Show Job Controls
Bid Cobra

BOWIE US 82 (0046-05-050)

Items: 16

County: BOWIE
Length: N/A
Highway: US 82
District: ATLANTA
Control Number: 0046-05-050
DBE Goal: N/A
Project: STP 2019(202)
Guaranty: N/A
Time: 20 WORKING DAYS
Engineer's Estimate: $470,867.05
Date: 11/06/2018 (7 years ago)
Contract Number: N/A
Type: LEVEL UP, MICROSURFACING & PAV MRKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$470,867.05
Over/Under Est: 5.09% $23,961.20
Over/Under Est: 13.97% $65,787.43
Amt Left: 8.45% $41,826.23
Over/Under Est: 16.74% $78,806.50
Amt Left: 11.08% $54,845.30
Delta: -2.43% -$13,019.07

Bid Items & Bid Tabulations

16 Total 0 of 16
BOWIE  |  US 82  |  ATLANTA  |  0046-05-050  |  11/06/2018  |  $470,867.05  |  STP 2019(202)  |  LEVEL UP, MICROSURF & PAV MRKS  |  20 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
VIKING CONSTRUCTION, INC.
INTERMOUNTAIN SLURRY SEAL, INC.
MICROSURFACING
TON 1,488.000 $200.000 $228.000 $267.000 $250.000
MOBILIZATION
LS 1.000 $42,579.000 $51,000.000 $22,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $2,500.000 $4,030.000 $12,000.000 $15,000.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,106.000 $1.500 $2.000 $1.000 $1.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 186.000 $25.000 $13.500 $14.850 $20.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $560.000 $700.000 $770.000 $700.000
REFL PAV MRKR TY II-A-A
EA 403.000 $4.000 $3.700 $4.070 $10.000
REFL PAV MRKR TY II-C-R
EA 7.000 $8.000 $8.000 $8.800 $10.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 8,425.000 $5.600 $3.500 $3.850 $4.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 4,212.000 $5.800 $3.500 $3.850 $4.000
REFL PAV MRK AWT (W) 6" (SLD) (100MIL)
LF 42,124.000 $0.600 $0.650 $0.720 $0.650
REFL PAV MRK AWT (W) 6" (BRK) (100MIL)
LF 147.000 $1.000 $2.000 $2.200 $2.500
REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)
LF 13,404.000 $0.650 $0.650 $0.720 $1.000
REFL PAV MRK AWT (Y) 6" (BRK) (100MIL)
LF 4,073.000 $0.650 $0.650 $0.720 $0.650
TMA (STATIONARY)
DAY 12.000 $500.000 $500.000 $300.000 $450.000
TMA (MOBILE OPERATION)
HR 64.000 $50.000 $25.000 $27.500 $25.000
Totals: $470,867.050 $494,828.250 $536,654.480 $549,673.550