Show Job Controls
Bid Cobra

BOWIE FM 2735 (0085-03-017)

Items: 25

County: BOWIE
Length: N/A
Highway: FM 2735
District: ATLANTA
Control Number: 0085-03-017
DBE Goal: N/A
Project: STP 2021(299)HES
Guaranty: N/A
Time: 285 WORKING DAYS
Engineer's Estimate: $1,759,581.25
Date: 06/03/2021 (5 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (9)
E
Engineer's Estimate
$1,759,581.25
$1,493,307.90
Over/Under Est: -15.13% -$266,273.35
$1,499,726.30
Over/Under Est: -14.77% -$259,854.95
Amt Left: 0.43% $6,418.40
Over/Under Est: -1.8% -$31,701.30
Amt Left: 15.71% $234,572.05
Delta: -15.21% -$228,153.65
Over/Under Est: -0.06% -$1,116.35
Amt Left: 17.76% $265,157.00
Delta: -1.77% -$30,584.95
Over/Under Est: 2.86% $50,395.79
Amt Left: 21.21% $316,669.14
Delta: -2.93% -$51,512.14
$1,827,735.19
Over/Under Est: 3.87% $68,153.94
Amt Left: 22.4% $334,427.29
Delta: -0.98% -$17,758.15
Over/Under Est: 13.42% $236,130.45
Amt Left: 33.64% $502,403.80
Delta: -9.19% -$167,976.51
Over/Under Est: 14.85% $261,228.18
Amt Left: 35.32% $527,501.53
Delta: -1.26% -$25,097.73
$2,371,153.00
Over/Under Est: 34.76% $611,571.75
Amt Left: 58.79% $877,845.10
Delta: -17.34% -$350,343.57
Subcontractor Percentage Amount
CLEANVAC ENVIRONMENTAL LLC 1.89% $29,979.41
FLEX SUPPLY, LLC 1.58% $25,062.15
H. V. CAVER, INC. 1.26% $19,986.28
Total: 4.73% $75,027.84

Bid Items & Bid Tabulations

25 Total 0 of 25
BOWIE  |  FM 2735  |  ATLANTA  |  0085-03-017  |  06/03/2021  |  $1,759,581.25  |  STP 2021(299)HES  |  SAFETY TREAT FIXED OBJECTS  |  285 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
HX FARMS, INC.
CDM HOLDINGS, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
R & G CONSTRUCTION, LLC
STATELINE CONSTRUCTION, LLC
H. V. CAVER, INC.
EAST TEXAS BRIDGE, INC.
HIGHWAY 19 CONSTRUCTION LLC
ENCINO LANDSCAPE, INC.
REMOVING CONC (DRIVEWAYS)
SY 368.000 $8.500 $12.000 $11.000 $20.000 $15.000 $55.000 $15.000 $22.000 $25.000 $20.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 1,369.000 $17.500 $12.000 $17.000 $18.000 $30.000 $16.000 $22.000 $25.000 $30.000 $20.000
BLADING
STA 350.050 $150.000 $40.000 $20.000 $155.000 $150.000 $75.000 $50.000 $300.000 $300.000 $100.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 47,390.000 $0.180 $0.600 $0.100 $0.140 $0.200 $0.370 $0.160 $0.210 $0.140 $0.150
VEGETATIVE WATERING
MG 745.900 $4.500 $1.000 $7.000 $4.000 $1.000 $11.160 $0.010 $12.000 $10.000 $5.000
CUT & RESTORE ASPH PAVING
SY 1,401.000 $75.000 $50.000 $55.000 $80.000 $55.000 $64.250 $65.000 $55.000 $61.000 $80.000
RIPRAP (CONC)(4 IN)
CY 7.000 $450.000 $500.000 $800.000 $860.000 $1,000.000 $800.000 $400.000 $675.000 $1,000.000 $420.000
RC PIPE (CL III)(15 IN)
LF 859.000 $37.500 $26.000 $35.000 $34.000 $37.000 $51.000 $34.870 $39.000 $33.370 $60.000
RC PIPE (CL III)(18 IN)
LF 4,059.000 $40.000 $0.000 $0.000 $37.000 $0.000 $0.000 $38.550 $44.000 $0.000 $0.000
RC PIPE (CL III)(18 IN)
LF 4,574.000 $40.000 $30.000 $37.000 $37.000 $40.000 $55.000 $38.550 $44.000 $37.500 $60.000
RC PIPE (CL III)(24 IN)
LF 462.000 $65.000 $50.000 $55.000 $55.000 $60.000 $66.000 $58.820 $62.000 $54.000 $60.000
RC PIPE (CL III)(24 IN)
LF 136.000 $65.000 $0.000 $0.000 $55.000 $0.000 $0.000 $58.820 $62.000 $0.000 $0.000
RC PIPE (CL III)(30 IN)
LF 44.000 $90.000 $75.000 $80.000 $90.000 $110.000 $200.000 $83.750 $100.000 $99.000 $80.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 124.000 $600.000 $480.000 $490.000 $530.000 $545.000 $650.000 $530.000 $530.000 $550.000 $800.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1,124.000 $550.000 $510.000 $550.000 $550.000 $650.000 $475.000 $571.250 $625.000 $611.000 $800.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 102.000 $1,000.000 $850.000 $920.000 $980.000 $1,050.000 $835.000 $992.500 $1,000.000 $1,032.000 $1,500.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 10.000 $1,800.000 $1,850.000 $1,850.000 $1,900.000 $1,800.000 $1,800.000 $1,838.000 $2,400.000 $2,363.000 $2,000.000
REMOV STR (PIPE)
LF 10,182.000 $9.500 $8.000 $8.000 $10.000 $3.000 $27.750 $15.000 $7.000 $10.000 $20.000
MOBILIZATION
LS 1.000 $39,000.000 $150,000.000 $72,500.000 $100,000.000 $110,000.000 $65,000.000 $145,000.000 $175,000.000 $200,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $5,000.000 $2,000.000 $2,000.000 $2,000.000 $2,000.000 $1,600.000 $4,050.000 $3,000.000 $5,000.000 $5,800.000
DRIVEWAYS (CONC)(TYPE 1)
SY 412.000 $80.000 $100.000 $80.000 $100.000 $104.000 $57.500 $100.000 $85.000 $100.000 $80.000
DRIVEWAYS (CONC)(TYPE 2)
SY 45.000 $90.000 $110.000 $120.000 $120.000 $115.000 $105.000 $135.000 $115.000 $150.000 $90.000
TMA (STATIONARY)
DAY 281.000 $175.000 $55.000 $90.000 $125.000 $110.000 $127.000 $50.000 $175.000 $200.000 $180.000
1
THERMOPLASTIC PIPE(24 IN)(PP)(TYPE III)
LF 136.000 $65.000 $25.000 $32.000 $0.000 $38.000 $95.000 $0.000 $0.000 $35.000 $20.000
1
THERMOPLASTIC PIPE(18 IN)(PP)(TYPE III)
LF 4,059.000 $40.000 $23.000 $22.000 $0.000 $31.500 $27.000 $0.000 $0.000 $32.000 $20.000
Totals: $1,930,781.250 $1,493,307.900 $1,499,726.300 $1,727,879.950 $1,758,464.900 $1,809,977.044 $1,827,735.199 $1,995,711.700 $2,020,809.430 $2,371,153.000