Show Job Controls
Bid Cobra

BEXAR SS 536 (0073-02-092)

Items: 56

County: BEXAR
Length: 0.8270 MILES
Highway: SS 536
District: SAN ANTONIO
Control Number: 0073-02-092
DBE Goal: 0.0%
Project: F 2026(363)
Guaranty: $36,000.00
Time: 53 WORKING DAYS
Engineer's Estimate: $1,278,676.58
Date: 05/07/2026 (5 weeks ago)
Contract Number: 5263237
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00214229
Contract Type: Federal
Project Description: SPOT BASE REPAIR, MILL, INLAY & PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CHRISTEN LONGORIA
CITLALI TAPIA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,278,676.58
$1,105,676.65
Over/Under Est: -13.53% -$172,999.93
Over/Under Est: -7.54% -$96,387.94
Amt Left: 6.93% $76,611.99
$1,204,051.08
Over/Under Est: -5.84% -$74,625.50
Amt Left: 8.9% $98,374.43
Delta: -1.84% -$21,762.44
Over/Under Est: 8.21% $105,017.77
Amt Left: 25.14% $278,017.70
Delta: -14.92% -$179,643.27
Over/Under Est: 14.1% $180,324.29
Amt Left: 31.96% $353,324.22
Delta: -5.44% -$75,306.52
Over/Under Est: 17.28% $220,932.42
Amt Left: 35.63% $393,932.35
Delta: -2.78% -$40,608.13
Over/Under Est: 33.78% $431,925.92
Amt Left: 54.71% $604,925.85
Delta: -14.07% -$210,993.50

