $26.000 $16.000 $22.000 $10.000 $34.000 $23.000
PRESTR CONC GIRDER (TX28)
LF 891.000 $151.000 $160.000 $195.000 $140.000 $180.000 $160.000 $275.000
PRESTR CONC GIRDER (TX46)
LF 1,551.000 $155.000 $160.000 $165.000 $165.000 $190.000 $185.000 $275.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 2,438.000 $128.000 $115.000 $110.000 $142.000 $120.000 $120.000 $123.000
RIPRAP (CONC)(FLUME)
CY 11.000 $500.000 $650.000 $800.000 $500.000 $600.000 $550.000 $1,260.000
RIPRAP (MOW STRIP)(4 IN)
CY 37.000 $450.000 $475.000 $440.000 $515.000 $500.000 $525.000 $550.000
RAIL (TY SSTR)(HPC)
LF 948.000 $79.000 $90.000 $113.000 $74.000 $100.000 $110.000 $85.000
ARMOR JOINT
LF 176.000 $51.000 $35.000 $70.000 $45.000 $75.000 $90.000 $55.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 181.300 $120.000 $95.000 $95.000 $70.000 $85.000 $95.000 $120.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 2.000 $80,000.000 $40,000.000 $60,000.000 $60,000.000 $55,000.000 $30,000.000 $60,000.000
MOBILIZATION
LS 1.000 $417,000.000 $350,000.000 $325,000.000 $340,000.000 $400,000.000 $480,000.000 $410,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $8,100.000 $2,500.000 $1,650.000 $4,000.000 $7,700.000 $3,000.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 328.000 $53.000 $70.000 $83.500 $51.000 $5.000 $68.000 $118.000
ROCK FILTER DAMS (REMOVE)
LF 328.000 $15.000 $14.000 $16.000 $13.000 $1.000 $16.000 $29.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,115.000 $3.000 $3.000 $3.000 $2.900 $1.000 $3.000 $2.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,115.000 $1.250 $1.200 $0.900 $1.000 $1.000 $1.400 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 240.000 $4.500 $13.000 $7.250 $6.600 $8.000 $10.000 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 240.000 $4.000 $1.000 $3.000 $1.550 $4.000 $4.500 $5.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 13.000 $5,000.000 $1,000.000 $1,500.000 $10,000.000 $2,500.000 $5,000.000 $6,250.000
PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL)
LF 2,675.000 $71.000 $70.000 $40.000 $80.000 $40.000 $70.000 $65.000
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
LF 2,520.000 $10.000 $5.000 $7.000 $7.000 $8.000 $12.000 $9.000
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL)
LF 2,675.000 $11.000 $5.000 $5.000 $12.000 $12.000 $24.000 $8.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 14,580.000 $0.300 $0.750 $1.000 $0.200 $1.000 $0.700 $0.600
MTL W-BEAM GD FEN (TIM POST)
LF 1,100.000 $22.000 $22.000 $18.000 $18.250 $20.000 $21.000 $17.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,850.000 $1,600.000 $1,275.000 $1,450.000 $1,400.000 $1,450.000 $1,400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,750.000 $2,600.000 $2,200.000 $2,500.000 $2,500.000 $2,700.000 $2,400.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $2,500.000 $2,200.000 $1,000.000 $2,400.000 $3,000.000 $2,200.000 $2,300.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,500.000 $1,000.000 $500.000 $880.000 $1,000.000 $900.000 $850.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $10,000.000 $8,000.000 $9,500.000 $10,000.000 $9,500.000 $9,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 4.000 $950.000 $950.000 $951.000 $825.000 $800.000 $950.000 $550.000
REMOVE SM RD SN SUP&AM
EA 1.000 $90.000 $150.000 $134.200 $110.000 $100.000 $190.700 $150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 10.000 $25.000 $20.000 $25.000 $20.000 $40.000 $20.000 $20.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $25.000 $30.000 $25.000 $26.000 $40.000 $25.000 $25.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 11,775.000 $0.250 $0.830 $0.830 $0.480 $0.800 $0.180 $0.200
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 48.000 $3.900 $8.000 $7.500 $6.600 $10.000 $3.300 $4.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 15,100.000 $0.250 $0.830 $0.800 $0.480 $0.800 $0.180 $0.200
PAVEMENT SEALER 4"
LF 930.000 $0.200 $1.100 $1.100 $0.160 $1.000 $1.600 $1.500
PREFAB PAV MRK TY B (W)(4")(SLD)
LF 1,340.000 $7.000 $8.000 $7.700 $7.150 $8.000 $6.200 $6.000
PREFAB PAV MRK TY B (Y)(4")(BRK)CNTST
LF 180.000 $8.000 $11.000 $11.000 $7.150 $15.000 $14.000 $12.500
REFL PAV MRKR TY II-A-A
EA 90.000 $3.200 $15.000 $6.600 $4.000 $10.000 $6.200 $6.000
PAV SURF PREP FOR MRK (4")
LF 930.000 $0.100 $1.100 $1.100 $0.700 $1.000 $1.100 $1.000
SP MIXES SP-C PG76-22
TON 2,947.000 $106.000 $110.000 $109.000 $125.000 $150.000 $155.000 $150.000
SP MIXES SP-D PG76-22
TON 2,525.000 $115.000 $110.000 $105.000 $126.000 $150.000 $142.000 $145.000
TACK COAT
GAL 3,500.000 $5.000 $4.000 $6.000 $3.600 $8.000 $8.000 $3.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $8,000.000 $8,000.000 $18,000.000 $10,000.000 $8,500.000 $23,000.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 7,280.000 $4.000 $5.000 $5.200 $7.150 $5.000 $5.250 $5.000
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 13,760.000 $0.400 $0.830 $0.820 $0.720 $0.800 $0.600 $0.750
REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)
LF 1,715.000 $0.500 $1.100 $1.100 $0.720 $1.000 $0.600 $0.750
TMA (STATIONARY)
DAY 90.000 $225.000 $200.000 $150.000 $100.000 $150.000 $175.000 $350.000
TMA (MOBILE OPERATION)
HR 20.000 $50.000 $30.000 $20.000 $100.000 $100.000 $75.000 $30.000
Totals: $4,498,344.100 $3,919,948.800 $4,065,123.466 $4,391,541.100 $4,497,963.000 $4,854,854.850 $5,194,759.850