Show Job Controls
Bid Cobra

BEXAR IH 35 (0017-09-114)

Items: 67

County: BEXAR
Length: 2.8760 MILES
Highway: IH 35
District: SAN ANTONIO
Control Number: 0017-09-114
DBE Goal: 0.0%
Project: C 17-9-114
Guaranty: $75,000.00
Time: 69 WORKING DAYS
Engineer's Estimate: $3,256,890.74
Date: 10/09/2025 (8 months ago)
Contract Number: 10253212
Type: RESURFACE ROADWAY
Project ID: A00187185
Project Description: SPOT BASE REPAIR, OVERLAY AND PAVEMENT MARKINGS ON FRONTAGE ROADS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CARLOS ARCILA
DANNY GALLEGOS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$3,256,890.74
$2,846,601.58
Over/Under Est: -12.6% -$410,289.16
Over/Under Est: -12.52% -$407,788.24
Amt Left: 0.09% $2,500.92
Over/Under Est: -10.5% -$342,088.10
Amt Left: 2.4% $68,201.06
Delta: -2.31% -$65,700.14
Over/Under Est: 6.36% $207,274.74
Amt Left: 21.69% $617,563.90
Delta: -18.85% -$549,362.84
Over/Under Est: 16.83% $548,229.76
Amt Left: 33.67% $958,518.92
Delta: -9.84% -$340,955.02

