BOSQUE FM 217 (0833-02-020)

Items: 162

County: BOSQUE
Length: N/A
Highway: FM 217
District: WACO
Control Number: 0833-02-020
DBE Goal: N/A
Project: F 2022(560)
Guaranty: N/A
Time: 315 WORKING DAYS
Engineer's Estimate: $11,923,878.47
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$11,923,878.47
$12,983,870.35
Over/Under Est: 8.89% $1,059,991.88
Over/Under Est: 15.06% $1,796,199.01
Amt Left: 5.67% $736,207.13
Over/Under Est: 33.73% $4,022,150.06
Amt Left: 22.81% $2,962,158.18
Delta: -16.22% -$2,225,951.05
Over/Under Est: 47.02% $5,606,942.12
Amt Left: 35.02% $4,546,950.24
Delta: -9.94% -$1,584,792.06
Over/Under Est: 48.67% $5,803,329.76
Amt Left: 36.53% $4,743,337.88
Delta: -1.12% -$196,387.64
Subcontractor Percentage Amount
BEAR CREEK CONSTRUCTION, LLC 15.86% $2,059,241.84
WILKO INDUSTRIAL, L.L.C. 11.26% $1,461,983.80
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 2.94% $381,725.79
COLD CREEK CONSTRUCTION, LTD 1.95% $253,185.47
DIIBS SPECIALISTS, LLC 1.93% $250,588.70
HODGES AND SON CONSTRUCTION COMPANY, INC. 1.25% $162,298.38
SAN-ANN-CO., INC. 1.23% $159,701.61
D. I. J. CONSTRUCTION, INC. 1.12% $145,419.35
TOTAL HIGHWAY MAINTENANCE, LLC 1.07% $138,927.41
LINDAMOOD, INC. 0.54% $70,112.90
BARRIER FENCE, LLC 0.15% $19,475.81
CHEROKEE SERVICES 0.10% $12,983.87
A-CORE CONCRETE CUTTING, INC. 0.07% $9,088.71
AWP SAFETY 0.03% $3,895.16
DALLAS LITE AND BARRICADE, INC. 0.03% $3,895.16
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 39.53% $5,132,523.96

Bid Items & Bid Tabulations

162 Total 0 of 162
BOSQUE  |  FM 217  |  WACO  |  0833-02-020  |  06/01/2022  |  $11,923,878.47  |  F 2022(560)  |  REHAB EXIST ROADWAY  |  315 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
STATELINE CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
JAMES CONSTRUCTION GROUP, LLC
PREPARING ROW
STA 424.000 $2,500.000 $895.000 $1,000.000 $1,000.000 $930.000 $4,000.000
REMOVING CONC (DRIVEWAYS)
SY 300.000 $15.000 $20.000 $25.000 $20.000 $14.000 $8.860
REMOVING CONC (CURB)
LF 1,287.000 $15.000 $2.550 $15.000 $20.000 $11.000 $1.370
REMOVING CONC (RETAINING WALLS)
SY 17.000 $32.500 $47.000 $125.000 $200.000 $200.000 $102.070
REMOVE CONC (MISC)
EA 1.000 $1,400.000 $400.000 $2,500.000 $1,000.000 $3,500.000 $1,792.030
REMOVING STAB BASE AND ASPH PAV (2"-8")
SY 576.000 $5.000 $5.000 $7.000 $17.000 $5.700 $8.860
OBLITERATING ABANDONED ROAD
SY 14,200.000 $2.200 $0.050 $1.000 $5.500 $0.010 $0.930
EXCAVATION (ROADWAY)
CY 9,110.000 $10.000 $10.750 $17.000 $12.000 $23.000 $6.380
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 15,959.000 $12.500 $11.660 $17.000 $13.500 $29.000 $10.600
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,860.000 $8.900 $17.000 $25.000 $19.000 $29.000 $29.520
BACKFILL (TY A)
STA 424.000 $185.000 $145.000 $250.000 $400.000 $320.000 $448.080
FURNISHING AND PLACING TOPSOIL (4")
SY 188,598.000 $0.750 $0.250 $0.500 $1.000 $0.010 $0.890
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 188,598.000 $0.120 $0.160 $0.160 $0.250 $0.160 $0.160
