BLANCO RM 1623 (1534-01-021)
Items: 26
County: BLANCO
Length: 0.0000 MILES
Highway: RM 1623
District: AUSTIN
Control Number: 1534-01-021
DBE Goal: 0.0%
Project: F 2B25(131)
Guaranty: $15,000.00
Time: 23 WORKING DAYS
Engineer's Estimate: $742,494.35
Date: 09/05/2025 (9 months ago)
Contract Number: 9253232
Type: SEAL COAT
Project ID: A00209805
Contract Type: Federal
Project Description: FDR, LEVEL-UP, SEAL COAT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOE MUCK
TYLER BRUDNICK
BLANCO RM 1623 (1534-01-021)
Project Name: N/A
Project: F 2B25(131)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.34 MI N OF RM 1888
Limits To: 0.13 MI W OF TRAINER WUEST RD.
Project Description: FDR, LEVEL-UP, SEAL COAT
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$742,494.35 | |||
| $507,632.56 |
-31.63%
-$234,861.79
|
|||
| $537,271.10 |
-27.64%
-$205,223.25
|
5.84%
$29,638.54
|
||
| $549,657.75 |
-25.97%
-$192,836.60
|
8.28%
$42,025.19
|
-2.31%
-$12,386.65
|
|
| $566,792.00 |
-23.66%
-$175,702.35
|
11.65%
$59,159.44
|
-3.12%
-$17,134.25
|
|
| $577,061.02 |
-22.28%
-$165,433.33
|
13.68%
$69,428.46
|
-1.81%
-$10,269.02
|
|
| $694,000.00 |
-6.53%
-$48,494.35
|
36.71%
$186,367.44
|
-20.26%
-$116,938.98
|
|
| $703,330.55 |
-5.27%
-$39,163.80
|
38.55%
$195,697.99
|
-1.34%
-$9,330.55
|
|
| $823,093.30 |
10.86%
$80,598.95
|
62.14%
$315,460.74
|
-17.03%
-$119,762.75
|
E
Engineer's Estimate
$742,494.35
1
Awarded
$507,632.56
Over/Under Est:
-31.63%
-$234,861.79
$537,271.10
Over/Under Est:
-27.64%
-$205,223.25
Amt Left:
5.84%
$29,638.54
$549,657.75
Over/Under Est:
-25.97%
-$192,836.60
Amt Left:
8.28%
$42,025.19
Delta:
-2.31%
-$12,386.65
$566,792.00
Over/Under Est:
-23.66%
-$175,702.35
Amt Left:
11.65%
$59,159.44
Delta:
-3.12%
-$17,134.25
$577,061.02
Over/Under Est:
-22.28%
-$165,433.33
Amt Left:
13.68%
$69,428.46
Delta:
-1.81%
-$10,269.02
$694,000.00
Over/Under Est:
-6.53%
-$48,494.35
Amt Left:
36.71%
$186,367.44
Delta:
-20.26%
-$116,938.98
$703,330.55
Over/Under Est:
-5.27%
-$39,163.80
Amt Left:
38.55%
$195,697.99
Delta:
-1.34%
-$9,330.55
$823,093.30
Over/Under Est:
10.86%
$80,598.95
Amt Left:
62.14%
$315,460.74
Delta:
-17.03%
-$119,762.75
| Subcontractor | Percentage | Amount |
|---|---|---|
| D. I. J. CONSTRUCTION, INC. | 13.43% | $68,175.05 |
| INTERSTATE BARRICADES & MARKINGS, INC. | 1.15% | $5,837.77 |
| Total: | 14.58% | $74,012.82 |
Bid Items & Bid Tabulations
26
Total
0 of 26
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $25,000.00 |