BEXAR SH 211 (3544-04-011)

Items: 69

County: BEXAR
Length: 3.6530 MILES
Highway: SH 211
District: SAN ANTONIO
Control Number: 3544-04-011
DBE Goal: 0.0%
Project: F 2026(463)
Guaranty: $66,000.00
Time: 86 WORKING DAYS
Engineer's Estimate: $3,287,114.71
Date: 03/05/2026 (3 months ago) Changed
Contract Number: 3263016
Type: RESURFACE ROADWAY
Project ID: A00135150
Contract Type: Federal
Project Description: BASE REPAIR, MILL, INLAY AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CARLOS ARCILA
ADDRESSDANNY GALLEGOS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$3,287,114.71
$2,498,077.69
Over/Under Est: -24% -$789,037.02
Over/Under Est: -22.87% -$751,600.09
Amt Left: 1.5% $37,436.93
Over/Under Est: -18.26% -$600,338.95
Amt Left: 7.55% $188,698.07
Delta: -5.97% -$151,261.14
Over/Under Est: -13.78% -$453,084.90
Amt Left: 13.45% $335,952.12
Delta: -5.48% -$147,254.05
Over/Under Est: -13.04% -$428,599.09
Amt Left: 14.43% $360,437.93
Delta: -0.86% -$24,485.81
Over/Under Est: -4.73% -$155,362.20
Amt Left: 25.37% $633,674.82
Delta: -9.56% -$273,236.89
$3,658,575.85
Over/Under Est: 11.3% $371,461.14
Amt Left: 46.46% $1,160,498.16
Delta: -16.82% -$526,823.34
Over/Under Est: 19.96% $656,133.39
Amt Left: 57.85% $1,445,170.41
Delta: -7.78% -$284,672.25

Bid Items & Bid Tabulations

69 Total 0 of 69
BEXAR  |  SH 211  |  SAN ANTONIO  |  3544-04-011  |  03/05/2026  |  $3,287,114.71  |  F 2026(463)  |  RESURF ROADWAY  |  86 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BOBCAT SERVICES, INC.
TEXAS MATERIALS GROUP, INC.
H. L. ZUMWALT CONSTRUCTION, INC.
DEAN WORD COMPANY, LTD.
LONE STAR PAVING COMPANY
HUNTER INDUSTRIES, LTD.
ALLEN KELLER COMPANY
CLARK CONSTRUCTION OF TEXAS, INC.
REMOV CONC (MOWSTRIP)
SY 1,753.000 $20.000 $19.000 $22.500 $6.080 $20.250 $17.000 $12.600 $11.450 $30.000
EMBANK (FNL)(OC)(TY B)
CY 100.000 $33.000 $75.000 $50.000 $3.000 $67.500 $100.000 $13.080 $69.030 $20.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 2,297.000 $90.000 $82.000 $86.000 $92.000 $93.750 $75.000 $71.820 $414.570 $148.690
SP MIXES SP-C SAC-B PG76-22
TON 12,339.000 $90.000 $69.000 $86.000 $93.000 $88.000 $93.000 $91.620 $75.070 $127.730
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 19,142.000 $33.000 $23.400 $27.500 $33.000 $31.000 $33.000 $34.170 $24.510 $39.780
PLANE ASPH CONC PAV(2")
SY 107,296.000 $1.600 $1.500 $1.200 $1.250 $1.250 $1.400 $1.230 $0.650 $1.940
RIPRAP (CONC)(4 IN)
CY 43.200 $590.000 $541.000 $550.000 $116.250 $718.250 $522.000 $572.340 $519.950 $650.000
RIPRAP (MOW STRIP)(4 IN)
CY 292.000 $695.000 $473.000 $460.000 $75.750 $548.000 $456.000 $618.540 $561.920 $665.000
CLEAN EXIST CULVERTS
EA 3.000 $3,913.000 $2,600.000 $2,250.000 $375.290 $1,133.500 $2,502.000 $2,625.390 $2,385.090 $5,000.000
MOBILIZATION
LS 1.000 $282,347.210 $130,500.000 $50,000.000 $150,000.000 $150,000.000 $100,000.000 $220,108.080 $348,000.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $6,700.000 $9,000.000 $450.000 $9,007.250 $750.000 $19,686.400 $2,788.170 $1,623.750
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,915.000 $5,855.000 $1,000.000 $1,000.000 $5,792.500 $5,000.000 $5,000.000 $2,828.830 $118.120
TMA (STATIONARY)
DAY 44.000 $189.000 $363.000 $25.000 $150.000 $468.750 $250.000 $150.000 $252.970 $90.000
TMA (MOBILE OPERATION)