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 188,598.000 $0.100 $0.120 $0.100 $0.180 $0.120 $0.120
VEGETATIVE WATERING
MG 3,066.000 $7.000 $1.000 $10.000 $5.000 $0.010 $30.780
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 13,024.000 $2.000 $1.250 $1.500 $1.750 $1.110 $1.110
PROOF ROLLING
HR 77.000 $90.000 $50.000 $50.000 $100.000 $158.000 $126.590
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 22,842.000 $45.000 $47.000 $55.000 $50.500 $90.000 $77.500
FL BS (RDWY DEL)(TY D GR 3)(FINAL POS)
CY 10,836.000 $40.000 $41.000 $55.000 $54.500 $59.000 $77.500
REWORK BS MATL (TY C)(9")(ORD COMP)
SY 112,841.000 $3.000 $1.250 $1.500 $5.950 $1.050 $4.360
CEMENT
TON 1,752.000 $185.000 $202.000 $225.000 $250.000 $200.000 $237.420
CEMENT TREAT(EXIST MATL)(8")
SY 146,195.000 $2.350 $1.750 $3.000 $3.500 $4.000 $1.930
EMULS ASPH (BS OR SUBGR TRT)(MS-2)
GAL 30,584.000 $2.500 $2.000 $4.000 $6.250 $6.600 $3.000
ASPH (CRS-2)
GAL 66,832.000 $3.000 $3.500 $3.750 $6.000 $5.100 $4.530
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 1,098.000 $100.000 $129.000 $125.000 $175.000 $146.000 $129.110
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 500.000 $45.000 $69.000 $70.000 $55.000 $93.000 $79.210
PLANE ASPH CONC PAV(0" TO 4")
SY 1,412.000 $2.500 $11.000 $5.000 $18.000 $6.600 $2.080
PAV JT UNDERSEAL (24")
LF 102.000 $25.000 $52.000 $95.000 $200.000 $38.000 $77.160
CEM STABIL BKFL
CY 3,541.000 $105.000 $180.000 $100.000 $190.000 $223.000 $198.900
CUT & RESTORING PAV
SY 715.000 $100.000 $124.000 $100.000 $74.000 $61.000 $51.690
FLOWABLE BACKFILL
CY 1.000 $130.000 $4,000.000 $750.000 $4,000.000 $200.000 $876.600
TRENCH EXCAVATION PROTECTION
LF 410.000 $2.100 $7.250 $20.000 $20.000 $7.000 $1.140
TEMPORARY SPL SHORING
SF 270.000 $28.000 $49.000 $65.000 $40.000 $107.000 $84.700
DRILL SHAFT (24 IN)
LF 372.000 $202.000 $205.000 $275.000 $300.000 $232.000 $179.710
DRILL SHAFT (36 IN)
LF 375.000 $200.000 $382.000 $400.000 $375.000 $370.000 $336.270
CL B CONC (FLUME)
CY 7.400 $700.000 $1,450.000 $1,000.000 $800.000 $1,200.000 $690.960
CL C CONC (ABUT)(HPC)
CY 70.000 $1,000.000 $1,290.000 $1,500.000 $1,600.000 $1,800.000 $1,505.570
CL C CONC (CAP)(HPC)
CY 54.600 $1,150.000 $1,446.000 $1,500.000 $1,800.000 $2,500.000 $2,282.190
CL C CONC (COLUMN)(HPC)
CY 47.600 $1,100.000 $980.000 $2,000.000 $2,000.000 $1,200.000 $993.680
REINF CONC SLAB
SF 7,260.000 $17.000 $26.850 $28.000 $25.000 $36.200 $37.800
REINF CONC SLAB (SLAB BEAM)
SF 2,409.000 $18.000 $22.400 $28.000 $29.000 $39.000 $32.360
APPROACH SLAB
CY 115.400 $500.000 $625.000 $1,000.000 $700.000 $900.000 $741.130
PRESTR CONC SLAB BEAM (4SB12)
LF 588.000 $190.000 $235.000 $200.000 $250.000 $200.000 $205.550
PRESTR CONC GIRDER (TX28)
LF 1,145.760 $130.000 $215.000 $200.000 $225.000 $200.000 $206.110
RIPRAP (CONC)(4 IN)
CY 2.000 $550.000 $630.000 $750.000 $2,000.000 $600.000 $1,810.360
RIPRAP (CONC)(5 IN)
CY 2.000 $400.000 $630.000 $750.000 $2,000.000 $600.000 $1,810.360
RIPRAP (CONC)(CL B)