Bid Items & Bid Tabulations

67 Total 0 of 67
BEXAR  |  IH 35  |  SAN ANTONIO  |  0017-09-114  |  10/09/2025  |  $3,256,890.74  |  C 17-9-114  |  RESURF ROADWAY  |  69 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
DEAN WORD COMPANY, LTD.
CLARK CONSTRUCTION OF TEXAS, INC.
LONE STAR PAVING COMPANY
HUNTER INDUSTRIES, LTD.
REMOV CONC (MOWSTRIP)
LF 540.000 $29.000 $12.000 $6.700 $15.000 $6.000 $14.300
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 504.000 $110.000 $90.000 $149.000 $108.730 $168.000 $113.300
SP MIXES SP-C SAC-B PG76-22
TON 15,593.000 $88.280 $90.500 $91.800 $92.930 $110.000 $108.900
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 17,109.000 $26.250 $31.500 $28.100 $33.060 $40.000 $42.590
PLANE ASPH CONC PAV(0" TO 3")
SY 8,125.000 $3.600 $2.000 $3.000 $0.500 $1.850 $3.300
PLANE ASPH CONC PAV(2")
SY 129,945.000 $1.950 $1.600 $1.300 $1.370 $2.100 $2.200
RIPRAP (CONC)(4 IN)
CY 111.000 $676.070 $590.000 $464.800 $585.000 $635.000 $720.000
RIPRAP (MOW STRIP)(4 IN)
CY 23.000 $737.700 $605.000 $748.900 $600.000 $675.000 $740.000
ADJUSTING MANHOLES
EA 3.000 $2,625.000 $850.000 $776.500 $1,000.000 $3,000.000 $2,500.000
ADJUSTING MANHOLES (UTILITY VALVE)
EA 2.000 $450.000 $500.000 $804.200 $485.000 $2,000.000 $1,800.000
MOBILIZATION
LS 1.000 $352,244.880 $75,000.000 $62,500.000 $50,000.000 $130,723.750 $315,872.680
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $10,000.000 $4,500.000 $11,800.000 $2,100.000 $2,544.000 $6,302.270
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 138.000 $100.000 $50.000 $90.000 $100.000 $45.100 $81.190
TMA (STATIONARY)
DAY 41.000 $370.000 $50.000 $420.300 $100.000 $100.000 $162.380
TMA (MOBILE OPERATION)
DAY 156.000 $100.000 $10.000 $10.000 $100.000 $100.000 $270.630
TEMP SEDMT CONT FENCE (INSTALL)
LF 700.000 $5.000 $5.000 $3.900 $3.500 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 700.000 $2.000 $1.000 $0.600 $0.500 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 266.000 $7.500 $12.000 $7.000 $6.300 $5.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 266.000 $1.000 $1.000 $1.100 $1.000 $2.000 $1.000
CURB RAMPS (TY 1)
EA 10.000 $2,400.000 $2,970.000 $2,329.900 $2,500.000 $2,100.000 $2,400.000
CURB RAMPS (TY 2)
EA 8.000 $2,600.000 $3,105.000 $2,440.900 $2,500.000 $2,200.000 $2,500.000
CURB RAMPS (TY 3)
EA 5.000 $2,700.000 $3,460.000 $2,551.800 $2,500.000 $2,300.000 $2,600.000
CURB RAMPS (TY 5)
EA 3.000 $4,000.000 $3,100.000 $3,661.300 $3,000.000 $3,300.000 $3,600.000
CURB RAMPS (TY 7)
EA 2.000 $2,500.000 $3,100.000 $2,884.700 $2,500.000 $2,600.000 $2,900.000
CURB RAMPS (TY 10)
EA 1.000 $2,700.000 $3,400.000 $2,773.700 $2,500.000 $2,500.000 $2,800.000
MTL W-BEAM GD FEN (TIM POST)
LF 540.000 $40.000 $28.300 $20.000 $35.000 $27.000 $27.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,500.000 $1,160.000 $1,442.300 $1,500.000 $1,600.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 540.000 $13.200 $3.000 $2.800 $3.000 $3.500 $3.500
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $300.000 $220.000 $277.400 $225.000 $655.000 $655.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $3,305.000 $3,328.500 $3,200.000 $3,300.000 $3,300.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $315.000 $330.000 $277.400 $250.000 $450.000 $450.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 29.000 $832.250 $665.000 $614.700 $700.000 $798.000 $665.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 40.000 $945.000 $800.000 $726.700 $800.000 $850.000 $800.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 3.000 $1,450.000 $1,140.000 $1,381.300 $800.000 $1,207.000 $1,140.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $1,147.750 $1,020.000 $971.900 $1,000.000 $1,110.000 $1,020.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 14.000 $1,125.000 $1,205.000 $938.600 $1,250.000 $1,205.000 $1,205.000
REMOVE SM RD SN SUP&AM
EA 92.000 $100.000 $100.000 $83.200 $120.000 $115.000 $100.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 6,802.000 $3.500 $1.150 $1.300 $0.770 $1.000 $1.630
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 214.000 $2.000 $1.150 $2.200 $1.000 $1.000 $1.630
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 320.000 $1.000 $1.000 $1.100 $1.250 $1.000 $1.500
REFL PAV MRK TY I (W)8"(LNDP)(100MIL)
LF 99.000 $1.600 $2.000 $2.200 $2.500 $2.000 $0.750
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 16,435.000 $1.100 $0.850 $0.900 $0.950 $0.850 $0.950
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 3,211.000 $5.900 $6.350 $7.100 $7.000 $6.350 $7.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 49.000 $125.000 $140.000 $155.300 $125.000 $140.000 $125.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 19.000 $161.100 $188.000 $208.600 $250.000 $188.000 $155.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 7.000 $180.000 $200.000 $221.900 $225.000 $200.000 $155.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 53.000 $175.000 $155.000 $172.000 $175.000 $155.000 $135.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 8.000 $325.000 $299.000 $331.700 $625.000 $299.000 $550.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 23.000 $50.000 $40.000 $44.400 $20.000 $40.000 $40.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 1,905.000 $1.000 $0.890 $1.000 $0.950 $0.890 $0.950
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 561.000 $5.900 $6.690 $7.400 $7.000 $6.690 $7.500
PAVEMENT SLER 4"
LF 320.000 $0.250 $0.150 $0.200 $0.200 $0.150 $0.300
PAVEMENT SLER 6"
LF 50,160.000 $0.400 $0.160 $0.200 $0.200 $0.160 $0.350
PAVEMENT SLER 8"
LF 18,439.000 $0.400 $0.160 $0.200 $0.300 $0.160 $0.450
PAVEMENT SLER 24"
LF 3,772.000 $2.600 $1.000 $1.100 $3.000 $1.000 $2.250
PAVEMENT SLER (ARROW)
EA 49.000 $63.300 $15.000 $16.600 $75.000 $15.000 $60.000
PAVEMENT SLER (WORD)
EA 53.000 $68.300 $15.000 $16.600 $85.000 $15.000 $60.000
PAVEMENT SLER (DBL ARROW)
EA 19.000 $80.000 $20.000 $22.200 $120.000 $20.000 $65.000
PAVEMENT SLER (UTURN ARROW)
EA 7.000 $105.000 $20.000 $22.200 $110.000 $20.000 $70.000
PAVEMENT SLER (RR XING)
EA 8.000 $200.000 $30.000 $33.300 $250.000 $30.000 $175.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 12,120.000 $0.750 $0.550 $0.600 $0.550 $0.550 $0.650
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 5,935.000 $0.750 $0.550 $0.600 $0.550 $0.550 $0.600
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 32,105.000 $0.750 $0.550 $0.600 $0.550 $0.550 $0.600
REFL PAV MRKR TY I-C
EA 456.000 $6.200 $3.790 $4.200 $5.000 $3.790 $5.500
REFL PAV MRKR TY II-A-A
EA 267.000 $6.200 $3.790 $4.200 $5.000 $3.790 $4.500
REFL PAV MRKR TY II-C-R
EA 1,157.000 $5.000 $3.790 $4.200 $5.000 $3.790 $4.500
UNDERSEAL COURSE
GAL 25,990.000 $4.290 $3.300 $4.300 $4.500 $3.500 $4.420
Totals: $3,256,890.740 $2,846,601.580 $2,849,102.500 $2,914,802.640 $3,464,165.480 $3,805,120.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $95,850.00
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $8,250.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $2,500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $107,600.00