Bid Items & Bid Tabulations

56 Total 0 of 56
BEXAR  |  SS 536  |  SAN ANTONIO  |  0073-02-092  |  05/07/2026  |  $1,278,676.58  |  F 2026(363)  |  SURF/ROADWAY RESTOR  |  53 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. L. ZUMWALT CONSTRUCTION, INC.
CLARK CONSTRUCTION OF TEXAS, INC.
BOBCAT SERVICES, INC.
TEXAS MATERIALS GROUP, INC.
LONE STAR PAVING COMPANY
DEAN WORD COMPANY, LTD.
HUNTER INDUSTRIES, LTD.
REMOV CONC (MOWSTRIP)
CY 16.000 $35.000 $115.000 $55.000 $190.000 $150.000 $75.000 $396.250 $181.500
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 15.000 $25.000 $45.000 $32.000 $33.000 $65.000 $19.000 $206.250 $24.500
REMOV CONC (CURB)
LF 8.000 $20.000 $45.000 $9.000 $35.000 $30.000 $10.000 $162.000 $14.000
EXCAV (SPECIAL)
CY 4.000 $32.310 $200.000 $65.000 $61.800 $120.000 $60.000 $328.500 $156.200
COMPOST MANUF TOPSOIL (4")
SY 64.000 $1.400 $55.000 $18.000 $67.500 $38.000 $10.000 $11.500 $21.000
BROADCAST SEED (PERM_URBAN_CLAY)
SY 64.000 $2.000 $45.000 $4.000 $10.500 $10.000 $5.000 $3.250 $10.500
VEGETATIVE WATERING
TGL 2.000 $30.000 $480.000 $50.000 $90.000 $750.000 $500.000 $60.250 $77.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 280.000 $140.000 $110.000 $81.330 $115.000 $137.000 $152.000 $186.000 $174.900
SP MIXES SP-C SAC-B PG76-22
TON 6,646.000 $92.080 $91.000 $100.070 $92.500 $108.000 $113.000 $110.000 $136.700
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 4,294.000 $39.500 $30.000 $41.780 $35.500 $42.750 $53.000 $52.750 $53.900
PLANE ASPH CONC PAV(0" TO 2")
SY 57,773.000 $1.970 $1.000 $1.460 $0.850 $1.900 $1.800 $2.000 $1.980
RIPRAP (MOW STRIP)(4 IN)
CY 16.000 $515.000 $480.000 $725.000 $600.000 $698.000 $585.000 $775.750 $899.070
ADJUSTING MANHOLES
EA 1.000 $3,920.000 $1,800.000 $300.000 $1,750.000 $3,800.000 $1,700.000 $2,967.500 $2,655.070
MOBILIZATION
LS 1.000 $162,106.320 $45,000.000 $16,500.000 $115,000.000 $100,000.000 $20,000.000 $50,000.000 $111,997.010
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $4,500.000 $4,500.000 $2,165.000 $2,300.000 $6,000.000 $1,916.000 $8,043.750 $6,410.410
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 79.000 $78.130 $65.000 $22.910 $78.500 $25.000 $150.000 $20.000 $90.910
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $1,167.010 $2,000.000 $1,145.070 $3,100.000 $1,500.000 $3,000.000 $5,000.000 $9,091.260
TMA (STATIONARY)
DAY 61.000 $152.000 $150.000 $90.000 $360.000 $25.000 $300.000 $436.250 $170.460
TMA (MOBILE OPERATION)
DAY 18.000 $270.470 $300.000 $87.000 $360.000 $250.000 $300.000 $125.000 $340.920
TEMP SEDMT CONT FENCE (INSTALL)
LF 310.000 $3.670 $3.500 $14.000 $4.100 $4.000 $5.750 $4.500 $4.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 310.000 $0.540 $2.000 $2.000 $0.500 $0.500 $2.000 $1.250 $0.520
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 126.000 $3.800 $3.500 $5.000 $9.600 $9.500 $7.500 $5.250 $9.970
BIODEG EROSN CONT LOGS (REMOVE)
LF 126.000 $0.800 $1.100 $1.000 $1.000 $1.000 $2.000 $1.250 $1.050
CONC CURB (TY I)
LF 26.000 $30.000 $30.000 $53.000 $26.000 $70.000 $25.000 $164.500 $188.670
CONC SIDEWALKS (4")
SY 26.000 $125.000 $70.000 $135.000 $93.500 $98.000 $90.000 $298.250 $102.510
CURB RAMPS (TY 1)
EA 4.000 $3,250.000 $1,900.000 $2,625.000 $2,900.000 $3,200.000 $2,800.000 $2,421.750 $2,943.500
CURB RAMPS (TY 7)
EA 2.000 $3,250.000 $1,900.000 $2,625.000 $3,150.000 $3,200.000 $3,050.000 $3,267.000 $2,943.500
MTL W-BEAM GD FEN (TIM POST)
LF 225.000 $28.500 $30.000 $35.000 $30.500 $28.750 $29.500 $31.500 $28.750
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,200.000 $1,800.000 $1,800.000 $1,400.000 $1,575.000 $1,350.000 $1,546.750 $1,409.880
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $2.240 $3.000 $3.000 $2.500 $2.800 $2.500 $3.500 $3.150
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 3.000 $200.000 $275.000 $385.000 $310.000 $135.000 $300.000 $230.250 $209.960
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,725.000 $3,300.000 $3,500.000 $4,000.000 $3,875.000 $3,850.000 $4,659.000 $4,246.440
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $250.000 $360.000 $250.000 $210.000 $150.000 $200.000 $288.000 $262.450
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $1,175.000 $730.000 $635.000 $810.000 $865.000 $650.000 $748.750 $745.360
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $1,375.000 $810.000 $745.000 $880.000 $1,175.000 $788.000 $907.250 $992.060
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 2.000 $650.000 $860.000 $695.000 $805.600 $790.000 $738.000 $849.750 $797.850
REMOVE SM RD SN SUP&AM
EA 13.000 $99.800 $115.000 $88.000 $80.600 $95.000 $88.000 $101.250 $142.130
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 4.000 $28.000 $36.000 $65.000 $40.280 $17.000 $21.000 $24.250 $60.360
INSTL OM SM RD SIGN (1-OM-PW)Y
EA 13.000 $31.580 $37.000 $65.000 $20.500 $55.000 $65.000 $74.750 $57.740
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,528.000 $0.220 $0.250 $0.520 $0.470 $1.250 $1.500 $1.750 $1.720
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 4,018.000 $0.130 $0.250 $0.520 $0.480 $1.250 $1.500 $1.750 $1.720
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,293.000 $9.880 $7.500 $7.370 $7.850 $7.000 $7.370 $8.500 $7.350
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 3.000 $475.000 $140.000 $137.000 $156.070 $170.000 $137.000 $157.750 $178.470
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 3.000 $500.000 $160.000 $157.000 $196.350 $175.000 $157.000 $180.750 $183.710
PAVEMENT SLER 6"
LF 41,818.000 $0.180 $0.250 $0.210 $0.280 $0.300 $0.210 $0.250 $0.310
PAVEMENT SLER 24"
LF 1,293.000 $0.700 $3.250 $3.000 $2.770 $0.750 $3.000 $3.500 $0.790
PAVEMENT SLER (ARROW)
EA 3.000 $75.000 $58.000 $57.000 $98.680 $25.000 $57.000 $65.750 $26.240
PAVEMENT SLER (WORD)
EA 3.000 $75.000 $79.000 $77.000 $115.800 $25.000 $77.000 $88.750 $26.240
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 4,618.000 $0.550 $0.650 $0.620 $0.780 $0.550 $0.620 $0.750 $0.580
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 17,538.000 $0.530 $0.580 $0.550 $0.680 $0.540 $0.550 $0.750 $0.570
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 19,572.000 $0.530 $0.580 $0.550 $0.670 $0.540 $0.550 $0.750 $0.570
REFL PAV MRKR TY I-C
EA 232.000 $5.870 $3.300 $3.220 $5.000 $4.000 $3.220 $3.750 $4.200
REFL PAV MRKR TY II-A-A
EA 549.000 $5.950 $3.300 $3.220 $5.000 $4.000 $3.220 $3.750 $4.200
UNDERSEAL COURSE
GAL 11,557.000 $0.610 $5.500 $5.500 $2.970 $3.850 $10.400 $5.250 $5.430
ADJUST VALVE BOX
EA 2.000 $1,120.000 $1,100.000 $400.000 $1,510.000 $1,075.000 $1,500.000 $2,760.750 $1,824.580
EXISTING MANHOLE ADJUSTMENTS
EA 2.000 $1,120.000 $1,500.000 $300.000 $4,800.000 $2,100.000 $4,750.000 $4,000.500 $2,506.840
Totals: $1,278,676.580 $1,105,676.650 $1,182,288.640 $1,204,051.080 $1,383,694.350 $1,459,000.870 $1,499,609.000 $1,710,602.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,800.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $29,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
Total: $32,800.00