CY 4.500 $400.000 $2,350.000 $750.000 $2,000.000 $1,200.000 $958.140
RIPRAP (STONE PROTECTION)(12 IN)
CY 869.000 $140.000 $155.000 $125.000 $135.000 $148.000 $86.100
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,127.000 $140.000 $115.000 $125.000 $140.000 $175.000 $84.850
RIPRAP (STONE PROTECTION)(24 IN)
CY 576.000 $110.000 $117.000 $125.000 $160.000 $175.000 $83.550
RIPRAP (MOW STRIP)(4 IN)
CY 166.000 $450.000 $495.000 $550.000 $600.000 $473.000 $719.930
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 102.000 $21.940 $52.000 $75.000 $300.000 $48.000 $44.840
CLEANING AND SEALING JOINTS (CL 3)
LF 68.000 $21.920 $62.000 $75.000 $300.000 $48.000 $44.840
RAIL (TY T1W)
LF 544.000 $200.000 $240.000 $325.000 $235.000 $240.000 $211.730
RETROFIT RAIL (TY SSTR)
LF 346.000 $172.230 $265.000 $200.000 $300.000 $110.000 $88.910
ARMOR JOINT (SEALED)
LF 57.000 $100.000 $145.000 $125.000 $200.000 $150.000 $122.080
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 86.000 $115.000 $210.000 $200.000 $225.000 $240.000 $192.330
CONC BOX CULV (3 FT X 2 FT)
LF 276.000 $255.000 $215.000 $275.000 $245.000 $205.000 $275.100
CONC BOX CULV (4 FT X 2 FT)
LF 88.000 $251.000 $251.000 $325.000 $300.000 $239.000 $420.910
CONC BOX CULV (4 FT X 3 FT)
LF 46.000 $370.000 $283.000 $375.000 $345.000 $269.000 $454.500
CONC BOX CULV (5 FT X 2 FT)
LF 92.000 $340.000 $333.000 $500.000 $385.000 $317.000 $486.680
CONC BOX CULV (7 FT X 3 FT)
LF 46.000 $420.000 $545.000 $625.000 $645.000 $518.000 $697.340
CONC BOX CULV (7 FT X 4 FT)
LF 138.000 $560.000 $617.000 $650.000 $685.000 $587.000 $739.220
CONC BOX CULV (7 FT X 7 FT)
LF 192.000 $1,200.000 $772.000 $800.000 $800.000 $734.000 $861.040
CONC BOX CULV (8 FT X 5 FT)
LF 144.000 $590.000 $674.000 $900.000 $800.000 $641.000 $819.500
CONC BOX CULV (10 FT X 5 FT)
LF 208.000 $800.000 $1,032.000 $1,100.000 $1,300.000 $981.000 $1,091.850
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 12.000 $800.000 $773.000 $1,000.000 $1,400.000 $735.000 $1,767.080
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 8.000 $650.000 $1,511.000 $1,250.000 $1,200.000 $1,436.000 $1,767.080
RC PIPE (CL III)(18 IN)
LF 1,160.000 $68.000 $60.000 $65.000 $59.500 $57.000 $93.190
RC PIPE (CL III)(24 IN)
LF 690.000 $80.000 $87.000 $90.000 $70.000 $83.000 $137.450
RC PIPE (CL III)(27 IN)
LF 76.000 $100.000 $103.000 $120.000 $100.000 $98.000 $170.990
RC PIPE (CL III)(30 IN)
LF 90.000 $100.000 $114.000 $150.000 $100.000 $109.000 $255.540
RC PIPE (CL III)(48 IN)
LF 120.000 $200.000 $243.000 $285.000 $210.000 $231.000 $258.990
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 4.000 $4,700.000 $7,500.000 $6,000.000 $7,500.000 $7,158.000 $14,136.620
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 4.000 $6,000.000 $7,900.000 $8,500.000 $11,000.000 $7,540.000 $18,848.820
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 1.000 $13,000.000 $13,000.000 $15,000.000 $18,000.000 $12,579.000 $42,409.870
HEADWALL (CH - PW - S) (DIA= 24 IN)