DAY 75.000 $120.000 $363.000 $50.000 $300.000 $53.000 $250.000 $250.000 $83.580 $90.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $3.000 $3.600 $5.000 $0.750 $3.750 $3.500 $3.500 $4.530 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $1.000 $0.500 $1.000 $0.150 $0.500 $0.500 $0.500 $1.690 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 3,062.500 $25.000 $25.500 $24.210 $3.650 $26.500 $24.300 $24.000 $22.890 $35.000
SHORT RADIUS (28")
LF 55.000 $50.000 $40.500 $39.040 $5.880 $42.750 $39.200 $32.000 $30.530 $80.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,500.000 $1,308.000 $1,254.380 $188.840 $1,374.750 $1,259.000 $1,200.000 $1,144.840 $1,150.000
MTL THRIE-BEAM GD FEN (TIM POST)
EA 4.000 $2,231.000 $1,403.000 $1,350.100 $202.520 $1,479.500 $1,350.000 $2,450.000 $1,860.360 $2,500.000
MTL BM GD FEN TRANS (31"-28")(25')
EA 1.000 $650.000 $1,141.000 $1,093.990 $164.700 $1,199.000 $1,097.000 $575.000 $548.570 $500.000
REMOVE METAL BEAM GUARD FENCE
LF 3,125.000 $3.500 $2.000 $1.900 $0.290 $2.000 $1.900 $2.500 $2.380 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $220.000 $268.000 $257.050 $38.700 $281.750 $258.000 $250.000 $238.510 $225.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $327.000 $268.000 $257.050 $38.700 $281.750 $258.000 $250.000 $238.510 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 15.000 $3,568.000 $3,309.000 $3,185.000 $477.750 $3,490.500 $3,185.000 $3,000.000 $2,862.100 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 15.000 $306.000 $268.000 $257.050 $38.700 $281.750 $258.000 $250.000 $238.510 $250.000
ALUMINUM SIGNS (TY A)
SF 27.000 $37.000 $23.840 $23.650 $45.000 $26.000 $23.700 $30.000 $23.850 $25.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 32.000 $689.000 $627.090 $622.050 $150.000 $681.750 $622.000 $580.000 $620.120 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $853.000 $834.390 $827.690 $165.000 $907.000 $828.000 $690.000 $715.520 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $896.000 $1,022.000 $1,013.790 $183.000 $1,111.000 $1,014.000 $775.000 $906.330 $950.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,015.000 $1,104.930 $1,096.050 $189.000 $1,201.250 $1,096.000 $940.000 $715.530 $750.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $1,236.000 $1,088.330 $1,079.590 $216.000 $1,183.000 $1,080.000 $1,000.000 $787.080 $825.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 7.000 $1,213.000 $1,145.340 $1,136.140 $232.500 $1,245.000 $1,136.000 $980.000 $906.330 $950.000
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 3.000 $333.000 $217.670 $215.920 $67.500 $236.750 $216.000 $200.000 $143.100 $150.000
REMOVE SM RD SN SUP&AM
EA 41.000 $121.000 $93.290 $92.540 $22.500 $101.500 $93.000 $100.000 $95.400 $100.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 3.000 $53.000 $93.290 $92.540 $18.750 $101.500 $93.000 $50.000 $47.700 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 6.000 $25.000 $20.160 $20.000 $3.000 $22.000 $20.000 $20.000 $23.850 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 26.000 $30.000 $20.160 $20.000 $3.000 $22.000 $20.000 $28.000 $33.390 $35.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 29.000 $42.000 $25.910 $25.700 $3.870 $28.250 $25.800 $30.000 $33.390 $35.000
INSTL OM ASSM (OM-2Z)(WFLX)GNDHH
EA 6.000 $114.000 $91.210 $90.480 $13.620 $99.250 $90.800 $75.000 $119.250 $125.000
INSTL OM ASSM (OM-2Z)(WFLX)SRFHH
EA 16.000 $60.000 $88.710 $88.000 $13.200 $96.500 $88.000 $75.000 $119.260 $125.000