EA 2.000 $7,500.000 $8,200.000 $5,000.000 $13,000.000 $7,971.000 $18,848.830
HEADWALL (CH - PW - S) (DIA= 36 IN)
EA 1.000 $12,500.000 $9,600.000 $8,000.000 $14,800.000 $9,236.000 $37,697.650
WINGWALL (FW - 0) (HW=5 FT)
EA 1.000 $9,000.000 $8,000.000 $10,000.000 $14,000.000 $7,785.000 $18,848.830
WINGWALL (PW - 1) (HW=10 FT)
EA 2.000 $40,000.000 $41,000.000 $50,000.000 $37,500.000 $39,500.000 $90,284.530
WINGWALL (PW - 1) (HW=3 FT)
EA 1.000 $8,600.000 $7,500.000 $6,000.000 $14,000.000 $7,387.000 $18,848.830
WINGWALL (PW - 1) (HW=4 FT)
EA 4.000 $9,100.000 $8,500.000 $8,000.000 $16,000.000 $8,112.000 $21,204.930
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $13,000.000 $9,500.000 $15,000.000 $22,000.000 $9,206.000 $23,561.050
WINGWALL (PW - 1) (HW=6 FT)
EA 7.000 $19,000.000 $12,000.000 $20,000.000 $20,000.000 $11,627.000 $24,678.760
WINGWALL (PW - 1) (HW=7 FT)
EA 4.000 $20,000.000 $13,500.000 $30,000.000 $21,000.000 $13,122.000 $28,260.410
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
EA 2.000 $6,200.000 $10,500.000 $4,000.000 $17,000.000 $9,999.000 $5,022.490
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P)
EA 2.000 $6,000.000 $11,500.000 $6,000.000 $12,000.000 $10,972.000 $8,800.220
SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C)
EA 4.000 $5,400.000 $10,900.000 $2,500.000 $14,800.000 $10,423.000 $8,800.220
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 50.000 $1,100.000 $1,175.000 $1,000.000 $1,800.000 $1,133.000 $1,234.830
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 10.000 $1,200.000 $1,075.000 $1,100.000 $2,200.000 $1,028.000 $1,272.670
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 12.000 $1,400.000 $1,400.000 $1,250.000 $2,400.000 $1,350.000 $1,427.050
SET (TY II) (27 IN) (RCP) (6: 1) (C)
EA 2.000 $2,500.000 $2,050.000 $2,000.000 $3,000.000 $1,988.000 $2,318.650
SET (TY II) (36 IN) (CMP) (4: 1) (C)
EA 1.000 $3,500.000 $2,600.000 $2,500.000 $4,200.000 $2,563.000 $3,806.330
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 1.000 $5,250.000 $12,850.000 $6,500.000 $7,200.000 $12,315.000 $5,914.830
CLEAN EXIST CULVERTS
EA 4.000 $3,500.000 $1,575.000 $3,500.000 $1,900.000 $1,500.000 $4,265.760
REMOV STR (SET)
EA 5.000 $375.000 $250.000 $1,000.000 $1,800.000 $244.000 $728.110
REMOV STR (WINGWALL)
EA 12.000 $1,000.000 $500.000 $1,800.000 $2,500.000 $488.000 $1,638.640
REMOV STR (HEADWALL)
EA 2.000 $1,100.000 $500.000 $1,800.000 $5,000.000 $489.000 $2,203.260
REMOV STR (PIPE)
LF 1,766.000 $16.000 $10.250 $22.000 $12.000 $10.000 $33.190
REMOV STR (BOX CULVERT)
LF 354.000 $56.000 $48.000 $60.000 $35.000 $46.000 $86.290
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $23,000.000 $60,000.000 $30,000.000 $30,000.000 $20,000.000 $50,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $66,000.000 $90,000.000 $60,000.000 $50,000.000 $39,000.000 $70,000.000
MOBILIZATION
LS 1.000 $925,000.000 $1,300,000.000 $1,300,000.000 $1,250,000.000 $1,619,555.000 $1,700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $8,100.000 $6,800.000 $5,000.000 $5,000.000 $47,050.000 $8,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 4,880.000 $26.000 $31.000 $25.000 $38.000 $30.220 $30.220
ROCK FILTER DAMS (REMOVE)
LF 4,880.000 $6.000 $10.300 $5.000 $6.000 $10.300 $10.300
TEMP SEDMT CONT FENCE (INSTALL)
LF 30,216.000 $2.730 $4.300 $3.300 $3.750 $3.520 $3.520
TEMP SEDMT CONT FENCE (REMOVE)
LF 30,216.000 $0.600 $0.630 $0.500 $0.750 $0.630 $0.630
CONSTRUCTING DETOURS
SY 1,298.000 $70.000 $99.000 $100.000 $75.000 $140.000 $79.210
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 80.000 $115.000 $50.000 $100.000 $75.000 $64.000 $123.370
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 27.000 $3,400.000 $500.000 $2,500.000 $7,000.000 $0.010 $2,148.070
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 960.000 $18.000 $31.000 $20.000 $45.000 $45.500 $11.600
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 960.000 $5.000 $26.000 $18.000 $22.000 $36.000 $7.420
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 960.000 $13.000 $24.000 $19.000 $25.000 $29.500 $11.470
CONC CURB (TY II)
LF 1,300.000 $17.000 $18.000 $25.000 $50.000 $40.000 $10.150
DRIVEWAYS (CONC)
SY 531.000 $85.000 $97.000 $90.000 $120.000 $89.000 $88.480
DRIVEWAYS (ACP)(TYPE 1)
SY 4,904.000 $32.000 $69.000 $50.000 $54.780 $100.000 $65.840
DRIVEWAYS (ACP) (TYPE 2)
SY 2,225.000 $42.000 $65.000 $60.000 $61.000 $110.000 $78.190
MTL W-BEAM GD FEN (STEEL POST)
LF 4,050.000 $30.000 $35.000 $35.000 $39.000 $34.570 $34.570
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $2,200.000 $2,850.000 $3,000.000 $3,100.000 $2,794.970 $2,794.970
SHORT RADIUS
LF 15.625 $66.000 $50.000 $100.000 $65.000 $72.650 $72.650
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,100.000 $840.000 $900.000 $1,500.000 $853.130 $853.130
MTL BM GD FEN TRANS (31"-28")
EA 1.000 $1,400.000 $1,050.000 $350.000 $1,500.000 $268.850 $268.850
REMOVE METAL BEAM GUARD FENCE
LF 2,950.000 $2.250 $2.100 $3.000 $3.000 $2.500 $2.300
GUARDRAIL END TREATMENT (INSTALL)
EA 23.000 $3,000.000 $3,150.000 $3,750.000 $3,800.000 $3,626.170 $3,626.170
CRASH CUSH ATTEN (MOVE & RESET)
EA 16.000 $1,400.000 $2,325.000 $1,500.000 $3,000.000 $1,500.000 $1,500.000
CRASH CUSH ATTEN (STKPL)
EA 4.000 $1,200.000 $1,000.000 $3,500.000 $1,250.000 $3,500.000 $3,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $9,000.000 $9,000.000 $8,000.000 $11,000.000 $7,523.000 $7,523.000
WIRE FENCE (TY C)
LF 113.000 $20.000 $42.000 $50.000 $40.000 $50.000 $10.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 29.000 $225.000 $210.000 $225.000 $500.000 $200.000 $214.070
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 4.000 $275.000 $260.000 $250.000 $800.000 $250.000 $217.350
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 3.000 $500.000 $470.000 $525.000 $1,000.000 $450.000 $506.780
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 143.000 $555.000 $525.000 $625.000 $400.000 $500.000 $616.710
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 9.000 $650.000 $630.000 $900.000 $600.000 $600.000 $877.760