INSTL OM SM RD SIGN (1-OM-PW)Y
EA 45.000 $11.000 $20.160 $20.000 $3.000 $22.000 $20.000 $15.000 $73.940 $77.500
INSTL OM SM RD SIGN (1-OM-PW)R
EA 9.000 $11.000 $20.160 $20.000 $3.000 $22.000 $20.000 $15.000 $73.940 $77.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,779.000 $0.840 $0.470 $1.000 $2.000 $1.250 $1.000 $1.750 $3.200 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,230.000 $0.400 $0.490 $1.000 $2.000 $1.250 $1.000 $1.750 $3.230 $1.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 54.000 $1.190 $1.010 $1.000 $0.150 $1.000 $1.000 $1.000 $0.950 $1.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 48.000 $1.300 $2.020 $2.000 $0.300 $2.250 $2.000 $2.000 $1.910 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 8,004.000 $1.000 $1.010 $0.800 $0.120 $1.000 $0.800 $0.800 $0.950 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 887.000 $7.000 $6.550 $6.300 $0.950 $7.000 $6.300 $6.300 $6.200 $6.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 41.000 $140.000 $151.210 $145.000 $21.750 $159.000 $145.000 $145.000 $143.100 $150.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 40.000 $155.000 $176.420 $149.000 $22.350 $163.250 $149.000 $149.000 $166.960 $175.000
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 7.000 $357.000 $352.830 $200.000 $30.000 $219.250 $200.000 $200.000 $333.910 $350.000
PAVEMENT SLER 6"
LF 77,438.000 $0.200 $0.200 $0.170 $0.030 $0.250 $0.170 $0.170 $0.190 $0.200
PAVEMENT SLER 8"
LF 8,052.000 $0.200 $0.250 $0.380 $0.060 $0.500 $0.380 $0.380 $0.240 $0.250
PAVEMENT SLER 24"
LF 887.000 $1.000 $3.020 $1.000 $0.150 $1.000 $1.000 $1.000 $2.860 $3.000
PAVEMENT SLER (ARROW)
EA 41.000 $15.000 $50.400 $10.000 $1.500 $11.000 $10.000 $10.000 $47.700 $50.000
PAVEMENT SLER (WORD)
EA 40.000 $15.000 $50.400 $10.000 $1.500 $11.000 $10.000 $10.000 $47.700 $50.000
PAVEMENT SLER (MED NOSE)
EA 7.000 $134.000 $100.810 $40.000 $4.500 $33.000 $30.000 $30.000 $95.400 $100.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 4,040.000 $0.600 $0.500 $0.540 $0.080 $0.550 $0.540 $0.540 $0.480 $0.500
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 30,900.000 $0.600 $0.500 $0.500 $0.080 $0.500 $0.500 $0.500 $0.480 $0.500
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 42,444.000 $0.510 $0.500 $0.500 $0.080 $0.500 $0.500 $0.500 $0.480 $0.500
REFL PAV MRKR TY I-C
EA 748.000 $4.000 $3.530 $3.550 $0.530 $4.000 $3.550 $3.550 $3.340 $3.500
REFL PAV MRKR TY II-A-A
EA 1,925.000 $4.000 $3.530 $3.540 $0.530 $4.000 $3.550 $3.540 $3.340 $3.500
LITTER REMOVAL
CYC 12.000 $5,000.000 $917.000 $100.000 $5,000.000 $297.750 $50.000 $2,000.000 $850.310 $7,677.340
LITTER REMOVAL (SPOT)
AC 238.000 $10.000 $14.500 $20.000 $100.000 $5.500 $50.000 $50.000 $708.590 $119.000
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
CYC 12.000 $2,000.000 $630.500 $100.000 $950.000 $80.750 $50.000 $1,000.000 $824.940 $7,677.340
DEBRIS REMOVAL (SPOT DEBRIS)
MI 3.000 $2,500.000 $611.500 $500.000 $3,000.000 $173.500 $50.000 $1,000.000 $1,374.910 $206.700
UNDERSEAL COURSE
GAL 25,288.000 $3.710 $2.900 $0.010 $6.000 $0.010 $3.700 $3.460 $4.800 $5.080
BONDING COURSE
GAL 3,828.000 $1.320 $2.600 $0.010 $7.000 $0.010 $3.100 $2.700 $4.510 $4.020
Totals: $3,287,114.710 $2,498,077.690 $2,535,514.615 $2,686,775.755 $2,834,029.810 $2,858,515.620 $3,131,752.508 $3,658,575.845 $3,943,248.100
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,200.00
Total: $45,200.00