IN SM RD SN SUP&AM TY10BWG(2)SA(P-EXAL)
EA 1.000 $800.000 $1,050.000 $1,600.000 $1,000.000 $1,000.000 $1,581.340
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $750.000 $785.000 $825.000 $1,000.000 $750.000 $803.410
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 9.000 $900.000 $840.000 $1,100.000 $900.000 $800.000 $1,054.530
REMOVE SM RD SN SUP&AM
EA 16.000 $95.000 $210.000 $125.000 $250.000 $200.000 $121.690
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 13.000 $23.000 $20.000 $15.000 $45.000 $12.700 $12.700
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 61.000 $40.000 $39.000 $40.000 $60.000 $36.370 $36.370
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 71.000 $90.000 $78.000 $100.000 $175.000 $150.000 $78.950
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 610.000 $0.250 $1.000 $1.000 $0.850 $1.650 $0.660
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 15,360.000 $0.150 $1.000 $0.700 $0.800 $1.650 $0.610
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 384.000 $4.400 $5.260 $5.000 $6.250 $9.000 $5.090
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 2,975.000 $0.700 $1.580 $2.000 $2.000 $4.500 $1.530
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 116.000 $10.000 $10.530 $10.000 $12.500 $18.000 $10.180
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 200.000 $0.600 $1.580 $2.000 $2.000 $4.500 $1.530
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,234.000 $0.450 $1.350 $1.500 $3.000 $1.250 $1.020
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 160.000 $6.000 $7.630 $10.000 $8.500 $15.000 $7.380
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 14.000 $40.000 $57.000 $65.000 $75.000 $45.000 $55.970
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 84,502.000 $0.560 $0.740 $0.700 $0.850 $0.800 $0.710
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 4,737.000 $0.610 $0.890 $0.900 $1.000 $0.800 $0.870
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 58,525.000 $0.580 $0.740 $0.700 $0.830 $0.800 $0.710
REFL PAV MRKR TY II-A-A
EA 965.000 $4.000 $5.260 $5.000 $6.250 $6.200 $5.090
ELIM EXT PAV MRK & MRKS (4")
LF 2,554.000 $0.550 $2.370 $2.500 $2.750 $2.000 $2.290
FULL - WIDTH MOWING
CYC 4.000 $3,500.000 $3,300.000 $2,000.000 $2,500.000 $7,500.000 $1,882.200
LITTER REMOVAL
CYC 7.000 $1,500.000 $1,000.000 $2,500.000 $1,000.000 $1,200.000 $690.660
D-GR HMA TY-C SAC-B PG64-22
TON 16,643.000 $75.000 $110.000 $100.000 $125.000 $140.000 $128.590
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,349.760 $7,500.000 $10,000.000 $8,500.000 $9,500.000 $11,305.620
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 80.000 $15.000 $36.840 $35.000 $47.000 $24.000 $35.620
TMA (STATIONARY)
DAY 273.000 $190.000 $100.980 $200.000 $175.000 $390.000 $346.150
TMA (MOBILE OPERATION)
HR 72.000 $45.000 $86.220 $50.000 $350.000 $145.000 $111.750
Totals: $11,923,878.470 $12,983,870.350 $13,720,077.480 $15,946,028.535 $17,530,820.596 $17,727,208.258